Petitions Status
As on 31/10/2019
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
1
385/MP/2019
REFEX ENERGY LIMITED (REL)
PETITION UNDER SECTION 129, 142, 79 AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 AND THE PROVISIONS OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (PROCEDURE, TERMS AND CONDITIONS FOR GRANT OF TRADING LICENCE AND OTHER RELATED MATTERS) REGULATIONS, 2009 FOR VIOLATION OF THE TERMS AND CONDITIONS OF THE LICENSE AND THE AGREEMENTS ENTERED INTO BETWEEN THE PARTIES FOR NON-PAYMENT OF DUES TO THE SELLER IN TRADING TRANSACTIONS.
Hearing
87/IA/2019
2
384/MP/2019
NER II Transmission Limited nerii
Petition for approval for creation of security interest under Sections 17(3) & 17(4) of Electricity Act, 2003 over Petitioner No. 1?s Assets in favour of Catalyst Trusteeship Limited for the benefit of Lenders and their assignees, transferees, novatees for the purpose of Petitioner No. 1?s Transmission Project
Preliminary Scrutiny
 
3
383/TT/2019
Torrent Power Grid Ltd (TPGL)
Truing-up of capital cost for the period from 01-Apr-2014 to 31-Mar-2019 and Determination of transmission tariff for the period from 01-Apr-2019 to 31-Mar-2024 for Transmission system constructed, maintained and operated by Torrent Power Grid Ltd vide License No. 2/Transmission/CERC dated 16.05.2007
Preliminary Scrutiny
 
4
382/AT/2019
SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
Petition under Section 63 of the Electricity Act, 2003 for Adoption of Tariff for the 480 MW Wind Power Projects (Tranche-VII) connected to the Inter-State Transmission System (ISTS) and selected through Competitive Bidding Process as per the Guidelines issued by Ministry of Power on 08.12.2017
Preliminary Scrutiny
 
5
381/MP/2019
West Bengal State Electricity Distribution Company Limited WBSEDCL
Petition under Section 79 of the Electricity Act, 2003 and the PPA dated 25.03.2011 between Adhunik Power and Natural Resources Ltd. and PTC India Ltd. with a back to back PSA dated 05.01.2011 between PTC India Ltd. and West Bengal State Electricity Distribution Company Ltd.
Preliminary Scrutiny
 
6
380/MP/2019
ODISHA POWER GENERATION CORPORATION LIMITED (OPGC)
Petition under Sections 29(5), 79(1)(c) and 79(1)(k) of the Electricity Act, 2003 read with Regulations 6.4.2(c)(iii), 7(1) and 7(3) of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 seeking directions for shifting of Control Area from Eastern Load Despatch Centre to Odisha State Load Despatch Centre and operating the bus coupler between Petitioner's 2 x 660 MW Units (viz. Units 3 and 4) in closed condition for the common bus mode operation.
Hearing
83/IA/2019
7
379/AT/2019
SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
Petition under Section 63 of the Electricity Act, 2003 for Adoption of Tariff for the 1200 MW Wind Power Projects (Tranche-V) connected to the Inter-State Transmission System (ISTS) and selected through Competitive Bidding Process as per the Guidelines issued by Ministry of Power on 08.12.2017
Preliminary Scrutiny
 
8
378/MP/2019
SOUTHERN REGIONAL LOAD DESPATCH CENTRE (SRLDC)
Application filed under subsection (4) of section 28 of Electricity Act 2003 and Regulation 10 of the Central Electricity Regulatory Commission (Fee and Charges of Regional Load Despatch Centre and other related matters) Regulations, 2019 for determining the SRLDC Charges for the control period 01.04.2019-31.03.2024.
Preliminary Scrutiny
 
9
377/MP/2019
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 10 of the Power Purchase Agreement dated 19.08.2013 entered into between the Petitioner and the Respondents, seeking approval of the cost to be incurred by the Petitioner on account of change in law, for installation/retrofit of �Electrostatic Precipitators� (ESP), installation of Flue Gas Desulphurisation (FGD), installation of low NOx burners, providing Over Fire Air (OFA) and any other measures for compliance of the notification dated 07.12.2015 issued by the Ministry of Environment, Forests and Climate Change, Government of India in respect of Thermal Power Plants installed/commissioned after 01.01.2003 and before 31.12.2016.
Preliminary Scrutiny
 
10
376/MP/2019
North Eastern Regional Load Despatch Centre NERLDC
Application filed under subsection (4) of section 28 of Electricity Act 2003 and Regulation 10 of the Central Electricity Regulatory Commission (Fee and Charges of Regional Load Despatch Centre and other related matters) Regulations, 2019 for determining the NERLDC Charges for the control period 01.04.2019-31.03.2024.
Preliminary Scrutiny
 
11
375/MP/2019
Power System Operation Corporation Ltd (POSOCO)
Application filed under subsection (4) of section 28 of Electricity Act 2003 and Regulation 10 of the Central Electricity Regulatory Commission (Fee and Charges of Regional Load Despatch Centre and other related matters) Regulations, 2019 for determining the NLDC Charges for the control period 01.04.2019-31.03.2024.
Preliminary Scrutiny
 
12
374/MP/2019
Northern Regional Load Desptach Centre (NRLDC)
Application filed under subsection (4) of section 28 of Electricity Act 2003 and Regulation 10 of the Central Electricity Regulatory Commission (Fee and Charges of Regional Load Despatch Centre and other related matters) Regulations, 2019 for determining the NRLDC Charges for the control period 01.04.2019-31.03.2024.
Preliminary Scrutiny
 
13
373/MP/2019
SB ENERGY FOUR PRIVATE LIMITED (SBEFPL)
Petition seeking change in law relief on account of imposition of safeguard duty on import of solar cells and modules
Preliminary Scrutiny
 
14
372/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act, 2003 read with related provisions of the Chapter-5 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 6(1), 6(2) & 6(3), chapter-3) of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations,2014 for revision of  tariff for the period 01.04.2014 to 31.03.2019 carrying out truing up exercise for the period 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period  of 2014-15 to 2018-19 in respect of  Kopili (Stage-II) Hydro Electric Plant (1 X 25 =25 MW) of North Eastern Electric Power Corporation Limited (NEEPCO LTD), Shillong.
Preliminary Scrutiny
 
15
371/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act, 2003 read with related provisions of the Chapter-5 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 6(1), 6(2) & 6(3), chapter-3) of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations,2014 for revision of  tariff for the period 01.04.2014 to 31.03.2019 carrying out truing up exercise for the period 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period  of 2014-15 to 2018-19 in respect of  Khandong Hydro Electric Plant (2 X 25 =50 MW) of North Eastern Electric Power Corporation Limited (NEEPCO LTD), Shillong.
Preliminary Scrutiny
 
16
370/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act, 2003 read with related provisions of the Chapter-5 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 6 of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations , 2014 for revision of  tariff for the period 01.04.2014 to 31.03.2019 carrying out truing up exercise for the period 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period  of 2014-15 to 2018-19 in respect of  Kopili Hydro Electric Plant (4 X 50 =200 MW) of North Eastern Electric Power Corporation Limited (NEEPCO), Shillong.
Preliminary Scrutiny
 
17
369/AT/2019
SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
PETITION UNDER SECTION 63 OF THE ELECTRICITY ACT, 2003 FOR ADOPTION OF TARIFF FOR THE 1000 MW WIND POWER PROJECTS (TRANCHE-II) CONNECTED TO THE INTER-STATE TRANSMISSION SYSTEM (ISTS) AND SELECTED THROUGH COMPETITIVE BIDDING PROCESS AS PER THE GUIDELINES ISSUED BY MNRE ON 04.05.2017
Preliminary Scrutiny
 
18
368/GT/2019
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 along with ?CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2017? for determination of project specific levelised tariff for100 MW floating solar Photo Voltaic Plant at water reservoir  of Ramagundam Super Thermal Power Station (RSTPS), Ramagundam, Telangana.
Preliminary Scrutiny
 
19
367/MP/2019
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
Petition under Section 79 of the Electricity Act, 2003 for execution of Order dated 30.04.2019 read with corrigendum dated 29.05.2019 passed in Petition No. 255/MP/2017; and initiation of proceedings/ appropriate action under Section 142 read with Section 149 of the Electricity Act, 2003 and Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 against the Respondents for non-compliance of the Order dated 30.04.2019 read with corrigendum dated 29.05.2019 passed by the Commission in Petition No. 255/MP/2017
Preliminary Scrutiny
 
20
366/MP/2019
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 10 of the Power Purchase Agreements both dated 01.11.2013 entered into between the Petitioner and the Respondents, seeking approval of the cost to be incurred by the Petitioner on account of change in law, for installation/retrofit of �Electrostatic Precipitators� (ESP), installation of Flue Gas Desulphurisation (FGD), installation of low NOx burners, providing Over Fire Air (OFA) and any other measures for compliance of the notification dated 07.12.2015 issued by the Ministry of Environment, Forests and Climate Change, Government of India in respect of Thermal Power Plants installed/commissioned after 01.01.2003 and before 31.12.2016.
Preliminary Scrutiny
 
21
365/MP/2019
MAHINDRA RENEWABLES PRIVATE LIMITED (MRPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 for (i) declaration  of ?Change in Law? event; and (ii) grant of consequential relief to compensate for the increase in capital cost due to introduction and imposition of Safe Guard Duty by way of  Notification No.01/2018- Customs SG dated 30.07.2018 issued by the Department of Revenue, Ministry of Finance, in terms of Article 17 of the power purchase agreement dated 17.04.2017 between Mahindra Renewables Private Limited and M.P. Power Management Company Limited and power purchase agreement dated 17.04.2017 between Mahindra Renewables Private Limited and Delhi Metro Rail Corporation.
Preliminary Scrutiny
 
22
364/MP/2019
NLC Tamilnadu Power Ltd (NTPL)
Increase in Operation and Maintenance expenses incurred by NLC TAMILNADU POWER LIMITED (NTPL) on account of Pay/Wage Revision to Executives wef 01.01.2017, Non Executives & workmen wef 01.01.2017 & CISF wef 01.01.2016 posted to NLC TAMILNADU POWER LIMITED (NTPL) and other hikes like gratuity ceiling increase & GST impact etc. and to allow the recovery of the same from the beneficiaries of NLC TAMILNADU POWER LIMITED (NTPL) Power Station for the period 01.04.2014 to 31.03.2019
Preliminary Scrutiny
 
23
363/MP/2019
JHAJJAR POWER LIMITED (JPL)
Petition under Section 79(1) (f) of the Electricity Act, 2003 and Article 18 of the PPA dated 07.08.2008 for approval of the amendment of the PPA.
Preliminary Scrutiny
 
24
362/TT/2019
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
Determination of Tariff for the year 2018-19 in respect of RVPN owned transmission lines/system connecting with other States and Intervening transmission lines incidental to inter-State transmission of electricity for Inclusion in the POC transmission charges in accordance with the CERC (Terms and Condition of Tariff) Regulation 2014 and CERC (Sharing of Transmission Charges and Losses) Regulation, 2010 and its subsequent amendments.
Preliminary Scrutiny
 
25
361/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For Special Protection Scheme for Rihand- Dadri HVDC Bi-pole and Gorakhpur-Muzzafarpur 400 kV line in Northern Region
Preliminary Scrutiny
 
26
360/MP/2019
Jyoti Solar Solutions Private Limited (jyotisolar)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 08.02.2017, with effective date of 22.12.2016, executed between the Petitioner and Solar Energy Corporation of India Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
 
27
359/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

For 220 kV D/C Anta Transmission System in Northern Region.
Preliminary Scrutiny
 
28
358/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for Series Compensation on Panki- Muradnagar 400 KV S/C line of UPPCL in Northern Region
Preliminary Scrutiny
 
29
357/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For 2nd 400 kV D/C Kahalgaon-Biharshariff transmission line in Eastern Region.
Preliminary Scrutiny
 
30
356/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For LILO of one circuit of 132 kV D/C Siliguri-Rangit transmission line at Gangtok in Eastern Region.
Preliminary Scrutiny
 
31
355/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For 2nd 315 (3 x 105) MVA, 400/220 kV transformer at Indravati (OHPC) Switchyard in Eastern Region.
Preliminary Scrutiny
 
32
354/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

     For LILO of both the circuit of Patratu-Hatia-Chandil 220kV D/C line at Ranchi Sub-Station associated with 220kV Interconnection with Jharkhand State Electricity Board (JSEB) system at Ranchi Sub-Station in Eastern Region.
Preliminary Scrutiny
 
33
353/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For Asset-a: 220 kVAllahabad-Rewa Road D/C Transmission line Ckt-1, Asset-b: 220 kV Allahabad-Rewa RoadD/C Transmission line Ckt-II, Asset-c: LILO of 220 kV Modipuram � Nara transmission line, Asset-d: LILO of 220 kV Modipuram-Simbholi transmission line, Asset-e: 220 kV Allahabad-Phulpur S/C transmission line and Asset-f: 220 kV S/C Meerut-Shatabdinagar transmission line under transmission system associated with 220 kV System Strengthening Scheme in UP in Northern Region.
Preliminary Scrutiny
 
34
352/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for 132 kV S/C Mau-Balia Transmission System in Northern Region
Preliminary Scrutiny
 
35
351/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

       for 315 MVA ICT-III at Nagarjunasagar sub-station with associated bay equipments in Southern Region.
Preliminary Scrutiny
 
36
350/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

for SPECIAL ENERGY METERS IN SOUTHERN REGION
Preliminary Scrutiny
 
37
349/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations?  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

For 2nd Spare Converter Transformers at Kolar and Talcher of Talcher-Kolar HVDC Link in Southern Region
Preliminary Scrutiny
 
38
348/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 and CERC (Terms and Conditions of Tariff) Regulations� 2019 for  

(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

       for assets under WRSS VII.
Preliminary Scrutiny
 
39
347/MP/2019
Meenakshi Energy Private Limited (MEPL)
Petition under Section 79 (1) (f) along with Section 79 (1) (k) of Electricity Act, 2003 read with Regulation 8 (7) of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-Term Access and Medium Term Open Access in Inter-State Transmission and Related Matters) Regulations, 2009 seeking permission  for extension of the period for injection of infirm power for commissioning and testing of phase II (unit III) thermal power project of Meenakshi Energy Limited near Thaminapatnam, Chilakur (Mandalam), SPSR Nellore, State of Andhra Pradesh for further period of six months i.e. from 01.07.2019 to 31.12.2019.
Hearing
 
40
346/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for Asset 1- 2 Nos. 765 kV line bays at 765/400kV Bilaspur Pooling Station(POWERGRID) (for Bilaspur PS (PG)-Rajnandgaon(TBCB) 765kV D/c line) alongwith 2 Nos. 240MVAR, 765kV switchable line Reactors at 765/400kV Bilaspur Pooling Station end under ?POWERGRID Works associated with Additional System Strengthening for Sipat STPS? in Western Region.
Preliminary Scrutiny
 
41
345/AT/2019
Bikaner - Khetri Transmission Limited (BKTL)
Application under Section-63 of the Electricity Act, 2003 for Adoption of Transmission Charges with respect to the Transmission System being established by Bikaner � Khetri Transmission Limited
Preliminary Scrutiny
 
42
344/TL/2019
Bikaner - Khetri Transmission Limited (BKTL)
Application for Grant of Transmission License under Sec 14 of Electricity Act 2003
Preliminary Scrutiny
 
43
10/SM/2019
Suo Motu
Methodology for Compilation of Coal Price Index applicable for Power Sector
Preliminary Scrutiny
 
44
343/MP/2019
NHPC LTD
Petition under section 79 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 12 & 13 of CERC (Terms & Conditions of Tariff) Regulations, 2004, Regulation 44 of CERC (Terms & Conditions of Tariff) Regulations, 2009 & Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of pay regularization of below board level executives of NHPC Limited for the period 01.01.2007 to 31.03.2019.
Preliminary Scrutiny
 
45
342/MP/2019
Prayatna Developers Private Limited (PDPL)
Petition invoking Regulation 1.5(iv) read with Regulation 5.2(u) and Regulation 6.5(11) of the CERC (Indian Electricity Grid Code) Regulations, 2010 for enforcement of �must run� status granted to solar power project and Regulation 111 of the CERC (Conduct of Business) Regulations, 1999 seeking direction to State Load Dispatch Centre to stop issuing backing down instructions to the Petitioner.
Hearing
 
46
341/GT/2019
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 along with �CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2017� for determination of project specific levelised tariff for 92 MW floating solar Photo Voltaic Plants in two phases (first phase 22 MW and second phase 70 MW) at Rajiv Gandhi Combined Cycle Power Project (RGCCP), Kayamkulam, Kerala.
Preliminary Scrutiny
 
47
340/AT/2019
PTC India Limited PTC
Petition under Section 63 of the Electricity Act, 2003 for adoption of tariff for the scheme for setting up of 1000 MW inter-state transmission system (ISTS) connected wind power selected through competitive bidding process as per guidelines issued by ministry of new and renewable energy (MNRE) on 14.06.2016 and 22.10.2016.
Hearing
 
48
339/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for  220 kV Jallandhar-Hamirpur D/C transmission line along with Associated bays in Northern Region.
Preliminary Scrutiny
 
49
338/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for 400 kV D/C Kaiga-Sirsi transmission line in Southern Region
Preliminary Scrutiny
 
50
337/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for LILO of 220 kV S/C Panki-Naubasta transmission line at Kanpur in Northern Region.
Preliminary Scrutiny
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
51
336/AT/2019
UDUPI KASARGODE TRANSMISSION LIMITED UKTL
Application under Section 63 of the Electricity Act, 2003 for Adoption of Transmission Charges
Preliminary Scrutiny
 
52
335/TL/2019
UDUPI KASARGODE TRANSMISSION LIMITED UKTL
Application under Sections 14, 15 and 79(1)(e) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations, 2009 with respect to Grant of Transmission License to Udupi Kasargode Transmission Limited.
Preliminary Scrutiny
 
53
9/SM/2019
Suo Motu
Non-compliance of the directions of this Hon'ble Commission in the judgment & order dated 09.08.2019 passed in Petition No. 393/MP/2018.
Preliminary Scrutiny
 
54
20/RP/2019 in 23/MP/2019
Rajasthan Urja Vikas Nigam Limited (RUVNL)
Petition for Review under Section 94(1)(f) read with Regulation 103 (1) of the CERC (Conduct of Business) Regulations 1999 of Order dated 09.08.2019 of the Central Electricity Regulatory Commission in Petition no.23/MP/2019 with regard to grant of regulatory approval for execution of transmission system for solar energy zones in Rajasthan.
Order reserved
 
55
334/MP/2019
EASTERN REGIONAL LOAD DESPATCH CENTRE (ERLDC)
Petition for Non-compliance of Section 29 of the Electricity Act, 2003 ,Regulations 2.3.1(5),2.3.1(6) and 2.3.1(7) of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 and Regulation 8 (6) of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and Regulation 6 and Regulation 8 of the Central Electricity Authority (Grid Standards) Regulations, 2010 with Regulation  1.5 of Indian Electricity Grid Code, section 29(6) and section 142 of the Electricity Act,2003.
Hearing
 
56
333/MP/2019
POWERGRID NM Transmission Limited (PNMTL)
Petition under Sections 63 and 79 (1) (c) and (d) of the Electricity Act, 2003 read with Regulation 86 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for allowing time overrun and cost overrun and the Approval of increase in tariff adopted for Nagapattinam � Salem � Madhugiri Transmission System on account of force majeure and Change in Law events.
Preliminary Scrutiny
 
57
332/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For LILO of Siliguri- Gangtok section of 132 kV Rangit-Siliguri transmission line at Melli under Integration of Sikkim Transmission system in Eastern Region.
Preliminary Scrutiny
 
58
330/MP/2019
ACME Solar Holdings Ltd. (ASHL)
Seeking quashing of letters dated 02.07.2019 and 27.09.2019 issued by PGCIL and seeking declaration that Petitioners are not required to open Letter of Credit
Hearing
 
59
329/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act,2003 read with related provisions of the Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations,1999 and the Central Electricity Regulatory Commission (Procedure for tariff Determination) Regulations,2014 for revision of tariff for the period 30.10.2017 to 31.03.2019 carrying out truing up exercise for the period of 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period of 30.10.2017 to 31.03.2019 in respect of Tuirial hydro Electric Power Plant (60 MW) of  North Eastern Electric Power Corporation Limited (NEEPCO), Shillong.
Preliminary Scrutiny
 
60
328/TD/2019
Amplus Energy Solutions Private Limited
Application for Surrender of Inter State Trading License Cat II( NO 77/ Trading License )
Preliminary Scrutiny
 
61
327/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

Combined 07 Nos of Assets under ERSS II Project
Preliminary Scrutiny
 
62
326/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
(i) Revision of Transmission Tariff for 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

     For combined Assets (i) Tala ? Siliguri Transmission System and (ii) Remaining part of Tala -Siliguri transmission System in Eastern Region
Preliminary Scrutiny
 
63
325/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 and CERC (Terms and Conditions of Tariff) Regulations? 2019 for  

(i) Revision of Transmission Tariff for 2004-09 and 2009-14 tariff block
(ii) Truing up of Transmission tariff for 2014-19 tariff block and 
(iii) Determination of Transmission tariff for 2019-24 tariff block 

for (a) LILO of N'Sagar - Raichur 400 kV S/c at Mehboobnagar & (b) LILO of both circuits of Nellore - Sriperumbudur 400 kV D/c at Alamatti under System Strengthening-IV in Southern Region
Preliminary Scrutiny
 
64
324/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For Farakka-Malda Transmission Link and Additional 315 MVA Transformer at Malda in Eastern Region.
Preliminary Scrutiny
 
65
323/MP/2019
Central Transmission Utility (CTU)
direct the Respondent to forthwith make payment towards late payment surcharge under the invoice dated 21.1.2019 issued by the Petitioner;
Preliminary Scrutiny
 
66
322/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Asset: 01 no. 160 MVA, 220/160 kV, 3-ph Transformer at Baripada (shifted to Purnea) (DOCO: 01.09.2013) under Provision of Spare ICTs and Reactors for Eastern, Northern, Southern and Western Regions.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
67
321/MP/2019
Essar Power Transmission Company Limited (EPTCL)
Modification of License in terms of CERC Order in 102/TT/2018
Preliminary Scrutiny
 
68
320/MP/2019
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014, read with regulation 44(8) and 44(7) of CERC (Terms and Conditions of Tariff) Regulation, 2019, for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2018-19 in respect of  Sewa-II Power Station.
Preliminary Scrutiny
 
69
319/MP/2019
DAMODAR VALLEY CORPORATION (DVC)
Disputes between DVC and BYPL in regard to appropriation of payments made by BYPL against dues of DVC
Preliminary Scrutiny
 
70
318/MP/2019
NER II Transmission Limited nerii
Petition under Section 79(1)(c), Section 18 and Section 17(3) of the Electricity Act, 2003, read with Regulation 19 of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of transmission Licence and other related matters) Regulations, 2009, and invoking all other enabling powers of the Hon?ble Central Electricity Regulatory Commission (?Hon?ble Commission?) permitting the amendment of the Transmission License dated 23.5.2017 (?Transmission License?) granted to the NER-II Transmission Limited (?Petitioner?/?NER-II?) for establishing Transmission System for NER System Strengthening Scheme-II (Part-B) and V, (NER-II B & V) on Build, Own, Operate and Maintain basis (?Project?) and accordingly allowing carving out of Silchar ? Misa 400 kV D/C (quad) transmission line from the purview of the aforesaid Transmission License and to vest the same in the favour of a separate entity i.e. Sterlite Grid 12 Limited (?Respondent No. 1?/ ?SGL12?).
Preliminary Scrutiny
 
71
317/MP/2019
Bharat Aluminium Company Limited (BALCO)
Petition under Section 79 (1)(b), 79 (1)(f) and 79 (1)(k) of the Electricity Act 2003, read with Articles 21.1.2 of the PPA dated 26.12.2014 executed between the Petitioner and the Respondent No. 1, seeking appropriate directions upon the Respondent No. 1/ KSEB for releasing the outstanding payment accrued in favour of the Petitioner on account of non-payment of the fixed charge and transmission losses in terms of the Power Purchase Agreement (PPA) dated 26.12.2014
Preliminary Scrutiny
 
72
316/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For 400 kV D/C Dhauliganga HEP � Bareilly (UPPCL) Transmission Line along with its associated bays at Bareilly(UPPCL) in Northern Region.
Preliminary Scrutiny
 
73
315/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for 400/220 KV Bhiwadi S/S along with LILO of Ballabhgarh-Bassi 400 KV S/C line and ICT-I & ICT-II at Bhiwadi in Northern Region.
Preliminary Scrutiny
 
74
314/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

For 400 kV S/C Chamera -1 Kishenpur transmission system in Northern Region
Preliminary Scrutiny
 
75
313/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

for Additional Converter Transformer (Spare) for Rihand-Dadri Bi-pole in Northern Region.
Preliminary Scrutiny
 
76
312/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For Transmission system associated with LOKTAK HEP in North Eastern Region (DOCO: 01.07.1983 to 01.07.1989).
Preliminary Scrutiny
 
77
311/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 and CERC (Terms and Conditions of Tariff) Regulations� 2019 for  
(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block
Preliminary Scrutiny
 
78
310/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 
for 400/220 kV, 1X315 MVA Autotransformer (ICT-III) at 400/220 kV substation at Vapi under installation of 1X315 MVA 400/220 kV Transformer at Vapi (POWERGRID) substation in WR.
Preliminary Scrutiny
 
79
308/MP/2019
Khargone Transmission Limited (KTL)
Petition under Section 63 and 79(1)(c) and 79(1)(f) of the Electricity Act, 2003 seeking an extension in the Scheduled Commercial Operation Date along with compensatory and declaratory relief under the Transmission Services Agreement dated 14.03.2016 on account of Force Majeure and Change in Law events.
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
80
307/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

For Spare Converter Transformer for Vizag back-to-back HVDC terminal in Southern Region (DOCO 01.01.2012).
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
81
306/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
400 kV D/C Bina ? Nagda Transmission Line along with associated bay equipment at Nagda and  Bina Substations under Transmission System associated with 400 kV Bina ? Nagda D/C Line in Western Region
Preliminary Scrutiny
 
82
305/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For combined asset of (i) 1x500 MW HVDC back to back station at Sasaram (DOCO 01.12.2002 and (ii) Associated AC Switchyard at Sasaram & Allahabad and auxiliary system including 400 kV Sarnath Allahabad line with associated bays etc (DOCO 01.12.2002) under Eastern Northern Inter-regional HVDC Transmission System in Eastern Region.
Hearing
 
83
304/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Bhadrawati-Chandrapur 400 kV D/C transmission line including bays at Bhadrawati (POWERGRID) Switching station(Extensions) and Chandrapur(MSEB) switchyard in Western Region
Preliminary Scrutiny
 
84
303/TL/2019
Khetri Transco Limited
Application under Section 14 of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations, 2009 with respect to Transmission License to Khetri Transco Limited
Preliminary Scrutiny
 
85
302/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For Hathidah River Crossing Section of 220 kV Biharsharif � Begusarai Transmission Line in Eastern Region.
Preliminary Scrutiny
 
86
301/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

  For Dehri-Karamnasa Transmission System in Eastern Region.
Hearing
 
87
300/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For 400 kV Biharsharif-Sasaram-Sarnath Transmission line along with associated bays under Eastern-Northern inters Regional HVDC Transmission system in Eastern Region.
Hearing
 
88
299/MP/2019
Sadipali Solar Private Limited Sadipalisolar
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 31.05.2017 executed between the Petitioner and Solar Energy Corporation of India Ltd., for seeing approval of Change in Law events due to enactment of the GST Laws
Hearing
 
89
298/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act, 2003 read with related provisions of the Chapter-5 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 8(1), 8(2) & 8(3)-chapter-3) of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations, 2014 for revision of  tariff for the period 01.04.2014 to 31.03.2019 carrying out truing up exercise for the period 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period  of 2014-15 to 2018-19 in respect of  Assam Gas Based Power Plant (GT 6 X 33.5 MW + ST 3X 30 MW=291 MW) of North Eastern Electric Power Corporation Limited (NEEPCO), Shillong
Preliminary Scrutiny
 
90
297/AT/2019
Khetri Transco Limited
Application under Section 63 of the Electricity Act, 2003 for Adoption of Transmission Charges with respect to the Transmission System being established by the Khetri Transco Limited(a 100% wholly owned subsidiary of Power Grid Corporation of India Limited)
Preliminary Scrutiny
 
91
296/MP/2019
LEXICON VANIJYA PVT. LTD. LEXICON
Petition under Section 79 (1) (b) and Section 79 (1) (f) of Electricity Act, 2003 for amendment of PPAs dated 27.01.2012 to align them with Regulation 15 of the RERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2017.
Preliminary Scrutiny
 
92
295/MP/2019
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014, read with regulation 44(8) and 44(7) of CERC (Terms and Conditions of Tariff) Regulation, 2019, for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2018-19 in respect of  Chamera-III Power Station.
Preliminary Scrutiny
 
93
294/MP/2019
NHPC LTD
Petition under Section 79(1) (f) of the Electricity Act, 2003 read with Regulation 54 & 55 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for adjudication of dispute between NHPC Ltd. & Punjab State Power Corporation Limited (PSPCL) regarding payment of ?Deferred Tax Liability Materialized? during FY 2017-18.
Preliminary Scrutiny
 
94
293/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act,2003 read with related provisions of the Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations,1999 and Regulation 8(1), 8(2) & 8(3) - (Chapter-3) of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,2014 for revision of tariff for the period 01.04.2014 to 31.03.2019 carrying out truing up exercise for the period of 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period of 2014-15 to 2018-19   in respect of  Doyang Hydro Electric Plant ( 75 MW) of North Eastern Electric Power Corporation Limited (NEEPCO), Shillong
Preliminary Scrutiny
 
95
292/MP/2019
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
Petition under Section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking compensation of carrying cost in respect of the Change in Law events allowed by this Hon�ble Commission under the Power Purchase Agreement dated 25.03.2011 (PPA) executed between the Petitioner and the Respondent No. 2 and the Power Supply Agreement (PSA) dated 05.01.2011 executed between Respondent No.1 and Respondent No. 2
Hearing
 
96
291/MP/2019
HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED (HPSEBL)
PETITION UNDER SECTION 79(1)(c) AND 79(1)(f) OF THE ELECTRICITY ACT, 2003, FOR REFUND OF AMOUNTS WRONGLY RECOVERED BY POWERGRID CORPORATION OF INDIA LIMITED UNDER POC CHARGES FOR THE ISTS LINES OPERATED AND MAINTAINED BY BBMB
Preliminary Scrutiny
 
97
290/GT/2019
NTPC Limited
Petition Under CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2017? for determination of project specific levelised tariff for 180 KW Varanasi WtE Station at Karsara, District Varanasi.
Preliminary Scrutiny
 
98
289/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

For Provision of Spare ICTs and Reactor for Southern Region.
Preliminary Scrutiny
 
99
288/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 
For LILO of 400 kV S/C Chamera -1 Kishenpur transmission line at Chamera-II under transmission system associated with Chamera HEP Stage � II Transmission System in Northern Region.
Hearing
 
100
287/MP/2019
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition invoking Regulation 1.5(iv) read with Regulation 5.2(u) and Regulation 6.5(11) of the CERC (Indian Electricity Grid Code) Regulations, 2010 for enforcement of ?must run? status granted to solar power projects and Regulation 111 of the CERC (Conduct of Business) Regulations, 1999 seeking direction to State Load Dispatch Centre to stop issuing backing down instructions to the Petitioners.
Preliminary Scrutiny
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
101
286/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Central Industrial Security Force (CISF) in Kishanganga Power Station during the period 18.05.2018 (COD of first Unit) to 31.03.2019.
Hearing
 
102
285/MP/2019
JHAJJAR POWER LIMITED (JPL)
Petition under Section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking approval of guidelines / mechanism for procurement of coal from alternate sources.
Preliminary Scrutiny
 
103
284/RC/2019
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION (TANGEDCO)
Petition under Section 79(1)(a) and 79(1)(b) of the Electricity Act, 2003 read with Regulation 8(6) of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014, and Regulation 111 to 113 & 115 of CERC ( Conduct of Business Regulations) 1999 seeking regulatory compliance of sharing of gains between generating company and the beneficiaries by NTPC in the monthly energy bills of the generating stations.
Preliminary Scrutiny
 
104
283/MP/2019
JHAJJAR POWER LIMITED (JPL)
Miscellaneous petition under section 79(1) (b) & (f) of the electricity act, 2003 read with clause 4.7 of the competitive bidding guidelines and article 13 of the power purchase agreements dated 07.08.2008 and 20.01.2009 entered into by jhajjar power limited with uttar haryana bijli vitran nigam limited,/ dakshin haryana bijli vitran nigam limited and tata power trading company limited respectively in relation to seeking compensation for decrease in revenues and increase in the costs as a result of �change in law� events.
Preliminary Scrutiny
 
105
19/RP/2019 in 269/MP/2018
HARYANA POWER PURCHASE CENTRE HPPC
Petition for review the order dated 08.07.2019 passed by this Hon�ble Commission in Petition No. 269/MP/2018
Preliminary Scrutiny
 
106
282/MP/2019
Aryan M.P. Power Generation Private Limited AMPPGPL
Petition under Section 142 of the Electricity Act, 2003 for non-compliance of the order dated 03.12.2018 passed in Petition No. 242/MP/2017 by Power Grid Corporation of India and for issuance of appropriate direction to Power Grid Corporation of India for payment of amount to be refunded after deduction of relinquishment charges from the encashed Bank Guarantee furnished by the Petitioner along with interest.
Preliminary Scrutiny
 
107
281/MP/2019
MYTRAH VAYU (SABARMATI) PRIVATE LIMITED (MVSPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 for (i) approval of �Change in Law�; and (ii) consequential relief to compensate for the increase in capital cost due to introduction of the Central Goods and Services Tax Act, 2017, the Integrated Goods and Services Tax Act, 2017 and the State Goods and Services Tax Acts enacted by respective states, in terms of Article 12 of the power purchase agreements dated 21.07.2017 between Mytrah Vayu (Sabarmati) Private Limited and PTC India Limited
Preliminary Scrutiny
 
108
280/MP/2019
EASTERN COALFIELDS LIMITED (ECL)
Reference from the Hon'ble High Court of Calcutta under Article 226 of Constitution of India in Writ Petition No. 17044 of 2015; Eastern Coalfields Limited & Anr. v/s Eastern Regional Power Committee and Others.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
109
279/MP/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Miscellaneous petition under Regulation 55, �Power to remove difficulties� and Regulation 54, "Power to Relax� of the CERC (Terms and Conditions of Tariff) Regulations, 2014, on account of additional cost incurred owing to revision of scale of pay for executives and non-executives from 1.1.2017 to 31.3.2019 consequent to implementation of pay revision and revision of gratuity amount with effect from 1.1.2017
Preliminary Scrutiny
 
110
278/MP/2019
ONGC Tripura Power Company (OTPC)
Miscellaneous Petition for Relaxation of Technical Minimum for OTPC Palatana Project as per IEGC (4th Amendment)
Preliminary Scrutiny
 
111
277/MP/2019
Sitac Kabini Renewables Private Limited (SitacKabini)
Petition under Section 79(1)(f) of the Electricity Act, 2003 for adjudication of dispute arising out of the action of Power Grid Corporation of India in revoking the Long-Term Open Access granted to the Petitioner for evacuation of 300MW power from its Wind Power Project on account of delay in submission of Bank Guarantee as required under the Long Term Access Agreement dated 23.02.2019 along with Affidavit
Hearing
 
112
276/TT/2019
Essar Power Transmission Company Limited (EPTCL)
Determination of Tariff for Stage-I Assets for Inter-State Transmission of Electricity under Section 79(1)(d) of the Electricity Act, 2003 read with Regulation-86 of Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
Preliminary Scrutiny
 
113
275/MP/2019
Adani Power (Mundra) Limited (APMuL)
Petition pursuant to the directions of the Hon?ble Supreme Court vide Order dated 02.07.2019 in Civil Appeal No. 11133 of 2011 and applicable provisions of the Electricity Act, 2003 including Sections 62 and 79(1)(b).
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
114
274/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 
for LILO of Vemagiri- Gajuwaka 400 kV D/C Line at SIMHADRI-II TPS under Transmission System Associated with SIMHADRI-II Generation project in Southern Region (DOCO 01.08.2011).
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
115
273/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act, 2003 read with related provisions of the Chapter-5 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 6 of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations,2014 for revision of  tariff for the period 01.04.2014 to 31.03.2019 carrying out truing up exercise for the period 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period  of 2014-15 to 2018-19 in respect of  Ranganadi Hydro Electric Plant (3X135 =405 MW) of North Eastern Electric Power Corporation Limited (NEEPCO LTD), Shillong.
Preliminary Scrutiny
 
116
18/RP/2019 in 315/GT/2018
SJVN Limited
Review of the order dated 26.06.19 passed by the Hon'ble Commission in Petition No. 315/GT of 2018
Hearing
 
117
272/GT/2019
Torrent Power Limited (TPL)
Petition under section 62 and 79 (1) (b) of the Electricity Act, 2003 read with CERC Terms and Conditions of Tariff, Regulation 2014 for Tariff of UNOSUGEN 382.5 MW Power Plant (SUGEN-40) of Torrent Power Limited from 01st April 2014 to 31st March 2019 - Truing up of Tariff under Regulation 8(1) of Tariff Regulation 2014.
Hearing
 
118
271/GT/2019
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 62 and 79 (1) of the Electricity Act,2003 read with related provisions of the Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations,1999 and the Central Electricity Regulatory Commission (Procedure for tariff Determination) Regulations,2014 for revision of tariff for the period 24.12.2015 to 31.03.2019 carrying out truing up exercise for the period of 2014-19 with respect to the capital expenditure including additional capital expenditure incurred during the period of 24.12.2015-16  to 2018-19   in respect Tripura Gas Based Power Plant (TGBP) (65.42x1+35.58x1=101 MW))of North Eastern Electric Power Corporation Limited (NEEPCO), Shillong.
Preliminary Scrutiny
 
119
270/GT/2019
Torrent Power Limited (TPL)
Petition under section 62 and 79 (1) (b) of the Electricity Act, 2003 read with CERC Terms and Conditions of Tariff, Regulation 2014 for Tariff of SUGEN 1147.5 MW Power Plant from 01st April 2014 to 31st March 2019 - Truing up of Tariff under Regulation 8(1) of Tariff Regulation 2014.
Hearing
 
120
269/MP/2019
Central Transmission Utility (CTU)
Grant of Regulatory Approval for execution of the Transmission  Scheme for Solar Energy Zones (SEZs) in Rajasthan under Phase-II
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
121
268/GT/2019
Torrent Power Limited (TPL)
Petition under section 62 and 79 (1) (b) of the Electricity Act, 2003 read with CERC Terms and Conditions of Tariff, Regulation 2014 for Tariff of UNOSUGEN 382.5 MW Power Plant (SUGEN-40) from 01st April 2019 to 31st March 2024.
Hearing
 
122
267/MP/2019
NHDC LIMITED
Application under Regulation-44 ( 7 & 8 ) of CERC (Terms and Conditions of Tariff) Regulations, 2019 for Recovery of Shortfall in Energy Charges in comparison to fifty percent of the Annual Fixed Cost (AFC) for reasons beyond the control of generating station during the FY 2017-18 and 2018-19 in respect of Omkareshwar Power Station (OSPS).
Preliminary Scrutiny
 
123
17/RP/2019 in 227/MP/2017
LANCO AMARKANTAK POWER LTD. LAMPL
Petition under Section 94(1)(f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) Regulations, 1999 for review of the order dated 30.05.2019 read with corrigendum dated 26.06.2019 passed by the Hon?ble Commission in Petition No. 227/MP/2017
Preliminary Scrutiny
 
124
266/TT/2019
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Identification of Maharashtra State Electricity Transmission Company Limited (MSETCL) 132kV Nepanagar (from 220kV Nepanagar Substation, Madhya Pradesh) to Dharni (132/33kV Dharni Substation, MSETCL Amaravati Zone, Maharashtra) line as Inter-State Transmission System and further Determination of Inter-State Transmission Tariff for the Tariff Period 2019-24, under Section 79(1)(d) of the Electricity Act, 2003 read with Regulation 86 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and in accordance with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019, for inclusion in the POC Transmission Charges as determined by the Central Electricity Regulatory Commission (CERC) time to time.
Preliminary Scrutiny
 
125
265/TT/2019
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED (APTRANSCO)
Petition for Determination of tariff of the inter-State transmission lines connecting two states along with the bays for the APTRANSCO owned transmission lines/system for FY 2019-20 to FY 2023-24 for inclusion in POC mechanism in accordance with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.
Preliminary Scrutiny
 
126
264/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 


 400 kV D/C Talcher-Meramundali transmission line in Eastern Region.
Preliminary Scrutiny
 
127
263/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

  For 315 MVA Transformer at Jeypore Substation along with associated bays in Eastern Region.
Preliminary Scrutiny
 
128
262/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for Approval under sub-section(4) of Section 28 & 79(1)(d) of Electricity Act 2003 and regulation-86 of CERC (Conduct of Business) Regulations�1999 for  determination of 
i) Trued up Fees and Charges for 2009-14 block
ii) Fees and Charges for the period 2014-19 block. 

For Asset-I: 17 Nos of OPGW links (759 km) (DOCO: 01.10.2012), Asset II: 09 nos of OPGW links (490 km) (DOCO: 01.04.2013), Asset III: 10 nos of OPGW links (440 km) (DOCO: 01.11.2013) and Asset IV: 01 nos of WBSETCL sector portion OPGW link (78.26 km) (DOCO: 01.03.2014) under �Fibre Optic communication system in lieu of existing Unified Load Despatch and Communication(ULDC) Microwave links� in Eastern Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
129
261/MP/2019
PTC India Limited PTC
Petition under Regulation 12 of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014 as amended from time to time read with Central Electricity Regulatory Commission (Cross Border Trade of Electricity) Regulations, 2019.
Preliminary Scrutiny
 
130
260/MP/2019
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking compensation on account of change in law events under the Power Purchase Agreement dated 25.03.2011 (PPA) executed between the Petitioner and the Respondent No. 2 and the Power Supply Agreement (PSA) dated 05.01.2011 executed between Respondent No.1 and Respondent No. 2
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
131
259/GT/2019
Torrent Power Limited (TPL)
Petition under section 62 and 79 (1) (b) of the Electricity Act, 2003 read with CERC (Terms and Conditions of Tariff) Regulations, 2019 for determination of Tariff of SUGEN 1147.5 MW Power Plant for the period 01st April 2019 to 31st March 2024.
Hearing
 
132
7/SM/2019
Suo Motu
Non Compliance of the Central Electricity Regulatory Commission(Payment of Fee) Regulation,2012
Preliminary Scrutiny
 
133
258/MP/2019
JHAJJAR POWER LIMITED (JPL)
Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Article 17 of the PPA dated 20.01.2009 for adjudication of dispute with respect to non-payment of amount towards the level of lifting penalty paid to coal suppliers by Jhajjar Power Limited in terms of Article 1.2.8 of Schedule 7 of the PPA for the Contract Year 2016-17
Preliminary Scrutiny
 
134
257/MP/2019
MB Power (Madhya Pradesh) Limited (MBPMPL)
PETITION UNDER SECTION 79(1)(C), 79(1)(F) AND 79(1)(K) OF THE ELECTRICITY ACT, 2003, CHALLENGING THE UNLAWFUL CONDUCT OF  POWER GRID CORPORATION OF INDIA LIMITED INTER ALIA WRONGFULLY RAISING AND RECOVERING TRANSMISSION CHARGES THROUGH IMPERMISSIBLE AND INAPPLICABLE INVOICES BEING CONTRA / AGAINST AND UNSUSTAINABLE TO THE TERMS OF THE TRANSMISSION SERVICE AGREEMENT DATED 18.10.2012 AND THE LONG TERM ACCESS AGREEMENT DATED 04.06.2015, PROVISIONS OF THE ELECTRICITY ACT 2003 AND THE REGULATIONS FRAMED THEREUNDER.
Preliminary Scrutiny
 
135
256/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

   For 400 kV Jamshedpur-Rourkela S/C (Ckt-II) transmission line in Eastern Region.
Preliminary Scrutiny
 
136
255/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

for Agra (Power Grid)- Agra (UPPCL) 400 kV D/C Interconnection in Northern Region.
Preliminary Scrutiny
 
137
254/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
IN THE MATTER OF: Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: URTDSM System(Control Center Equipment, PMU�s and associated equipment�s) integrated and commissioned at SRLDC & SLDCs of Southern Region under �Phase-I- Unified Real Time Dynamic State Measurement (URTDSM)�
Preliminary Scrutiny
 
138
16/RP/2019 in 242/MP/2017
Central Transmission Utility (CTU)
REVIEW PETITION UNDER SECTION 94 OF THE ELECTRICITY ACT, 2003 READ WITH REGULATIONS 103, 111 AND 114 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 READ WITH ORDER 47, RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 FOR REVIEW OF ORDER DATED 3.12.2018 PASSED BY THIS HON'BLE COMMISSION IN PETITION NO.242/MP/2017
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
139
253/MP/2019
Shiga Energy Private Limited (SEPL)
Petition under Section 79 (1) (c) (d) and (f) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009
Preliminary Scrutiny
75/IA/2019
140
252/MP/2019
Central Transmission Utility (CTU)
PETITION UNDER SECTION 79(1)(C) READ WITH REGULATION 111 OF CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 SEEKING DIRECTIONS FOR IMPLEMENTING ORDER DATED 8.3.2019 PASSED BY THIS HON�BLE COMMISSION IN PETITION NO.92/MP/2015.
Hearing
 
141
251/MP/2019
Clean Solar Power (Jodhpur) Private Limited CSPJodhpur
Petition under Section 79 (1) (f) and (k) of the Electricity Act, 2003 (?Act?) read with Regulation 32 (Redressal Mechanism) and Regulation 33A (Power to Relax) of Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium-term Open Access and inter-State Transmission and related matters) Regulations, 2009 as amended from time to time (?Connectivity Regulations?) as well as Clause 9.0 of the Transmission Agreement for Connectivity dated 09.10.2018 seeking permission for extension of the period for submitting proof of release of 10% funds through equity towards execution of 250 MW Solar Power Project located at Vill: Kushlaram Ki Basti, Ismail Khan Ki Dhani & Dedasari, Tehsil: Baap, District: Jodhpur, Rajasthan for further period of five months i.e. from 25.08.2019 to 25.01.2020.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
142
250/MP/2019
GUJARAT URJA VIKAS NIGAM LIMITED (GUVNL)
Petition under Section 79 (1)(b) & (f) of E.A. 2003 for recall of CERC order dated 12.04.2019 in 374/MP/2018 granting approval to the Supplemental Agreement(s) dated 5.12.2018
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
143
249/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

 for 63 MVAR line Reactor on 400 kV Kolaghar-Rengali Line at Rengali Substation in Eastern Region (DOCO 01.06.2000).
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
144
248/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for Transmission Asset �2 nos of 240 MVAR, 765kV Switchable Line Reactors (6x80MVAR, 765kV, 1-Ph Shunt Reactor), along with Reactor Bays & 2 Nos 765kV Line Bays excluding PLCC, Telecom equipment and Line Terminal equipment such as LA, CVT & Wave Trap" at 765/400kV Kurnool S/s� under �Substation works associated with additional inter-regional AC link for import of power into Southern Region i.e., Warora- Warangal and Chilakaluripeta-Hyderabad - Kurnool 765kV Link''.
Preliminary Scrutiny
 
145
247/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

for  Series Capacitors on circuit I and II of 220 kV D/C Kishanpur - Pampore TL at Kishanpur Sub-station in Northern Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
146
246/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  

(i) Revision of Transmission Tariff for 2001-04 tariff  block, 2004-09 tariff  block, 2009-14 tariff  block
(ii) Truing up of Transmission tariff for 2014-19 tariff  block and 
(iii) Determination of Transmission tariff for 2019-24  tariff block 

For  LILO of Purnea-Dalkola 132 kV S/C line and extension at Purnea substation in Eastern Region.
Preliminary Scrutiny
 
147
245/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

For LILO of Alamathy-Siperumbudur 400 kV DC line at North Chennai TPS switchyard under transmission system associated with Chennai NTPC �TNEB JV TPS in Southern Region
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
148
244/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations,  2014 and CERC (Terms and Conditions of Tariff) Regulations�  2019 for  
(i) Truing up of Transmission tariff for 2014-19 tariff  block and 
(ii) Determination of Transmission tariff for 2019-24  tariff block 

       for assets under Korba III Transmission System in WR.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
149
243/MP/2019
DCM SHRIRAM INDUSTRIES LIMITED (DCMSIL)
Petition under section 79(1)(k) of Electricity Act, 2003 and Regulation 2(1)(d) read with Regulation 27 and 111 of Central Electricity Regulatory Commission (Conduct of Business Regulations), 1999 and Regulations 3, 7, 14 and 15 of Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation), Regulations, 2010 seeking condonation of Delay in uploading Energy Injection Report data for the month of October, 2018  and consequently delay in  complying with the procedure for issuance of Renewable Energy Certificates and to further direct the Respondent to issue the Certificates due to the Petitioner
Hearing
 
150
242/MP/2019
TECHNO ELECTRIC AND ENGINEERING COMPANY LIMITED TECHNO
Petition filed under Section 79 of the Electricity Act, 2003 read with Regulations 3(4) and 14 of the Central Electricity Regulatory Commission (Terms and Conditions for Recognition and Issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 and Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999.
Hearing
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
151
241/MP/2019
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Sections 79(1)(f) read with 79(1)(c) and 79(1)(b) of the Electricity Act, 2003 relating to adjudication of dispute relating to Energy Meter Data discrepancy at Bhadrawati station leading to commercial loss to GMR Warora Energy Limited
Preliminary Scrutiny
 
152
240/MP/2019
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79(1)(b) of the Electricity Act, 2003 for claiming compensation on account of occurrence of "Change in Law" event as per Article 10.1.1 of the Case-1 long-term Power Purchase Agreement dated 21.03.2013 entered into between GMR Warora Energy Limited and DNH Power Distribution Corporation Limited, thereby resulting into additional recurring/non-recurring expenditure to GMR Warora Energy Limited for supply of 200 MW Contracted Capacity from its 2 x 300 MW Thermal Power Station at Warora, Distt. Chandrapur in the State of Maharashtra to DNH Power Distribution Corporation Limited.
Preliminary Scrutiny
 
153
239/MP/2019
THDC India Limited (THDCIL)
Recovery of money due and outstanding from BSES Yamuna Power Limited as per the tariff determined by the Hon?ble Commission and in terms of the agreement between THDC India Limited and BSES Yamuna Power Limited
Preliminary Scrutiny
 
154
238/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Central Industrial Security Force (CISF) in Parbati-III Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
155
237/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Central Industrial Security Force (CISF) in Chamera-III Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
156
236/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) / Dayanand Anglo Vedic (DAV) & Central Industrial Security Force (CISF) in Chamera-II Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
157
235/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) / Dayanand Anglo Vedic (DAV) & Central Industrial Security Force (CISF) in Chamera-I Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
158
234/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in Salal Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
159
233/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in Dhauliganga Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
160
232/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) / Dayanand Anglo Vedic (DAV) & Indian Reserve Battalion (IRBN) in Rangit Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
161
231/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Indian Reserve Battalion (IRBN) in Teesta-V Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
162
230/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Central Industrial Security Force (CISF) in TLDP-IV Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
163
229/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in TLDP-III Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
164
228/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in Tanakpur Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
165
227/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in Uri-II Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
166
226/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Central Industrial Security Force (CISF) in Sewa-II Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
167
225/MP/2019
HARYANA POWER PURCHASE CENTRE HPPC
Petition under section 79(1)(f) of the Electricity Act, 2003 for refund of amounts wrongly recovered by Power Grid Corporation of India Limited under POC Charges
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
168
224/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in Uri-I Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
169
223/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of J&K Police in Chutak Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
170
222/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of J&K Police in Nimoo Bazgo Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
171
221/MP/2019
NHPC LTD
Petition under section 94 of the Electricity Act, 2003 read with regulations 79, 111 & 114 of CERC (Conduct of Business) Regulations, 1999 and Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations, 2014 for recovery of impact of wage revision of its employees and deputed employees of Kendriya Vidyalaya (KV) & Central Industrial Security Force (CISF) in Dulhasti Power Station during the period 01.01.2016 to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
172
220/MP/2019
NHDC LIMITED
Application under Regulation-44 ( 7 & 8 ) of CERC (Terms and Conditions of Tariff) Regulations, 2019 for Recovery of Shortfall in Energy Charges in comparison to fifty percent of the Annual Fixed Cost (AFC) for reasons beyond the control of generating station during the FY 2017-18 and 2018-19 in respect of Indira Sagar Power Station (ISPS).
Preliminary Scrutiny
 
173
219/GT/2019
NLC INDIA LIMITED (formerly Neyveli Lignite Corporation  Limited) (NLCIL)
NNTPS (Neyveli New Thermal Power Station) 2 X 500 MW�Determination of tariff for the period from the date of anticipated CoD during the control period 2019-24 until 31.03.2024� Petition under section 79 read with Section 62 and 64 of the electricity act for determination of tariff.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
174
218/GT/2019
NLC INDIA LIMITED (formerly Neyveli Lignite Corporation  Limited) (NLCIL)
Andaman NLC Solar Power Station I - 20 MW (2X10 MW (AC) -solar PV power projects integrated with 8MWHr BESS) in South Andaman
Preliminary Scrutiny
 
175
216/GT/2019
NABINAGAR POWER GENERATING COMPANY PRIVATE LIMITED (NPGCPL)
Approval of tariff of Nabinagar STPS Stage-I (3x660 MW) from anticipated COD of Unit-1 (01.08.2019) to 31.03.2024.
Preliminary Scrutiny
 
176
215/AT/2019
SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
Petition under section 63 of the electricity act, 2003 for adoption of tariff for the 1200 MW wind power projects (tranche-VI) connected to the Inter-state transmission system and selected through competitive bidding process as per the standard bidding guidelines dated 08.12.2017 of the Central Government
Order reserved
 
177
214/MP/2019
Tata Power Trading Company Limited (TPTCL)
Petition under Sections 79(1) (c) and 79 (1)(f) of the Electricity Act, 2003 read with Regulation 32 of the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 impugning the wrongful rejection of open access.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
178
213/MP/2019
YARROW INFRASTRUCTURE PVT LTD (YIPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 22.06.2016 executed between Yarrow Infrastructure Private Limited and National Thermal Power Corporation Limited for seeking approval of Change in Law events due to enactment of the GST Laws
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
179
212/MP/2019
SEMBCORP ENERGY INDIA LIMITED (SEIL)
Petition under Section 79 of the Electricity Act, 2003 read with Power Supply Agreement dated 18.02.2016 executed between Sembcorp Energy India Limited and the Discoms for release of amounts arbitrarily and wrongfully withheld by Respondents from fuel charges legally payable to Sembcorp Energy India Limited
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
180
211/MP/2019
RATTANINDIA SOLAR 2 PVT LTD (RS2PL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 27.06.2016 executed between RattanIndia Solar 2 Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
181
6/SM/2019
Suo Motu
Non-Compliance of the directions of the Commission in Order dated 17.5.2019 in Petition No 17.5.2019 in Petition No 211/MP/2016 by Global Energy Private Limited(GEPL)
Interim order issued
 
182
210/MP/2019
SEMBCORP ENERGY INDIA LIMITED (SEIL)
Petition under Section 79(1)(b) read with 79(1)(f) of the Electricity Act, 2003 and Article 34.1 of the Power Supply Agreement dated 18.02.2016, for the approval and consequent relief sought by the Petitioner due to a 'Change in Law' event viz. the introduction of new environmental norms by way of the Environment (Protection) Amendment Rules, 2015 issued by the Ministry of Environment, Forest and Climate Change dated 07.12.2015, impacting the revenues and costs of the Petitioner during the operating period.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
183
209/MP/2019
SEMBCORP ENERGY INDIA LIMITED (SEIL)
Petition under Section 79(1)(b) read with 79(1)(f) of the Electricity Act, 2003 and Article 10.1 of the Power Purchase Agreement dated 01.04.2013, for the approval and consequent relief sought by the Petitioner due to a 'Change in Law' event viz. the introduction of new environmental norms by way of the Environment (Protection) Amendment Rules, 2015 issued by the Ministry of Environment, Forest and Climate Change dated 07.12.2015, impacting the revenues and costs of the Petitioner during the operating period.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
184
208/MP/2019
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 for execution/implementation of the Order dated 16.05.2019 passed in Petition No. 08/MP/2014 and Petition No. 284/MP/2018; and initiation of proceedings under Section 142 of the Electricity Act, 2003 against Maharashtra State Electricity Distribution Company Limited and DNH Power Distribution Corporation Limited in relation thereto
Hearing
 
185
207/MP/2019
Railway Energy Management Co.Ltd. (REMCL)
Petition under Section 79(1)(k) of the Electricity Act, 2003 read with Section 66 of the Electricity Act, 2003 and Regulations 26(i)(a), 63 & 64 of the Central Electricity Regulatory Commission (Power Market) Regulations, 2010 for grant of proprietary membership of Power Exchanges to M/s. Railways Energy Management Company Limited for transactions involving Indian Railways
Hearing
 
186
206/MP/2019
Punjab State Power Corporation limited (PSPCL)
PETITION UNDER SECTION 79(1)(c) AND 79(1)(f) OF THE ELECTRICITY ACT, 2003, FOR REFUND OF AMOUNTS WRONGLY RECOVERED BY POWERGRID CORPORATION OF INDIA LIMITED UNDER POC CHARGES FOR THE ISTS LINES OPERATED AND MAINTAINED BY BBMB
Hearing
 
187
15/RP/2019 in 327/MP/2018
DHARIWAL INFRASTRUCTURE LIMITED (DIL)
REVIEW PETITION UNDER SECTION 94(1)(f) OF THE ELECTRICITY ACT, 2003 READ WITH ORDER 47 RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 AND REGULATION 103 OF THE CERC (CONDUCT OF BUSINESS) REGULATIONS, 1999.
Preliminary Scrutiny
 
188
205/TD/2019
Saranyu Power Trading Private Limited (SPTPL)
PETITION FOR CHANGE OF NAME AND FURTHER NECESSARY CHANGES IN DOCUMENTS HELD IN THE NAME OF �IPCL POWER TRADING PRIVATE LIMITED� TO �SARANYU POWER TRADING PRIVATE LIMITED� UNDER SECTION 17(3) OF THE ELECTRICITY ACT, 2003 READ WITH REGULATION 7(t) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (PROCEDURE, TERMS AND CONDITIONS FOR GRANT OF TRADING LICENCE AND OTHER RELATED MATTERS) REGULATIONS, 2009
Preliminary Scrutiny
 
189
204/AT/2019
SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
Petition under Section 63 of the Electricity Act, 2003 for Adoption of Tariff for the 1200 MW (Tranche-III) Solar PV Projects connected to the Inter-State Transmission System (ISTS) and selected through competitive bidding process as per the Standard Bidding Guidelines dated 03.08.2017
Order reserved
 
190
203/MP/2019
Solaire Surya Urja Private Limited (SuryaUrja)
Petition under Section 79 of the Electricity Act, 2003 read with Article 16.3.1 of the Power Purchase Agreements dated 02.05.2016 executed between the Petitioner and NTPC Limited, seeking extension of the Scheduled Commissioning Date for two 70 MW solar power projects established under the National Solar Mission Phase-II, Batch-II, Tranche-I and seeking refund of the amount wrongfully and forcibly collected by NTPC Limited purportedly as liquidated damages for delay in commencement of supply of power.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
191
202/MP/2019
NLC INDIA LIMITED (formerly Neyveli Lignite Corporation  Limited) (NLCIL)
NLCIL-Thermal �increase in O&M Expenses on account of Pay/Wage revision and other pay hikes to Employees (Executives wef 01.01.2017, Non Executives& workmen wef 01.04.2014) of NLCIL�s Power Stations & CISF security personnel wef 01.01.2016 including Gratuity ceiling limit increase-  recovery from the beneficiaries of NLCIL Power Stations for the year  2014-19
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
192
201/MP/2019
Weizmann Limited
Petition Seeking Payment of Differential Tariff of Rs. 1.685 Per Unit for the Period from January 2011 To May 2014
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
193
200/MP/2019
Central Transmission Utility (CTU)
Section 38(2) of the of the Electricity Act, 2003 read with Section 79(1)(c) and Section 79(1)(k) of the Act, alongwith (i) Central Electricity Regulatory Commission (Grant of Regulatory Approval for execution of Inter-State Transmission Scheme to Central Transmission Utility) Regulations, 2010; (ii) Regulation 111 & 114 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations,1999 and (iii) Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010 for Grant of Regulatory Approval for execution of the Transmission System for 18.5 GW of Solar and Wind Energy Zones in Southern Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
194
14/RP/2019 in 318/MP/2018
Central Transmission Utility (CTU)
REVIEW OF ORDER DATED 9.4.2019 PASSED BY THIS HON?BLE COMMISSION IN PETITION NO.318/MP/2018.
Reply / additional information as per ROP to filed by Petitioner
80/IA/2019
195
13/RP/2019 in 35/MP/2018
Central Transmission Utility (CTU)
REVIEW OF ORDER DATED 19.3.2019 PASSED IN PETITION NO.35/MP/2018
Order reserved
68/IA/2019
196
199/MP/2019
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Section 79 (1) (f) and Section 79 (1) (c) of the Electricity Act, 2003 seeking adjudication of disputes between Tata Power Delhi Distribution Limited and Pragati Power Corporation Limited regarding declaration of Availability by Pragati Power Corporation Limited and claiming fixed charges thereto
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
197
198/MP/2019
Teesta Urja Limited (TUL)
Miscellaneous Petition under Section 29(5) of the Electricity Act, 2003 read with Regulations 111& 115 of Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 2.3(7) & Part 7 of Indian Electricity Grid Code 2010 for harmonious interpretation and application of Regulations for meeting the ends of justice and for consequential orders on revision of schedule in case of Forced Outage attributable to Force Majeure for reasons beyond the control of the generating company
Reply / additional information as per ROP to filed by Petitioner,Respondent
67/IA/2019
198
196/MP/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 765 kV Line Bays and 240 MVAr Switchable Line Reactor at Raichur and Sholapur Sub-stations Under ?Line bays and reactor at POWERGRID sub-station for Raichur ? Sholapur transmission line for Synchronous interconnection between SR and WR?
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
199
195/MP/2019
Vivid Solaire Energy Private Limited (VSEPL)
Petition under Section 79 read with Regulations 20 and 21 of the Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010, read with Regulation 33A and 33B of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and Regulations 111 and 112 of the CERC (Conduct of Business) Regulations, 1999 invoking the jurisdiction of this Hon�ble Commission for resolving discrepancies arising on account of conflict between the SCOD under the PPA and date of operationalisation of Connectivity and LTA.
Hearing
65/IA/2019
200
194/MP/2019
Porwal Auto Components Ltd. (PACL)
Petition under section 66 and 79 of The Electricity Act 2003 read with regulation  14 and 15 of CERC  (Terms and Conditions for Recognition and Issuance of Renewable energy certificate for renewable energy generation) Regulations, 2010) for directions to the Respondents, National Load Despatch Centre and Madhya Pradesh Urja Vikas Nigam Ltd  - State Nodal Agency for the revalidation of accreditation and registration of the Petitioner under the Renewable Energy Certificates (REC) mechanism and consequent reliefs
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
201
193/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations?1999, and CERC (Terms and Conditions of Tariff) Regulations?2014 for Determination of Transmission Tariff for Asset-I: 400 kV D/C Alipurduar- Punatsangchun alongwith associated bays at Alipurduar substation Asset-II: 02 nos of 220 kV bays at Alipurduar Substation from actual DOCO to 31.03.2019 under the transmission system associated with ?Transmission system for development of pooling station in Northern part of West Bengal and transfer of power from Bhutan to NR/WR?.
Preliminary Scrutiny
 
202
192/MP/2019
NLC INDIA LIMITED (formerly Neyveli Lignite Corporation  Limited) (NLCIL)
Exemption from Technical Minimum operation for NLCIL TPS-II Expansion (2 X 250 MW) CFBC Units till 31.03.2020.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
203
191/MP/2019
North East Transmission Company Ltd. (NETC)
PETITION UNDER SECTION 79(1)(D) OF THE ELECTRICITY ACT 2003 READ WITH REGULATIONS 54 AND 55 OF THE CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014 SEEKING RELAXATION OF OPERATIONS AND MAINTENANCE NORMS SPECIFIED UNDER CERC REGULATION 29(4)
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
204
190/MP/2019
NTPC Limited
Petition under Section 79 of the Electricity Act, 2003 to give a framework on the issue of advance being paid by NTPC to Indian Railways for transportation of coal from coal mines to thermal coal stations of NTPC for the period 2018-19 and 2019-20
Order reserved
 
205
189/MP/2019
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 (1) (b), Section 79(1 )(f) and Section 79(1) (k) of the Electricity Act, 2003 read with Article 11 of the power purchase agreements entered into between Solar Energy Corporation of India and Parampujya Solar Energy Private Limited seeking directions to Solar Energy Corporation of India to act in accordance with Article 11 of the PPA accepting the impact of Force Majeure Events and extend the timeline for fulfillment of Conditions Subsequent and Scheduled Commissioning Date of the Petitioner�s project.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
206
188/MP/2019
PTC India Limited PTC
Petition under Section 79(1)(f) of the Electricity Act, 2003 for adjudication of disputes arising out of and in relation to the Power Sale Agreement (PSA) dated 15.09.2006 between erstwhile Punjab State Electricity Board, i.e. the predecessor of Punjab State Power Corporation Ltd.  (PSPCL) and PTC India Ltd. (PTC) for purchase of 340 MW of power from 1200 MW Teesta�III Hydro-electric Project of Teesta Urja Ltd. (TUL), pursuant to the Power Purchase Agreement (PPA) dated 28.07.2006 between PTC and TUL and the Bulk Power Transmission Agreement (BPTA) dated 04.06.2010 signed between Power Grid Corporation of India Ltd (PGCIL), PSPCL, other DISCOMs of Uttar Pradesh, Rajasthan & Haryana and PTC.
Reply / additional information as per ROP to filed by Petitioner,Respondent
66/IA/2019
207
187/AT/2019
Tata Power Delhi Distribution Limited (TPDDL)
ADOPTION OF TARIFF FOR THE PURCHASE OF 100 MW OF SOLAR POWER FROM SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
Reply / additional information as per ROP to filed by Petitioner,Respondent
86/IA/2019
208
12/RP/2019 in 102/TT/2018
NTPC Limited
Review of the Order dated 02.05.2019 passed by Hon�ble Commission in Petition No. 102/TT/2018 with IA no. 60/IA/2018 in respect of  determination of Tariff for two 400KV bays at Gandhar owned by NTPC from COD of the asset to 31.3.2014 (2009-14 period) & from 1.4.2014 to 31.3.2019 (2014-19 period)
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
209
184/MP/2019
JSW Hydro Energy Limited (formerly Himachal Baspa Power Company Limited) JSWHEL
Petition under Regulation 44(6), (7) & (8) of The Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 for recovery of unrecovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2018-19 in respect of Karcham Wangtoo HEP
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
210
183/MP/2019
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking adjudication of disputes arising out of the Agreement for Power Procurement (�APP�) executed between Petitioner and Respondent No. 2 to 5.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
211
182/GT/2019
MEJA URJA NIGAM (P) LIMITED (MUNPL)
Petition Under Section 62 and 79(1)(a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff  of  Meja Thermal Power Station Stage-I (2x660 MW) for the period from anticipated Date of Commercial Operation  of Unit # 1 (i.e. 30.04.2019) to 31.03.2024.
Preliminary Scrutiny
 
212
181/GT/2019
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Gadarwara Super Thermal Power Station  (2 X 800 MW) for the period from anticipated date of Commercial Operation ofthe Unit-I (i.e. 30.04.2019)to 31.03.2024.
Preliminary Scrutiny
 
213
180/MP/2019
Indian Railways ECR
Petition under Regulation 13 read with Regulation 7 and 8 of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014, and Regulations 7(10) and 7(11a) of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (Fourth Amendment) Regulations, 2018, as inserted vide Amendment dated 20.11.2018, and read with Regulations 111 and 112 of the CERC (Conduct of Business) Regulations, 1999
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
214
179/MP/2019
Coastal Gujarat Power Limited (CGPL)
Petition under Section 79 of the Electricity Act read with Article 13 of the PPA dated 22.04.2007 seeking appropriate directions from this Hon?ble Commission for adequately compensating Coastal Gujarat Power Limited (by adjustment in tariff or by prescribing any other appropriate compensatory mechanism) on account of increased transportation cost of fuel due to occurrence of Change in Law events
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
215
178/MP/2019
JBM SOLAR ENERGY MAHARASHTRA PVT LTD (JBMSEM)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 07.02.2017, executed between JBM Solar Energy Maharashtra Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
216
177/MP/2019
JBM SOLAR POWER MAHARASHTRA PVT LTD (JBMSPM)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 07.02.2017, executed between JBM Solar Power Maharashtra Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
217
176/MP/2019
Solairepro Urja Private Limited
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement dated 07.02.2018 between the Petitioner and NTPC Limited seeking relief on account of Change in Law event, viz., the imposition of Safeguard Duty by Notification No. 01/2018 Customs (SG) dated 30.07.2018 issued by the Department of Revenue, Ministry of Finance, Government of India.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
218
175/MP/2019
RAICHUR SHOLAPUR TRANSMISSION COMPANY PRIVATE LIMITED (RSTCPL)
Application under section 17(3) and Section 17(4) of the Electricity Act,2003
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
219
174/MP/2019
Bharat Aluminium Company Limited (BALCO)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming carrying cost/ interest on account of event pertaining to change in law allowed by this Hon�ble Commission vide order dated 27.04.2018 passed in Petition No. 126/MP/2016 read with the terms of Power Purchase Agreements dated 23.08.2013 (PPAs) executed between the Petitioner and the Respondent No. 1/ TANGEDCO.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
220
173/MP/2019
Bharat Aluminium Company Limited (BALCO)
Petition under Section 79 (1) (b), 79 (1)(f) and 79 (1)(k) of the Electricity Act 2003, read with Articles 8.3.5, 8.4.3 and 8.4.11 of the PPA dated 23.08.2013 and the amended PPA dated 10.12.2013 executed between the Petitioner (BALCO) and the Respondent (TANGEDCO) seeking payment of the outstanding amount on account of (i) late payment surcharge; (ii) additional interest, and for furnishing of Stand by Letter of Credit as payment security mechanism
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
221
172/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1:765kV D/C Bhuj Pool Sub-station-Banaskantha TL along with associated  Bays & 2x330 MVAR Switchable Line Reactors at both ends along with bays, Asset-2: 765kV Bhuj Pool Sub-station (New) along with 2 Nos. 1500MVA, 765/400 kV ICTs, 1 No. 765kV Bus Reactor, 2 No. 500MVA 400/200kV ICTs and 1 no. 400kV Bus Reactor alongwith associated bays under Green Energy Corridors-Inter State Transmission Scheme (ISTS) Part-C for tariff block 2014-19 period.
Preliminary Scrutiny
 
222
171/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: Loop In Portion of LILO of Kadapa-Hindupur 400kV D/c line (both circuits) at NP Kunta Substation along with associated bays, Asset-2: Loop out Portion of LILO of Kadapa-Hindupur 400kV D/c line (both circuits) at NP Kunta Substation along with associated bays Asset-3: 02nos of 220kV Line bays (Bay No 217 & 218) at NPKunta sub-station and Asset-4: 04 Nos of 220 kV line bays (Bay No. 213,214 219 & 220) at NP Kunta Substation under �Transmission System for Ultra Mega Solar Park in Anantpur District, Andhra Pradesh - Part B (Phase-II).
Preliminary Scrutiny
 
223
170/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1- 192.509 kms of OPGW Links (Central Sector) (DOCO-01.04.2018) and Asset 2- 242.484 Km of OPGW Links (State Sector) (DOCO-31.12.2018) under project- �Fibre Optic Communication system in lieu of existing Unified Load Despatch and Communication (ULDC) Microwave links in North Eastern region.�
Preliminary Scrutiny
 
224
11/RP/2019 in 74/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Review of Order dated 29.04.2019
Reply / additional information as per ROP to filed by Petitioner
 
225
169/MP/2019
Jhabua Power Limited (JhabuaPower)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 for adjudication of the issues arising out of the Power Supply Agreement (PSA) dated 31.12.2014 for supply of 115 MW and PSA dated 26.12.2014 for supply of 100 MW of power to Kerala State Electricity Board Ltd. (KSEBL)
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
226
168/MP/2019
Coastal Gujarat Power Limited (CGPL)
Petition, under Section 79 of the Electricity Act, 2003 read with Article 13 of the Power Purchase Agreement dated 22.04.2007 and Clause 4.7 of the Competitive Bidding Guidelines and this Hon?ble Commission?s Order dated 17.09.2018 in Petition No. 77/MP/2016
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
227
165/MP/2019
Bharat Aluminium Company Limited (BALCO)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming carrying cost/ interest on account of event pertaining to change in law allowed by this Hon�ble Commission vide order dated 18.04.2018 passed in Petition No. 18/MP/2017 read with the terms of Power Purchase Agreements dated 13.06.2013 (PPA) executed between the Respondent No. 1/ KSEB and the Respondent No. 2/ PTC and back to back Power Purchase Agreements dated 13.06.2013 executed between the Petitioner and Respondent No. 2/PTC
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
228
164/MP/2019
Anrak Aluminium Limited (AnrakAluminiumLimited)
Recovery of due amount for the power supply made to the Respondents, non payment of surcharge, recovery of rebate deducted by Respondents despite making delayed payment violating the terms of the agreement to pay within time.
Hearing
 
229
163/MP/2019
DNH POWER DISTRIBUTION CORPORATION LTD (DNHPDCL)
PETITION UNDER SECTION 79 (1) (C) AND (F) OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES WHICH HAVE ARISEN ON ACCOUNT OF THE INCORRECT BILLING OF POC CHARGES BY THE RESPONDENTS ON THE PETITIONER
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
230
162/AT/2019
Tata Power Delhi Distribution Limited (TPDDL)
adoption of tariff for PPA executed with SECI
Reply / additional information as per ROP to filed by Petitioner,Respondent
84/IA/2019
231
161/AT/2019
Tata Power Delhi Distribution Limited (TPDDL)
Petition for approval of tariff under section 63 of the Electricity act, 2003 along with Section 79(1) (k) of the Act, for adoption of tariff for purchase of 50MW wind power from SECI.
Reply / additional information as per ROP to filed by Petitioner,Respondent
85/IA/2019
232
160/AT/2019
Tata Power Delhi Distribution Limited (TPDDL)
Adoption of tariff
Reply / additional information as per ROP to filed by Petitioner,Respondent
81/IA/2019
233
159/MP/2019
Toramba Renewable Energy Private Limited (TorambaEnergy)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in Inter State Transmission and related matters) Regulations, 2009 seeking time extension for achieving financial closure as provided under Clause 9.3.2 of the Detailed Procedure issued by the Central Commission for `Grant of Connectivity to projects based on Renewable sources to the Inter State Transmission System� dated 15.05.2018
Order reserved
 
234
158/MP/2019
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
Petition under Section 79(1) (b) read with Section 79(1) (f) of the Electricity Act, 2003 seeking a declaration that the deductions made by the Respondents towards penalty imposed and capacity charges from the bills raised by the Petitioner for the months of December, 2018, January, 2019 and February, 2019 is illegal and wrongful and a consequent direction to the Respondents, to jointly and severally, pay the deducted/withheld amounts against the bills raised for the month of December, 2018, January, 2019 and February, 2019, i.e. penalty imposed and unpaid capacity charges
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
235
157/TD/2019
Rajasthan Urja Vikas Nigam Limited (RUVNL)
Application from for grant of License for Inter-State Trading
Preliminary Scrutiny
 
236
155/MP/2019
UDUPI POWER CORPORATION LTD (UPCL)
Petition filed under Section 79 (1) (f) of the Electricity Act, 2003 read with Articles 3, 6, 7.2(b) and other provisions of the Power Purchase Agreement dated 26.12.2005 seeking adjudication of disputes related to legitimate dues payable to Udupi Power Corporation Limited by the Karnataka ESCOMs.
Reply / additional information as per ROP to filed by Petitioner,Respondent
79/IA/2019
237
154/RC/2019
Indian Energy Exchange Ltd. (IEX)
Application for approval of Cross Border Trade in IEX
Preliminary Scrutiny
 
238
153/MP/2019
Rajasthan Urja Vikas Nigam Limited (RUVNL)
PETITION UNDER SECTION 79(1)(c) AND 79(1)(f) OF THE ELECTRICITY ACT, 2003, FOR REFUND OF AMOUNTS WRONGLY RECOVERED BY POWER GRID CORPORATION OF INDIA LIMITED UNDER POC CHARGES FOR THE ISTS LINES OPERATED AND MAINTAINED BY BBMB
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
239
152/MP/2019
Maithon Power Limited (MPL)
Petition under Regulations 11 and 29 of the CERC (Terms and Conditions of Tariff) Regulations, 2019 read with other relevant provisions and this Hon�ble Commission�s directions in the Order dated 20.03.2017 in Petition no. 72/MP/2016.
Order reserved
 
240
151/MP/2019
INDIA GLYCOLS LIMITED (IGL)
Petition under Section 79(1)(k) of the Electricity Act, 2003 read with Regulation 15 of the Central Electricity Regulatory Commission (Terms and Conditions for Recognition and Issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 seeking condonation of delay in submitting the Application for issuance of Renewable Energy Certificate (REC) and other appropriate direction.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
241
150/MP/2019
Azure Power Uranus Private Limited (APUPL)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements dated 03.05.2016 and 08.05.2016 executed by the Petitioner with the Respondents, seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
242
149/MP/2019
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 (1) (b), Section 79(1 )(f) and Section 79(1) (k) of the Electricity Act, 2003 read with Article 11 of the power purchase agreements entered into between Solar Energy Corporation of India and Parampujya Solar Energy Private Limited seeking directions to Solar Energy Corporation of India to act in accordance with Article 11 of the PPA accepting the impact of Force Majeure Events and extend the timeline for fulfillment of Conditions Subsequent and  Scheduled Commissioning Date of the Petitioner�s projects.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
243
10/RP/2019 in 168/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review under Section 94(1)(f) read with Regulation 103 (1) of the CERC (Conduct of Business) Regulations 1999 of Order dated 20.02.2019 of the Central Electricity Regulatory Commission in Petition no. 168/TT/2018 for determination of Transmission Tariff from DOCO to 31-03-2019 for assets under �Fiber Optic Communication system for central sector Sub-stations & Generating Stations� in Southern Region.
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
244
148/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation 86 of  CERC (Terms and Conditions of Tariff) Regulations�2014 for  DOCO as effective 01.04.2014 determination of Transmission Tariff from DOCO to 31-03-2019; Regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for Asset-1: 230 KV D/C Kalpakkam PFBR - Kanchipuram Transmission Line and 2 numbers of 230 KV Bays at Kanchipuram Sub Station of TNEB  upon Determination of final transmission tariff from Proposed DOCO 01.04.2014 to 31.03.2019 in pursuance  of Hon�ble Appellate Tribunal vide order dated 20.09.2018 in Appeal no. 168 of 2015 and Hon,ble Commission vide Order dated 27.12.2018 in Petition 105/TT/2012 under Transmission system associated with Kalpakkam PFBR (500MW) project in Southern Region for tariff block 2014-19 period.
Preliminary Scrutiny
 
245
147/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Transmission System Associated with Augmentation of Transformation Capacity  in Northern region Part-A in Northern Region consisting of Asset-I:  500 MVA, 400/220/33 kV ICT-I along with associated bays at Moga S/s  (DOCO: 01.07.2013) ; Asset-II :  500 MVA, 400/220/33 kV ICT-II along with associated bays at Moga S/s  (DOCO: 01.03.2014); Asset-III : 500 MVA 400/220 kV Spare Transformer for Northern Region at Neemrana (DOCO: 01.11.2013) .
Preliminary Scrutiny
 
246
146/MP/2019
Phelan Energy India RJ Private Limited (PEIRJ)
Petition under section 79 of the Electricity Act, 2003 for execution of the Order dated 05.02.2019 passed in Petition no. 192/MP/2018; and initiation of proceedings under Section 142 of the Electricity Act, 2003 against Solar Energy Corporation of India Limited in relation thereto
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
247
9/RP/2019 in 2/SM/2019
Coastal Gujarat Power Limited (CGPL)
Application under Section 94 of the Electricity Act 2003, read with Regulation 103 of the Central Electricity Regulatory Commission (Conduct Of Business) Regulation,1999, Seeking review of the order dated 31.01.2019 passed by the Commission in Petition No.  2/SM/2019
Hearing
50/IA/2019
248
145/GT/2019
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Lara Super Thermal Power Station  (2x800 MW) for the period from anticipated date of Commercial Operation ofthe Unit-I (i.e. 15.05.2019)to 31.03.2024.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
249
144/MP/2019
Airpower Windfarms Private Limited
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in Inter State Transmission and related matters) Regulations, 2009 for time extension of infusion of equity as provided under Clause 9.3.2 of the Detailed Procedure issued by the Central Commission for `Grant of Connectivity to projects based on Renewable sources to the Inter State Transmission System� dated 15.05.2018
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
250
143/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 �ASSET � I: Neelamangla-Yelahanka (39.006 KM) OPGW Fibre Communication link of Central Sector along with associated communication Equipment under the project Fibre Optic Communication system in lieu of existing ULDC Microwave links in Southern Region�.
Preliminary Scrutiny
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
251
142/MP/2019
KSK Mahanadi Power Company Limited (kskmahanadi)
Memorandum of Review Petition
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
252
141/TT/2019
ODISHA POWER TRANSMISSION CORPORATION LIMITED (OPTCL)
Petition for approval of Tariff for inclusion of Transmission Assets in Computation of Point of Connection (PoC) Charges and Losses as per Hon�ble Commission�s order dated 12.05.2017 in Petition No. 07/SM/2017 for inclusion in PoC charges in accordance with Central Electricity Regulatory Commission (Sharing of Inter-state Transmission Charges and Losses) Regulations, 2010 and amendments made thereto.
Preliminary Scrutiny
 
253
140/MP/2019
TRN ENERGY PRIVATE LIMITED
Petition under section 79 (1) (f) of the Electricity Act, 2003 seeking various reliefs against Respondent No. 1 in terms of Power Purchase Agreement dated 25.7.13 along with Affidavit.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
254
138/MP/2019
ACME Kurukshetra Solar Energy Private Limited (AKSEPL)
Non-compliance of order 09.10.2018 passed by the Hon'ble Commission
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
255
137/MP/2019
Torrent Power Limited (TPL)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33 (A) of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-Term and Medium term Open Access in inter-State Transmission and related matters) Regulations, 2009for granting time extension as provided in this petition including to achieve financial closure required under Clause 9.3.2of the detailed procedure issued by Central Electricity Regulatory Commission for �Grant of Connectivity To Projects based on renewable energy sources To Inter-State Transmission System� dated 15.05.2018.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
256
136/MP/2019
ACME Rewari Solar Power Private Limited (ARSPPL)
Petition under Section 79 (1) (c) and Section 79(1) (k) of the Electricity Act, 2003 seeking directions to Karnataka Solar Power Development Corporation Limited to not place any restrictions in evacuation of the power from solar generating stations of ACME Rewari Solar Power Private Limited and ACME Kurukshetra Solar Energy Private Limited having 100 MW (50 MW*2) capacity in Pavagada Solar Park under National Solar Mission Phase-II Batch-II Tranche-I
Hearing
 
257
135/MP/2019
CLEAN SOLAR POWER GULBARGA PRIVATE LIMITED (CSPGULBARGA)
PETITION UNDER SECTION 79(1)(b) READ WITH SECTION 79(1)(f) OF THE ELECTRICITY ACT, 2003 AND ARTICLE 12.2.1 OF THE POWER PURCHASE AGREEMENT DATED 02.08.2016 ON BEHALF OF M/S. CLEAN SOLAR POWER (GULBARGA) PRIVATE LIMITED SEEKING THIS HON�BLE COMMISSION TO ACKNOWLEDGE AND APPROVE PROMULGATION OF THE CENTRAL GOODS AND SERVICES TAX ACT, 2017, THE INTEGRATED GOODS AND SERVICES TAX ACT, 2017, AND THE KARNATAKA GOODS AND SERVICES TAX ACT, 2017 AS EVENTS OF �CHANGE IN LAW� WITH EFFECT FROM 01.07.2017 AND SEEKING RELIEF FOR THE NON-RECURRING ADDITIONAL EXPENSE INCURRED BY THE PETITIONER ON ACCOUNT OF THE SAID �CHANGE IN LAW� EVENTS AMOUNTING TO INR 10,36,76,660.18, AS ALSO THE CARRYING COSTS ASSOCIATED THEREWITH.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
258
134/MP/2019
CLEAN SOLAR POWER GULBARGA PRIVATE LIMITED (CSPGULBARGA)
PETITION UNDER SECTION 79(1)(b) READ WITH SECTION 79(1)(f) OF THE ELECTRICITY ACT, 2003 AND ARTICLE 12.2.1 OF THE POWER PURCHASE AGREEMENT DATED 02.08.2016 ON BEHALF OF M/S. CLEAN SOLAR POWER (GULBARGA) PRIVATE LIMITED SEEKING THIS HON�BLE COMMISSION TO ACKNOWLEDGE AND APPROVE PROMULGATION OF THE CENTRAL GOODS AND SERVICES TAX ACT, 2017, THE INTEGRATED GOODS AND SERVICES TAX ACT, 2017, AND THE KARNATAKA GOODS AND SERVICES TAX ACT, 2017 AS EVENTS OF �CHANGE IN LAW� WITH EFFECT FROM 01.07.2017 AND SEEKING RELIEF FOR THE NON-RECURRING ADDITIONAL EXPENSE INCURRED BY THE PETITIONER ON ACCOUNT OF THE SAID �CHANGE IN LAW� EVENTS AMOUNTING TO INR 7,09,35,542.34, AS ALSO THE CARRYING COSTS ASSOCIATED THEREWITH.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
259
132/MP/2019
Indian Railways ECR
Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Clause 7.0 of the Bulk Power Purchase Agreement executed between Indian Railways and Bharatiya Rail Bijlee Company Limited dated 16.12.2010 seeking relief on account of Force Majeure events being suffered by the Indian Railways.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
260
8/RP/2019 in 238/MP/2017
Darbhanga Motihari Transmission Company Limited (DMTCL)
Review Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Order 47 Rule 1 of the Code of Civil Procedure, 1908 and Regulation 103 (1) of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999, seeking review of order dated 29.03.2019 passed in Petition No. 238/MP/2017
Order reserved
 
261
7/RP/2019 in 195/MP/2017
NRSS XXXI (B) Transmission Limited (NRSSXXXIB)
Review Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Order 47 Rule 1 of the Code of Civil Procedure, 1908 and Regulation 103 (1) of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999, seeking review of order dated 29.03.2019 passed in Petition No. 195/MP/2017
Order reserved
 
262
131/MP/2019
BSES YAMUNA POWER Ltd. (BYPL)
Petition invoking Section 79(1)(e), 79(1)(i) and Section 79(1)(k) read with Sections 129 & 130 of the Electricity Act, 2003 read with Regulation 7, 8 and 13 of Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading license and other related matters) Regulations, 2009 seeking  appropriate directions against Global Energy Private Ltd..
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
263
130/MP/2019
CLEAN SOLAR POWER GULBARGA PRIVATE LIMITED (CSPGULBARGA)
PETITION UNDER SECTION 79(1)(b) READ WITH SECTION 79(1)(f) OF THE ELECTRICITY ACT, 2003 AND ARTICLE 12.2.1 OF THE POWER PURCHASE AGREEMENT DATED 02.08.2016 ON BEHALF OF M/S. CLEAN SOLAR POWER (GULBARGA) PRIVATE LIMITED SEEKING THIS HON�BLE COMMISSION TO ACKNOWLEDGE AND APPROVE PROMULGATION OF THE CENTRAL GOODS AND SERVICES TAX ACT, 2017, THE INTEGRATED GOODS AND SERVICES TAX ACT, 2017, AND THE KARNATAKA GOODS AND SERVICES TAX ACT, 2017 AS EVENTS OF �CHANGE IN LAW� WITH EFFECT FROM 01.07.2017 AND SEEKING RELIEF FOR THE NON-RECURRING ADDITIONAL EXPENSE INCURRED BY THE PETITIONER ON ACCOUNT OF THE SAID �CHANGE IN LAW� EVENTS AMOUNTING TO INR 18,19,37,667.74, AS ALSO THE CARRYING COSTS ASSOCIATED THEREWITH.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
264
129/MP/2019
CLEAN SOLAR POWER GULBARGA PRIVATE LIMITED (CSPGULBARGA)
PETITION UNDER SECTION 79(1)(b) READ WITH SECTION 79(1)(f) OF THE ELECTRICITY ACT, 2003 AND ARTICLE 12.2.1 OF THE POWER PURCHASE AGREEMENT DATED 02.08.2016 ON BEHALF OF M/S. CLEAN SOLAR POWER (GULBARGA) PRIVATE LIMITED SEEKING THIS HON?BLE COMMISSION TO ACKNOWLEDGE AND APPROVE PROMULGATION OF THE CENTRAL GOODS AND SERVICES TAX ACT, 2017, THE INTEGRATED GOODS AND SERVICES TAX ACT, 2017, AND THE KARNATAKA GOODS AND SERVICES TAX ACT, 2017 AS EVENTS OF ?CHANGE IN LAW? WITH EFFECT FROM 01.07.2017 AND SEEKING RELIEF FOR THE NON-RECURRING ADDITIONAL EXPENSE INCURRED BY THE PETITIONER ON ACCOUNT OF THE SAID ?CHANGE IN LAW? EVENTS AMOUNTING TO INR 4,54,46,778.78, AS ALSO THE CARRYING COSTS ASSOCIATED THEREWITH.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
265
128/MP/2019
ODISHA POWER GENERATION CORPORATION LIMITED (OPGC)
Petition under Sections 79(1)(c) and 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 of Connectivity Regulations, 2009 challenging the legality of Bill Nos. OGPTL-OPGC-01 dated 15.10.2018 and OPGTL-OPGC-02 dated 08.03.2019 raised by Respondent No. 1, Central Transmission Utility
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
266
127/MP/2019
CLEAN SOLAR POWER GULBARGA PRIVATE LIMITED (CSPGULBARGA)
PETITION UNDER SECTION 79(1)(b) READ WITH SECTION 79(1)(f) OF THE ELECTRICITY ACT, 2003 AND ARTICLE 12.2.1 OF THE POWER PURCHASE AGREEMENT DATED 02.08.2016 ON BEHALF OF M/S. CLEAN SOLAR POWER (GULBARGA) PRIVATE LIMITED SEEKING THIS HON�BLE COMMISSION TO ACKNOWLEDGE AND APPROVE PROMULGATION OF THE CENTRAL GOODS AND SERVICES TAX ACT, 2017, THE INTEGRATED GOODS AND SERVICES TAX ACT, 2017, AND THE KARNATAKA GOODS AND SERVICES TAX ACT, 2017 AS EVENTS OF �CHANGE IN LAW� WITH EFFECT FROM 01.07.2017 AND SEEKING RELIEF FOR THE NON-RECURRING ADDITIONAL EXPENSE INCURRED BY THE PETITIONER ON ACCOUNT OF THE SAID �CHANGE IN LAW� EVENTS AMOUNTING TO INR 10,72,24,792.20, AS ALSO THE CARRYING COSTS ASSOCIATED THEREWITH.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
267
126/MP/2019
Fatehgarh-Bhadla Transmission Limited (FBTL)
Petition under Section 79 (1) (c) and (f) and other applicable provisions of the Electricity Act, 2003 seeking declaration that the event namely, notification of the GIB Arc coordinates vide letter dated 28.02.2019 by the Deputy Conservator of Forest, Jaisalmer on account of which Petitioner is required to re-route the 765 kV D/C Fatehgarh - Bhadla Transmission Line, is a �Change in Law� event under Article 12 of the TSA dated 10.01.2018, with liberty to approach this Hon�ble Commission to assess the actual impact of such �Change in Law� event, based on the actual and audited expenditure incurred by the Petitioner as per formula specified under Article 12.2.1 of the TSA and other consequential reliefs.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
268
125/MP/2019
Welspun Energy Private Limited (WelspunEnergy)
Petition under Section 79 of the Electricity Act, 2003 for seeking extension of time for commissioning of balance capacity of 72 MW (out of 100 MW) Solar PV project in terms of the order dated 17.12.2018 passed by this Hon?ble Commission.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
63/IA/2019
269
124/MP/2019
Sasan Power Limited (SPL)
Petition pursuant to Judgment of the Hon�ble Appellate Tribunal for Electricity dated 06.03.2019 in Appeal No. 149 of 2017 and under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 13.2(b) of the Power Purchase Agreement dated 07.08.2007 executed between Sasan Power Limited and the Procurers for awarding of Carrying Cost on the compensation payable for allowed Change in Law events.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
270
122/MP/2019
Essar Power M.P. Ltd. (EPMPL)
Petition under Section 79(1)(f) of the Electricity Act, 2003 for adjudication of dispute arising out of the action of Power Grid Corporation of India in raising Bill-3 in contravention of Regulation 11 of the Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
271
121/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from Proposed DOCO to 31.03.2019 for 400kV D/C Kameng - Balipara Transmission Lines along with associated bays at Balipara Substation under �North East - Northern / Western Interconnector - I� in North-Eastern Region
Preliminary Scrutiny
 
272
120/MP/2019
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79 (1) (c) & (f) of the Electricity Act, 2003 read with the provisions of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations), 2010 to set aside the bills dated, 07.12.2018, 07.01.2019, 08.02.2019 and 08.03.2019 of the Central Transmission Utility (PGCIL) towards Transmission Charges (POC and HVDC charges)
Order reserved
 
273
119/MP/2019
NTPC Limited
Petition under Section 79(1)(a) and Section 79(1)(f) of the Electricity Act, 2003 read with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for relief on account of a Change in Law affecting Stage II of the Badarpur Thermal Power Station.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
274
117/MP/2019
Azure Power India Private Limited (APIPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 16.3.1 of the Power Purchase Agreement dated 27.04.2018 under the National Solar Mission Phase-II, Batch-IV, Tranche-XII seeking extension of the Scheduled Commissioning Date and stay of any coercive measures including stay of encashment of Performance Bank Guarantees.
Hearing
 
275
116/MP/2019
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Petition under Section 79 (1)(f) of the Electricity Act, 2003 read with CERC Tariff Regulations, 2014 for resolution of disputes regarding payment of capacity charges for the allocated capacity for Muzaffarpur Thermal Power Station (MTPS) Stage-II ( 2 X 195 MW)
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
276
115/MP/2019
GMR Kamalanga Energy Limited (GKEL)
Petition under Sections 79(1)(b) and (f) of the Electricity Act, 2003 read with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for recovery of dues owed by GRIDCO to GMR Kamalanga Energy Limited under Revised Power Purchase Agreement dated 04.01.2011
Hearing
 
277
114/MP/2019
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 (1) (b) and (f) of the Electricity Act, 2003 for adjudication of disputes arising out of Power Purchase Agreement dated 27.11.2013 executed between the Petitioners and the Respondent.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
278
113/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: Banaskantha-Chittorgarh 765 kV D/C line along with associated bays and 240 MVAR Switchable Line reactors at both ends, 765/400 kV Banaskantha ( New) S/S along with 765/400 KV ICT -1 & 2, 765 kV, 330 MVAr Bus reactor & 400 kV, 125 MVAr Bus reactor alongwith bays and Asset 2: Banskantha-Sankhari 400 kV D/C line along with associated bays at both ends under �Green Energy Corridors-Inter State Transmission Scheme (ISTS) Part-B� for tariff block 2014-19 period.
Preliminary Scrutiny
 
279
112/MP/2019
Tadas Wind Energy Private Limited (TWEPL)
Petition under Section 66 & 79 of the Electricity Act, 2003 read with Regulations 14 & 15 CERC (Terms and Conditions for recognition & issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 for issuance of directions to the Respondents to effect accreditation and registration of the Petitioner under the Renewable Energy Certificates (REC) mechanism and grant / issue the RECs.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
55/IA/2019
280
111/MP/2019
GMR Vemagiri Power Generation Ltd. (GVPGL)
Petition under Section 79 of the Electricity Act, 2003 read with PPA dated 31.03.1997 against the illegal and unlawful refusal of the Respondents to accept declaration of availability from the 370 MW combined cycle power station at Vemagiri, East Godavari District, Andhra Pradeh and consequent refusal to schedule power from the Project and pay applicable tariff including capacity charges for deemed generation.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
281
110/MP/2019
PTC India Limited PTC
Petition under Section 79(1)(f) of the Electricity Act, 2003 for adjudication of disputes arising out of and in relation to the power purchase of 200 MW of power by Haryana Power Purchase Centre from Teesta-II Hydroelectric Project of Teesta Urja Ltd. through PTC India Ltd.
Reply / additional information as per ROP to filed by Petitioner,Respondent
53/IA/2019 ,37/IA/2019
282
109/MP/2019
ACME Solar Holdings Ltd. (ASHL)
Petition under Section 79(1)(c) read with section 79(1)(f) of the Electricity Act 2003 and Regulation 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations 2009.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
283
108/MP/2019
ACME Solar Holdings Ltd. (ASHL)
Petition under Section 79(1)(c) read with section 79(1)(f) of the Electricity Act 2003 and Regulation 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations 2009.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
284
107/MP/2019
RATEDI WIND POWER PRIVATE LIMITED (RWPPL)
Petition under Section 66 & 79 of the Electricity Act, 2003 read with Regulations 14 & 15 CERC (Terms and Conditions for recognition & issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 for issuance of directions to the Respondent, National Load Despatch Centre to effect accreditation and registration of the Petitioner under the Renewable Energy Certificates (REC) mechanism and consequent reliefs.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
285
106/MP/2019
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Petition under Sections 79 (1)(c) and 79(1)(f) of the Electricity Act, 2003 read with the regulatory framework under the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access to the Inter-State Transmission and related matters), Regulations 2009, as amended from time to time, seeking issuance of appropriate directions to the generators, which are impleaded herein as Respondents, to execute the revised Implementation Agreements with fresh timelines for the expedient and efficient execution of the generation plants and the associated transmission system, which is being implemented by the Petitioner under the Uttarakhand Integrated Transmission Project (�UITP�) as Deemed Inter State Transmission System (�ISTS�), that is required for providing Long Term Open Access (�LTA�) for evacuation of power from the said generation plants and to also enter into tripartite Long Term Access Agreements (�LTA Agreements�) with the Petitioner and the Central Transmission Utility (�CTU�).
Reply / additional information as per ROP to filed by
 
286
105/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for �Tuticorin Pooling Station � Salem Pooling Station 765kV D/C line (initially charged at 400kV) along with Bay extensions at Salem PS and Tuticorin Pooling Station and 80 MVAR Line Reactors at each end of both circuits of Tuticorin Pooling Station � Salem Pooling Station 765kV D/C line (initially charged at 400kV) under Transmission System associated with Common System Associated with Coastal Energen Private Limited & Ind-Bharat Power (Madras) Limited LTOA Generation Projects in Tuticorin Area � Part-B�  in Southern Region in pursuance to direction of Hon�ble commission in Review Petition No. 40/RP/2017
Preliminary Scrutiny
 
287
6/RP/2019 in 278/TT/2015
ODISHA POWER TRANSMISSION CORPORATION LIMITED (OPTCL)
REVIEW PETITION UNDER SECTION 94 (1)(F) OF ELECTRICITY ACT, 2003 READ WITH REGULATION 103, 111 AND 114 OF THE CERC (CONDUCT OF BUSINESS) REGULATIONS, 1999, FOR REVIEW OF THE ORDER DATED 20.09.2017 IN PETITION NO. 278/TT/2015.
Hearing
 
288
104/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: Extension of Kota 400/220 kV Substation (POWERGRID) ? Shifting of 400 kV, 50 MVAR line reactor from Merta to Kota Substation for its use as Bus Reactor and 400 kV Bus reactor bay; Asset-II: Extension of Koteshwar 400/220kV Substation (THDC) ? installation of 400 kV, 125 MVAR bus reactor along with associated bay at Koteshwar; Asset-III: Extension of Dehar 400/220kV Substation (BBMB)- installation of 400kV, 1x63 MVAR bus Reactor-II through a single 400kV hybrid GIS bay and Asset-IV: Replacement  of 250MVA ICT with 4x105MVA, 1-phase ICT & retrofitting of associated 400/220kV bay equipment and protection relays at Dehar. under ?Strengthening Scheme in  Region?.
Preliminary Scrutiny
 
289
5/RP/2019 in 214/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Memorandum of Review Petition
Additional information as per Interim Order to be filed by Petitioner,Respondent
 
290
103/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for 2x1500MVA 765/400kV ICT�s along with associated bays at Srikakulam Pooling station under �Common System associated with East Coast Energy private limited and NCC power projects limited LTOA generation projects in Srikakulam Area -part-C� in Southern Region and Eastern region.
Preliminary Scrutiny
 
291
101/MP/2019
DAMODAR VALLEY CORPORATION (DVC)
Petition under Section 62(a) and 79(1) (a) of the Electricity Act, 2003 read with Regulation 8(3) (ii) and 8 (7) of the CERC (Terms and Conditions of Tariff) Regulations, 2014 read with Regulation 111 of the CERC (Conduct of Business) Regulations, 1999 for recovery of additional expenditure incurred due to sharing of transportation cost of fly ash consequent to Ministry of Environment and Forest, Government of India Notification dated 25.01.2016 as �Change in Law� Event.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
292
100/MP/2019
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition Under Section 79 (1)(b) and 79 (a)(f) of the Electricity Act, 2003 seeking adjudication of disputes arising out of the Agreement for Procurement of Power ("APP" dated 13.04.2016 and Supplementary Agreement dated 08.11.2017 executed between the Petition and the Respondent No.1
Hearing
 
293
97/MP/2019
MAGADH SUGAR & ENERGY LTD UNIT HASANPUR SUGAR MILLS (MAGADHSUGAR)
Petition under Section 79(1) of the Electricity Act, 2003 and Section 14 & 15 of Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010, challenging the illegal and arbitrary rejection of the Petitioner by Respondents, seeking change of name and/or re-accreditation.
Order reserved
 
294
96/TT/2019
Teestavalley Power Transmission Limited TPTL
PETITION UNDER SECTION 62 AND 79(1)(d) OF THE ELECTRICITY ACT 2003 READ WITH REGULATION 86 OF CERC (CONDUCT OF BUSINESS) REGULATIONS FOR DETERMINATION OF TRANSMISSION TARIFF OF THE 400 kV D/C RANGPO-KISHANGANJ SECTION, 2 NO. OF LINE BAYS AND 2 NO. OF 63 MVAR REACTORS OF 400 kV TEESTA III - KISHANGANJ TRANSMISSION SYSTEM FOR CONTROL PERIOD FY 2014-19 UNDER CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS 2014
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
295
94/MP/2019
DAMODAR VALLEY CORPORATION (DVC)
Petition under Section 79 of the Electricity Act, 2003 read with Regulation 14 (3) (ii) and Regulation 8 (3) (ii) of the CERC (Terms and Condition of Tariff) Regulations 2014 for approval of Expenditure on installation of various Emission control systems as detailed in this Petition for compliance of Ministry of Environment and Forests and Climate Change, Government of India Notification dated 07.12.2015.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
296
93/MP/2019
NTPC Limited
PETITION UNDER SECTION 79(1) (C) AND (F) OF THE ELECTRICITY ACT, 2003 FOR RESOLUTION OF DISPUTES REGARDING PAYMENT OF TRANSMISSION CHARGES FOR THE GADARWARA ATS.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
297
90/MP/2019
sks power generation (chhattisgarh) limited (SPGCL)
PETITION UNDER CLAUSE 12 AND 13 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (DEVIATION SETTLEMENT MECHANISM AND RELATED MATTERS) REGULATIONS, 2014 AS AMENDED FROM TIME TO TIME READ WITH REGULATIONS 2(1) (ff) AND (gg) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (INDIAN ELECTRICITY GRID CODE) REGULATIONS, 2010 FOR WAIVER OF VIOLATION AND ADDITIONAL DSM CHARGES ON ACCOUNT OF FORCE MAJEURE
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
298
87/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: 1 no. 500MVA 400/220kV Transformer along with associated bays at NP Kunta Sub-Station, Asset-2: 02 nos 220kV Line bays (Bay No 210 & 212) at NP Kunta sub-station and Asset-3: 02 nos 220kV Line bays (Bay No 209 & 211) at NP Kunta sub-station under �Transmission System for Ultra Mega Solar Park in Anantpur District, Andhra Pradesh - Part C (Phase-III)
Preliminary Scrutiny
 
299
86/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 02 Nos. 220kV Line bays at 765/400/220kV Fatehpur S/s(DOCO:28.05.2018) and Asset-II: 02 Nos. 400kV Line bays of 400kV D/C Barmer(RRVPNL)-Bhinmal(PG) line at Bhinmal S/s(Anticipated DOCO:31.01.2019) under � Line bays associated with various Regional Strengthening Schemes in NR�
Preliminary Scrutiny
 
300
85/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: +/-200 MVAR STATCOM at 400/220 kV Nalagarh S/s (Anticipated DOCO: 01.02.2019) and Asset-II: +/-300 MVAR STATCOM at 400kV Lucknow S/s (Anticipated DOCO: 01.02.2019) under �Provision of STATCOM at Nalagarh & Lucknow in Northern region�.
Preliminary Scrutiny
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
301
84/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: 765KV S/C Jaipur(RVPN)-Bhiwani TL (PART-I&II) along with associated bays under �Northern Region System Strengthening Scheme XXV� in Northern Region in pursuance to direction of Hon�ble commission in Review Petition No. 41/RP/2017.
Preliminary Scrutiny
 
302
83/MP/2019
Maharashtra State Electricity Distribution Company Limited (MSEDCL)
Petition under Section 19 of the Electricity Act 2003 seeking revocation of trading licensees for breach of contractual obligation by allowing the source generator to sell the power in exchanges instead of supplying to MSEDCL, as per contract/LOI.
Reply / additional information as per ROP to filed by Petitioner,Respondent
61/IA/2019 ,59/IA/2019
303
82/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCOs to 31.03.2019 for Asset-I: 02 nos 765kV Line Bays at 765kV Jharsuguda (Sundargarh) sub-station alongwith 02x240 MVAR Switchable Line Reactor (SLR) with 700 ohm NGR (Neutral Grounding Reactor) for termination of Jharsuguda (Sundargarh) � Raipur pool 765kV D/C line (under TBCB); Asset-II: 02 nos 765kV Line Bays at 765kV Raipur Pool station alongwith 02x240 MVAR Switchable Line Reactor (SLR) with 700 ohm NGR (Neutral Grounding Reactor) for termination of Jharsuguda (Sundargarh) � Raipur pool 765kV D/C line (under TBCB) under POWERGRID works associated with �TBCB lines under common transmission system for Phase-II generation projects in Odisha� in Eastern Region.
Preliminary Scrutiny
 
304
81/MP/2019
Chhattisgarh WR Transmission Limited (CWRTL)
Petition under Section 79 (1) (c) and (f) and other applicable provisions of the Electricity Act, 2003 inter-alia seeking a declaration that the factor/event, namely, direction of Power Grid Corporation Limited to re-route the LILO of One Circuit of 765kV D/C Aurangabad-Padghe Transmission Line at Shikarpur GIS, is a Force Majeure event under the TSA dated 24.06.2015 and further seeking extension of time period for achieving the SCoD of the Project under Article 4.4.2 of the TSA and other consequential reliefs.
Reply / additional information as per ROP to filed by Petitioner,Respondent
51/IA/2019
305
80/MP/2019
CHETTINAD CEMENT CORPORATION PVT LTD (CCCPL)
Petition under Section 79(1)(c ) and 79(1)(f) of the Electricity Act, 2003 read with applicable provisions of the Central Electricity Regulatory Commission (Open Access in Inter- state transmission) Regulations, 2008
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
306
78/MP/2019
Shri Ambalika Sugar Pvt Ltd Ambikanagar (SASPL)
The Petition is filed seeking condonation of delay in applying for issuance of Renewable Energy Certificates against eligible quantum of renewable energy injected into the grid; and consequently for issuance of the certificates by the Respondent.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
307
76/MP/2019
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
Petition under section 79 (1) (f) of the Electricity Act, 2003 for the recovery of dues from the respondent (Punjab State Power Corporation Limited).
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
308
75/MP/2019
Azure Power Forty Three Private Limited Azure43
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and Solar Energy Corporation of India Limited dated 31.10.2018 seeking relief on account of a 'Change in Law' viz. the Notification Nos. 24 and 27 of 2018- Central Tax (Rate) and 25 and 28 of 2018 ? Integrated Tax (Rate) dated 31.12.2018 issued by the Ministry of Finance, Government of India, inter alia effectively amending the Goods and Services Tax rates relating to setting up of solar power projects, resulting in additional non-recurring expenditure in the form of an additional tax burden to be borne by the Petitioner with effect from 01.01.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
309
74/MP/2019
Azure Power India Private Limited (APIPL)
Petition under Section 79 of the Electricity Act, 2003 read with the Letter of Award dated 29.10.2018 and Article 12 of the draft Power Purchase Agreement issued by NTPC Limited inter alia seeking declaratory and compensatory reliefs on account of a 'Change in Law' viz. the issuance of Notification Nos. 24 and 27 of 2018- Central Tax (Rate) and 25 and 28 of 2018 � Integrated Tax (Rate) dated 31.12.2018 by the Ministry of Finance, Government of India, inter alia effectively amending the Goods and Services Tax rates applicable on setting up of solar power projects, resulting in additional non-recurring expenditure in the form of an additional tax burden applicable with effect from 01.01.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
57/IA/2019
310
71/MP/2019
Sasan Power Limited (SPL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Power Purchase Agreement dated 07.08.2007 executed between Sasan Power Limited and the Procurers for compensation and restoration of project economics due to unprecedented, unforeseen and uncontrollable depreciation of the INR vis a-vis USD pursuant to Hon�ble Appellate Tribunal for Electricity�s Judgment dated 18.01.2019 in Appeal No. 202 of 2016.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
311
70/MP/2019
SOLAR EDGE POWER AND ENERGY PRIVATE LIMITED (SEPEPL)
A petition before the Central Electricity Regulatory Commission seeking an appropriate mechanism for grant of an appropriate adjustment/ compensation to offset financial/ commercial impact of change in law events on account of imposition of Goods and Service Tax
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
312
68/MP/2019
Fermi Solarfarms Private Limited
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements executed between the Petitioner and the Respondent for seeking approval of GST laws as an event under ?Change in Law? and consequential relief.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
313
67/MP/2019
Clean Sustainable Energy Private Limited (CSEPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement executed between the Petitioner and the Respondent No.1 for seeking declaration of and relief for Change in Law.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
314
66/MP/2019
Punjab State Power Corporation limited (PSPCL)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 5 and 7 of the Central Electricity Regulatory Commission (Deviation, Settlement Mechanism and related matters) Regulations, 2014 as amended by the Fourth Amendment Regulations, 2018 effective 1.1.2019
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
315
65/MP/2019
NTPC Limited
Petition for Recovery of money from the Rajasthan Distribution Companies for the power supplied from June, 2017 to April, 2018 under the Power Sale Agreement dated 26.02.2016 entered into between NTPC Limited and the Rajasthan Distribution Companies.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
316
64/MP/2019
Sprng Agnitra Private Limited (SprngAgnitra)
PETITION UNDER SECTION 79(1)(B) READ WITH SECTION 79(1)(F) OF THE ELECTRICITY ACT, 2003 ALONG WITH SECTION 79 (1)(K) OF THE ELECTRICITY ACT, 2003 FOR (I) DECLARATION OF EVENTS AS �CHANGE IN LAW� UNDER THE POWER PURCHASE AGREEMENT DATED 05.07.2018; AND (II) GRANT OF CONSEQUENTIAL RELIEF TO COMPENSATE FOR THE INCREASE IN CAPITAL COST DUE TO INTRODUCTION AND IMPOSITION OF SAFE GUARD DUTY BY WAY OF  NOTIFICATION NO.01/2018- CUSTOMS SG DATED 30.07.2018 ISSUED BY THE DEPARTMENT OF REVENUE, MINISTRY OF FINANCE, IN TERMS OF ARTICLE 12 OF THE POWER PURCHASE AGREEMENT DATED 05.07.2018 EXECUTED BETWEEN SPRNG AGNITRA PRIVATE LIMITED AND NTPC LIMITED.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
317
63/MP/2019
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 inter alia seeking recovery of Capacity Charges/ Damages under the Power Purchase Agreements both dated 01.11.2013 entered into between the Petitioner and the Respondents
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
318
62/MP/2019
NOIDA POWER COMPANY LIMITED NPCL
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 5 and 7 of the Central Electricity Regulatory Commission (Deviation, Settlement Mechanism and related matters) Regulations, 2014 as amended by the Fourth Amendment Regulations, 2018 effective from 1.1.2019
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
319
61/MP/2019
Karma Energy Limited (Karen)
Petition seeking directions against the Respondent, National Load Dispatch Center in the matter of issuance of the Renewable Energy Certificates to the Petitioners for the specified period
Hearing
 
320
60/MP/2019
Maharashtra State Electricity Distribution Company Limited (MSEDCL)
Petition for Seeking relief against scheduling of suo-moto power to Maharashtra State Electricity Distribution Company Limited by Western Regional Load Despatch Center
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
321
58/MP/2019
Vaayu Renewable Energy (Krishna) Private Limited (VaayuKrishna)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in Inter State Transmission and related matters) Regulations, 2009 for time extension of achieving financial closure as provided under Clause 9.3.2 of the Detailed Procedure issued by the Central Commission for `Grant of Connectivity to projects based on Renewable sources to the Inter State Transmission System� dated 15.05.2018
Order reserved
 
322
57/MP/2019
Vaayu Renewable Energy (Kaveri) Private Land (VaayuKaveri)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in Inter State Transmission and related matters) Regulations, 2009 for time extension of achieving financial closure as provided under Clause 9.3.2 of the Detailed Procedure issued by the Central Commission for `Grant of Connectivity to projects based on Renewable sources to the Inter State Transmission System� dated 15.05.2018
Order reserved
 
323
56/MP/2019
Vaayu Renewable Energy (Sironj) Private Limited (VaayuSironj)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in Inter State Transmission and related matters) Regulations, 2009 for time extension of achieving financial closure as provided under Clause 9.3.2 of the Detailed Procedure issued by the Central Commission for `Grant of Connectivity to projects based on Renewable sources to the Inter State Transmission System� dated 15.05.2018
Order reserved
 
324
55/MP/2019
Vaayu Renewable Energy (Mevasa) Private Limited (vaayumevasa)
Petition under Section 79 (1) (c) of the Electricity Act, 2003 read with Regulations 27 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in Inter State Transmission and related matters) Regulations, 2009 for time extension of achieving financial closure as provided under Clause 9.3.2 of the Detailed Procedure issued by the Central Commission for `Grant of Connectivity to projects based on Renewable sources to the Inter State Transmission System�
Order reserved
 
325
54/MP/2019
TRN ENERGY PRIVATE LIMITED
Adjudication of disputes under Section 79 of the Electricity Act, 2003
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
326
52/MP/2019
Solitaire Powertech Private Limited (SPPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 for (i) approval of ?Change in Law?; and (ii) consequential relief to compensate for the increase in capital cost due to introduction of the Central Goods and Services Tax Act, 2017, the Integrated Goods and Services Tax Act, 2017 and the State Goods and Services Tax Acts enacted by respective states, in terms of Article 12 of the power purchase agreement dated 02.08.2016 between Solitaire Powertech Private Limited and Solar Energy Corporation of India Limited.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
327
51/MP/2019
Azure Power Forty Three Private Limited Azure43
PETITION UNDER SECTION 79(1)(B) READ WITH SECTION 79(1)(F) OF THE ELECTRICITY ACT, 2003 FOR THE DECLARATION OF ?CHANGE IN LAW? EVENT DUE TO INTRODUCTION AND IMPOSITION OF SAFEGUARD DUTY BY WAY OF  NOTIFICATION NO.01 / 2018 - CUSTOMS (SG) DATED 30.07.2018 ISSUED BY THE DEPARTMENT OF REVENUE, MINISTRY OF FINANCE, GOVERNMENT OF INDIA, IN TERMS OF ARTICLE 12 OF THE POWER PURCHASE AGREEMENTS DATED 31.10.2018 EXECUTED BETWEEN THE PETITIONER AND THE RESPONDENT.
Hearing
 
328
50/MP/2019
BALRAMPUR CHINI MILLS LIMITED (BCML)
The Petition is filed seeking condonation of delay in applying for issuance of Renewable Energy Certificates against eligible quantum of renewable energy injected into the grid; and consequently for issuance of the certificates by the Respondent.
Hearing
 
329
49/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for Transmission Asset �ASSET- 1: Tumkur (Pavagada) pool-Hiriyur 400KV D/C line along with associated bays & equipments at both ends under Transmission System for Ultra mega Solar Power Park at Tumkur (Pavagada), Karnataka-Phase-I�.
Preliminary Scrutiny
 
330
48/MP/2019
REGEN WINDFARM ( VAGARAI) PVT LTD REGEN
Petition under Regulation 32 and 33A of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term and Medium Term Open Access in inter-State transmission and related matters) Regulations, 2009 and Detailed Procedure of the Central Electricity Regulatory Commission, Delhi dated May 15, 2018 for extension of time for filing of documentation under Clause 5.1 and Clause 9.2 of the Detailed Procedure and Deemed Stage II Connectivity accorded by POWERGRID Corporation of India (Ltd.) to Regen Wind Farm (Vagarai) Pvt. Ltd.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
331
47/MP/2019
Avaada Clean Energy Pvt. Ltd. AvaadaClean
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements executed between the Petitioner and the Respondent for seeking approval of Safeguard Duty as an event under �Change in Law�.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
332
45/MP/2019
TALETTUTAYI SOLAR PROJECTS ONE PVT LTD (TT1)
Petition under Section 79 (1) (b) & (f) of the Electricity Act, 2003 read with read with Article 12 of the Power Purchase Agreements dated 02.08.2016, executed between the Petitioner and Solar Energy Corporation of India Ltd.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
333
44/MP/2019
ACME Jaipur Solar Power Private Limited (AJSPPL)
A petition before the Central Electricity Regulatory Commission seeking compensation/ charges against the arbitrary deductions made by the Respondent from the tariff payments made to the Petitioner.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
334
43/MP/2019
Prayatna Developers Private Limited (PDPL)
Petition under Sections 79 of the Electricity Act, 2003 read with Article 12 of the PPAs dated 16.09.2016 claiming Carrying Cost on Change in Law compensation granted by the Order of the Ld. Commission dated 19.09.2018 in Petition No 50/MP/2018.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
335
42/MP/2019
Indian Railways ECR
Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Regulations 8(5) and 8(6) of the Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, read with Clause 4 of the Bulk Power Transmission Agreement dated 08.01.2010; read with Clause 12 of the Bulk Power Transmission Agreement entered into between PGCIL and various Electricity Boards for the Western Region dated 31.03.1999; Clause 14 of the Bulk Power Transmission Agreement entered into between PGCIL and various State Electricity Boards for the Eastern Region dated 16.09.2004; and Clause 13 of the Bulk Power Transmission Agreement entered into between PGCIL and Haryana Vidyut Prasaran Nigam Limited for the Northern Region dated 16.10.2003 challenging the levy of Transmission Charges on East Central Railway by PGCIL
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
336
41/MP/2019
North Karanpura Transmission Company Limited (NKTCL)
Petition under Section 73(n), 79(1)(c) and 79(1)(f) and other Applicable Provisions of the 2003 Act and in terms of Hon'ble Appellate Tribunal's Order dated 01-02-2019 read with Order dated 07-02-2019 in Appeal No. 200/15 and 201/15
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
337
40/MP/2019
Talcher-II Transmission Company Limited (TTCL)
Petition under Section 73(n), 79(1)(c) and 79(1)(f) and Other Applicable Provisions of the 2003 Act and in terms of Hon'ble Appellate Tribunal's Order dated 01-02-2019 read with Order dated 07-02-2019 in Appeal No. 200/2015 and 201/2015
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
338
39/MP/2019
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 read with PPA dated 21.03.2013 for (i) resolution of bill dispute; (ii) recovery of amounts due to GMR Warora Energy Limited pursuant to Supplementary Bills raised; and (iii) implementation of  Orders of this Hon?ble Commission namely, Order dated 01.02.2017 in Petition No. 8/MP/2014, Order dated 14.03.2018 in Petition No. 13/SM/2017, Order dated 16.03.2018 in Petition No. 1/MP/2017 and Order dated 15.11.2018 in Petition No. 88/MP/2018
Order reserved
 
339
35/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for ASSET-1:1x500MVA,400/220/33kV ICT along with associated bays at Trichy Substation under System strengthening-XX�  in Southern Region.
Preliminary Scrutiny
 
340
34/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Asset-I 400 kV D/C Hiriyur � Mysore transmission line along with associated bays and 2X80 MVAR switchable line reactors alongwith associated bays at 400/220 kV Mysore S/S, Asset-II: 2X500 MVA 400/220 kV  ICTs along with  associated bays at Tumkur (Pavagada)S/S Asset-III: 1X500 MVA 400/220 kV  ICT along with associated bays and equipments at Tumkur (Vasantnarsapur) S/S under Transmission system for Ultra Mega Solar Power Park at Tumkur (Pavgada), Karnataka - Phase II (Part A)
Preliminary Scrutiny
 
341
33/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 3X110 MVAR, 765kV Bus Reactor �I at 765/400kV Varanasi GIS (Reactor shifting from Sasaram S/S) under �Transmission System for Phase I Generation Projects in Jharkhand and West Bengal Part A2�.
Hearing
 
342
32/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: 02 Nos. 400kV bays  at Samba Substation for Amargarh to Samba (POWERGRID) transmission line along with 02 Nos. 50 MVAR Non switchable line Reactors under Northern Region System Strengthening Scheme-XXIX (NRSS-XXIX) in Northern Region.
Preliminary Scrutiny
 
343
31/MP/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under Regulations 12 and 13 of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014, read with Regulations 111 and 112 of the CERC (Conduct of Business) Regulations, 1999 seeking relaxation of the proviso to Regulation 7(1), Regulations 7(10) and 7(11a) of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014, as amended vide Amendment dated 20.11.2018.
Hearing
18/IA/2019 ,60/IA/2019
344
30/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Raipur Pooling Station � Wardha 765 kV 2nd D/C line along with bay extension and equipment at 765kV Raipur Pooling station & Wardha substation under �System Strengthening in Raipur - Wardha Corridor for IPP Projects in Chhattisgarh (IPP-F)� for determination of transmission tariff from DOCO to 31.03.2019 as per directive of Hon�ble Commission vide Order dated 11.07.2018 in Petition 42/RP/2017.
Hearing
 
345
29/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for ASSET-I: 1X125 MVAR 400KV Bus reactor alongwith associated bays at Cuddapah S/S, 1X240 MVAR 765KV Bus reactor alongwith associated bays at Kurnool S/S, 1X240 MVAR 765KV Bus reactor alongwith associated bays at Nellore PS S/S, 1X240 MVAR 765KV Bus reactor alongwith associated bays at Raichur S/S, Asset-II: 2X240 MVAR 765 kV Bus Reactors alongwith associated bays at Thiruvalam S/S under Installation of Bus reactors at Cuddapah, Nellore PS, Kurnool, Raichur and Thiruvalam in Southern Region.
Hearing
 
346
28/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset- 1 : 2 nos. 220 kV Line Bays at 400/220 kV Damoh S/S , Asset-2 : 400/220 kV, 500 MVA, ICT 1 & 2 with associated bays and 2 nos. 220kV downstream bays at Vadodara substation and  Asset-3: 2 nos. 220kV downstream bays at Vadodara substation upon determination of final transmission tariff as per directive of Hon�ble Commission vide order dated 04.07.2018 for Review petition no. 06/RP/17 in petition no. 208/TT/2016 Under �Installation of Bus Reactor & ICT in Western Region � project for tariff block 2014-19 period.
Hearing
 
347
2/RP/2019 in 95/MP/2017
SOLAR ENERGY CORPORATION OF INDIA LIMITED (SECI)
Petition seeking review of order dated 17.12.2018 passed by this Hon'ble Commission in Petition No. 95/MP/2017
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
348
26/MP/2019
ACME Jaipur Solar Power Private Limited (AJSPPL)
Petition before the Central Electricity Regulatory Commission seeking appropriate compensation for the charges to be paid to the Petitioner in respect of solar energy injected into the grid for the period from the date of synchronization of the initial part capacity of the project upto the date of receipt of the commissioning certificate for such initial part capacity
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
349
25/MP/2019
Indian Energy Exchange Ltd. (IEX)
Petition under Section 66 of The Electricity Act, 2003 read with the Regulation 7 of the Central Electricity Regulatory Commission (Power Market) Regulations, 2010 for approval of introduction of the Green Term-Ahead Market (Renewable Energy) Contracts at Indian Energy Exchange Ltd.
Interim order issued
 
350
24/MP/2019
Coastal Gujarat Power Limited (CGPL)
Petition under Section 79 (1)(b) of the Electricity Act, 2003 read with Article 18.1 of Power Purchase Agreement dated 22.04.2007 for Implementation of the Recommendations issued by the High-Power Committee vide its Report dated 03.10.2018, as ratified by the Policy Decision of the Government of Gujarat issued by Government Resolution dated 01.12.2018.
Hearing
45/IA/2019
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
351
22/MP/2019
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 8.3 of the Power Purchase Agreement dated 19.08.2013 entered into between the Petitioner and the Respondent, for recovery of Late Payment Surcharge on account of delay in payment of Monthly Bills of the Petitioner by the Respondent
Order reserved
 
352
21/MP/2019
Adani Renewable Energy Park Rajasthan Limited (AREPRL)
Petition under Section 79 (1) (c) and (f) and other applicable provisions of the Electricity Act, 2003 seeking extension of SCoD of the Project due to occurrence of force majeure events covered under Article 11 of the TSA dated 10.01.2018 executed between the Petitioner and Respondent No. 1 M/s FBTL; and further seeking extension of LTA operational time under the LTAAs dated 22.09.2016 executed between Petitioner and Respondent No. 2, PGCIL on account of ?Change in Law? as covered under Clause 5.7 of the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects issued by Govt. of India on 03.08.2017 and as further amended on 14.06.2018
Hearing
14/IA/2019
353
20/MP/2019
NHPC LTD
Petition under Section 66, 142 & 149 of the Electricity Act, 2003 read with Regulation 24, 37(ii), 53, 63 & 64 of CERC (Power Market) Regulations, 2010 for seeking urgent intervention of Hon�ble Commission and issue of appropriate direction to Indian Energy Exchange (IEX) and Power Trading Corporation (PTC) of India Ltd.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
35/IA/2019
354
18/MP/2019
Coastal Andhra Power Limited CAPL
Petition under Section 79 of the Electricity Act, 2003 read with Article 17 of the PPA dated 23.03.2007 between Coastal Andhra Power Limited and Distribution licensees of States of Andhra Pradesh, Telangana, Maharashtra, Karnataka and Tamil Nadu seeking reference of disputes between CAPL and Procurers to Arbitration.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
355
16/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 2 Nos. 765kV line bays at 765/400kV Raipur Pooling Station (POWERGRID) for Raipur PS (POWERGRID)- Rajnandgaon(TBCB) 765kV D/c line under �POWERGRID works associated with additional System Strengthening Scheme for Chhattisgarh IPPs (Part-B)� for tariff block 2014-19 period.
Preliminary Scrutiny
 
356
15/MP/2019
JHAJJAR POWER LIMITED (JPL)
Petition under Section 79(1) (b) and 79 (1) (f) of the Electricity Act, 2003 for declaration that any variation in the cost of fuel ?invoiced? to the Petitioner, owing to any increase in rate of taxes, levies, cess or duties which includes but is not limited to royalty, central excise duty, S.E.D. CST, energy cess, sizing charges, surface transportation, and also enactment of new taxes/royalties on the coal cost which includes but is not limited to NMET, DMF, forest transit fee and PWD cess, imposed by the Central Government, State Government/Union Territory, or any other Government, being a component of invoiced rate of coal, is a pass-through cost as per the terms of the PPA dated 07.08.2008
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
357
12/MP/2019
M.P. Power Management Co. Ltd. (MPPMCL)
PETITION UNDER SECTIONS 79 (1) (c) (F), (K) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 IN CONNECTION WITH THE DISPUTES AND DIFFERENCES ARISING DUE TO BREACH OF POWER PURCHASE AGREEMENT DATED 08.08.2005 ENTERED BETWEEN PETITIONER AND RESPONDENT NO1 AND CLAIM FOR  DAMAGES & COMPENSATION
Hearing
64/IA/2019
358
11/RC/2019
Indian Energy Exchange Ltd. (IEX)
Introduction of New Bid (Order) Types at Indian Energy Exchange
Reply / additional information as per ROP to filed by Petitioner
 
359
10/TT/2019
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED (APTRANSCO)
Petition for Determination of tariff of the inter-State transmission lines connecting two states for the APTRANSCO owned transmission lines/system as per the Central Electricity Regulatory Commission�s order dated 05.09.2018 in Petition No. 07/Suo-Motu/2017 and order dated 21.6.2018 in petition No. 237/TT/2016 for inclusion in POC Transmission charges in accordance with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for FY 2014-15 (40 Nos. ISTS lines), FY 2015-16 (40 Nos. ISTS lines), FY 2016-17 (2 Nos. ISTS lines), FY 2017-18 (42 Nos. ISTS lines) and FY 2018-19 (42 Nos. ISTS lines) .
Hearing
 
360
9/TT/2019
Chhattisgarh State Power Transmission Company Limited (CSPTCL)
Petition for determination of Transmission Tariff from FY 2014-15 to FY 2018-19 of the Transmission Lines belonging to the Petitioner (CSPTCL) conveying electricity as ISTS lines, for inclusion of these assets in computation of Point of Connection, Transmission Charges and Losses in accordance with the CERC (Terms & Conditions of Tariff) Regulations 2014 and (Sharing of Inter-State Transmission Charges and Losses), Regulations, 2010 namely;
(i) Kotmikala- Amarkantak-1, 220 kV Line
(ii) Kotmikala- Amarkantak-2, 220 kV Line
(iii) Raigarh ? Budhipadar, 220 kV Line
(iv) Korba ? Budhipadar, 220 kV Line
(v) Seoni- Bhilai 400 kV Line
Hearing
 
361
8/MP/2019
Ratnagiri Gas and Power Private Limited (RGPPL)
Petition for relaxation/modification of the provisions of the India Electricity Grid Code (Fourth Amendment) Regulations, 2016 and the Central Electricity Regulatory Commission (Deviation and Settlement Mechanism and related matters) (Fourth Amendment) Regulations, 2018 in respect of the schedule for operation of the Ratnagiri Gas Power Station
Hearing
 
362
5/MP/2019
ITC Limited
Memorandum of original petition under section 79 (1) of the Electricity Act, 2003 and sections 14 and 15 of the Central Electricity Regulatory Commission (Terms and Conditions for Recognition and Issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010, challenging the rejection of renewable energy certificate application of the petitioner by the respondent.
Order reserved
 
363
4/MP/2019
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 02.08.2016, executed between Parampujya Solar Energy Private Limited. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
364
2/TT/2019
TRANSMISSION CORPORATION OF TELANGANA LTD (TSTRANSCO)
Determination of tariff for the TSTRANSCO owned Inter State Transmission Lines/System of the 38 Nos. natural Inter-State Transmission lines connecting Telangana and Andhra Pradesh States as per the Central Electricity Regulatory Commission order dated 14.03.2012 in petition No15/Suo-Motu/2012, for inclusion in PoC Transmission charges in accordance with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
Order reserved
 
365
1/TT/2019
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
1. Approval under Regulation 6(1) & 15 of  CERC(Terms and Conditions of Tariff) Regulation 2009 & Regulation -6 of CERC ( Terms and Conditions of Tariff) Regulations�2014 for true up of transmission tariff for 2009-14 period & determination of transmission tariff for 2014-19 period for assets under Common Scheme for 765 kV Pooling Station and Network for NR, Import by NR from ER and Common Scheme for network for WR and Import by WR from ER and from NER/SR/WR via ER in Eastern, Northern and Western Region.
Order reserved
 
366
395/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 04.08.2016, executed between the Parampujya Solar Energy Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
367
394/MP/2018
PTC India Limited PTC
Petition under Section 79 (1) (c) & (f) of the Electricity Act, 2003, rad with Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in inter-State Transmission and related matters) Regulations, 2009, seeking directions in respect of an alleged LTOA of 216 MW granted to PTC India Limited for Merchant Trading of power from 1200MW Teesta-III Hydroelectric Project in terms thereof.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
368
391/MP/2018
Northern Railway (NR)
Agreement for Procurement of Power dated 13.04.2016 between Northern Railways for Uttar Pradesh and Jindal India Thermal Power Limited read with the Supplementary Agreement dated 08.11.2017
Hearing
 
369
389/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition for the recovery of charges from PGCIL under Clause 6.0 (d) of the Bulk Power Transmission Agreement dated 24.02.2010 read with Regulation 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in inter-State Transmission and related matters) Regulations, 2009.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
370
388/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
371
387/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from Anticipated DOCO to 31.03.2019 for 400kV D/C Mundra UMPP � Bhuj (Triple Snowbird) Transmission Line alongwith extension of 400kV Mundra UMPP Switchyard and 400kV Bhuj Pooling Station under Transmission System Strengthening Associated with Mundra UMPP (Part-B).
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
372
384/MP/2018
KUDGI TRANSMISSION LIMITED (KTL)
Approval for creation of security for refinanced debt
Hearing
 
373
382/MP/2018
NTPC Limited
Petition under Section 79 of the Electricity Act read with Regulations 15 & 16 of the CERC (Ancillary Services Operations) Regulations, 2015 seeking the exercise of the power to relax and remove difficulties on the aspect of the severe under-recovery of variable charges under Regulation 13.3 for the Five (5) Gas Based Generating Stations of NTPC, the Petitioner
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
374
380/MP/2018
IL&FS Tamil Nadu Power Company Limited ITPCL
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 read with Article 10 of the Power Purchase Agreement dated 12.12.2013 executed between the Petitioner and the Respondent for claiming compensation on account of events pertaining to change in law
Hearing
 
375
378/MP/2018
Rajasthan Sun Technique Energy Private Ltd RSTEPL
The Power Purchase Agreement 8th January 2011 (?PPA?) entered into between NTPC Vidyut Vyapar Nigam Limited and Rajasthan Sun Technique Energy Pvt Ltd
Hearing
 
376
375/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 1x63MVAR,400kV Bus Reactor-I at 400/220kV Sohawal Sub-station, Asset-II: 1x63MVAR,400kV Bus Reactor-II at 400/220kV Sohawal Sub-station, Asset-III: 2 nos. 220kV bays of 220kV(PG)-Sohawal(UP) TL at 400/220kV Sohawal(PG) Substation, Asset-IV:2 nos. 220kV bays No. 208 & 209 (Barabanki-I &II of UPPTCL) at 400/220kV Sohawal(PG) Substation, Asset-V: 02 nos 220 kV Line Bays of Sohawal (PG)-Tanda (UP) TL at 400/220kV Sohawal(PG) Substation, Asset-VI: 2 nos. 220kV bays No. 206 & 207 of Shahjahanpur(PG)-Shahjahanpur(UPPTCL) at 400/220kV Shahjahanpur Sub-Station, Asset-VII: 1 Nos, 220kV line bays No. 210 of Shahjahanpur(PG)-Shahjahanpur(UPPTCL) at 400/220kV Shahjahanpur Sub-Station, Asset-VIII: 1 Nos, 220kV line bays No. 211 of Shahjahanpur(PG)-Shahjahanpur(UPPTCL) at 400/220kV Shahjahanpur Sub-Station, Asset-IX: 2 Nos. 220kV Line bays (Vatika-I and Vatika-II) at 400/220kV Jaipur(South) Substation, Asset-X: 2 Nos. 220kV line bays(211 and 212) at 400/220kV  Jaipur (South) Substation under �Northern Regional Transmission Strengthening Scheme� in Northern Region�.
Order reserved
 
377
373/MP/2018
BSES YAMUNA POWER Ltd. (BYPL)
Petition invoking Section 79(1)(b) and Section 79(1)(f) of the Electricity Act, 2003 read with Regulation 111 of the CERC (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner, i.e., BSES Yamuna Power Limited and Damodar Valley Corporation.
Hearing
 
378
369/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of the generating station during the FY 2016-17 in respect of Bairasiul Power Station.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
379
368/TT/2018
Teestavalley Power Transmission Limited TPTL
APPROVAL UNDER SECTION 62 AND 79(1)(d) OF THE ELECTRICITY ACT 2003 READ WITH REGULATION 86 OF CERC (CONDUCT OF BUSINESS) REGULATIONS FOR DETERMINATION OF TRANSMISSION TARIFF FOR CIRCUIT 1 (b) OF 400 kV D/C TEESTA III - RANGPO SECTION UPTO LILO POINT AT RANGPO FOR CONTROL PERIOD OF FY 2014-19 UNDER CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS 2014
Order reserved
 
380
367/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for  determination of    Transmission Tariff  from DOCO to 31.03.2019 for �Salem Pooling Station � Madhugiri Pooling Station 765kV S/C Line (initially charged at 400kV) along with associated Bays & equipments at Salem PS and Madhugiri PS and 400KV 63 MVAR line reactor at Madhugiri end only of the Salem Pooling Station � Madhugiri 765kV S/C Line (Initially charged at 400kV) under Common System Associated with Coastal Energen Private Limited & Ind-Bharat Power (Madras) Limited LTOA Generation Projects in Tuticorin Area � Part-B� in Southern Region.
Order reserved
 
381
366/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for assets under �POWERGRID works associated with System Strengthening for IPPs in Chhattisgarh and other generation projects in Western Region� for tariff block 2014-19 period.
Hearing
 
382
365/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1- Extension of 220kV Navsari (GIS) Substation: 2 Nos line bays and Asset 2- Extension of 400kV Vadodara (GIS) substation: 3 nos of bays ( 2 nos line bays & 1 no. bus reactor bay)  including 1x 125 MVAR, 400kV Bus reactor under �Transmission System associated with DGEN (1200 MW) of Torrent Power Ltd� in Western Region.
Hearing
 
383
364/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of Transmission Tariff for Asset-I: 400kV D/C Silchar-Melriat transmission line (Charged at 132kV) alongwith associated bays, Asset-II: LILO of  132kV S/C Aizawl-Zemabawk Transmission Line along with associated bays at Melriat S/S (New), Asset-III: 132kV D/C Melriat (New)� Sihhmui Transmission Line alongwith associated bays, Asset-IV: 4x5MVAr (including 01 no hot spare), 132kV, 1-ph, Bus Reactor at Melriat S/S alongwith Melriat (PG) GIS Substation from anticipated DOCO to 31.03.2019 under the transmission system associated with �Transmission system associated with Pallatana GBPP and Bongaigaon TPS�.
Order reserved
 
384
363/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for approval of Transmission Tariff from DOCO to 31.03.2019 for  Asset-I: � � 800 kV HVDC Biswanath Chariali � Agra Pole-I (1500 MW HVDC Terminals each at Biswanath Chariali and Agra with � 800 kV Hexa Lapwing Transmission Line), Asset-II: Loop In and Loop Out (LILO) of 400kV Ranganadi-Balipara-I T/L at Biswanath chariali PS alongwith associated bays at Biswanath chariali PS, Asset-III: Loop In and Loop Out (LILO) of 400kV Ranganadi-Balipara-II T/L at Biswanath chariali PS alongwith associated bays at Biswanath chariali PS, Asset-IV: 132kV D/C Biswanath Chariali (PG) - Biswanath Chariali (AEGCL) T/L alongwith associated bays at Biswanath Chariali (AEGCL) and Biswanath Chariali Pooling Station (PGCIL), Asset-V: 200MVA, 400/132/33kV ICT � I at Biswanath Chariali PS,  Asset-VI: � 800kV Biswanath Chariali-Agra HVDC POLE-II (1500MW HVDC Terminal at Biswanath Chariali and Agra) along with Earth Electrode line and Earth Electrode Station for both Biswanath Chariali and Agra upon determination of final transmission tariff as per directive of Hon�ble Commission vide Order dated 12.07.2018 in Petition 43/RP/2017 Under �Transmission system associated with North East-Northern/Western Inter Connector-I� project for tariff block 2014-19 period.
Order reserved
 
385
362/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1- 63MVAr, 400 KV  Switchable Line Reactor along with 500 Ohms NGR at Rajgarh ( POWERGRID) end of Khargone TPS � Rajgarh (POWERGRID) 400kV line under  �POWERGRID Works associated with Transmission system Strengthening in WR associated with Khargone TPS� in Western Region.
Hearing
 
386
361/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for Asset-1: LILO of 400kV S/C Neelmangla-Hoody Transmission Line at new 400/220kV GIS Substation at Yelahanka with 1X63 MVAr 420kV Bus Reactor along with associated bays and equipments and Asset-2: 2X500MVA, 400/220kV ICT�s along with associated bays and equipments at 400/220kV Yelahanka Substation under System Strengthening XII in Southern Region.
Order reserved
 
387
359/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
388
358/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
389
356/MP/2018
Azure Power India Private Limited (APIPL)
Petition under Section 79(1)(b) and (f) of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the PPA executed by the Petitioner and Solar Energy Corporation of India Limited dated 27.04.2018 seeking relief on account of a �Change in Law� viz. the introduction of Safeguard Duty, resulting in additional recurring and non-recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the effective date of the PPA.
Hearing
 
390
355/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
391
354/GT/2018
NHPC LTD
Petition under section 79(1) & 86 of the CERC (Conduct of Business), Regulation 1999, section 62 (1) (a) of the Electricity Act 2003 and Regulation 7 (4)  & 14 of CERC (Terms & Conditions of Tariff) Regulations, 2014 in respect of Teesta Low Dam Power Station, Stage-IV for the period from 11.03.2016 (COD of first unit) to 31.03.2019
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
392
352/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
393
351/MP/2018
Coastal Energen Private Limited (CEPL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 read with Article 10 of the Power Purchase Agreement dated 19.12.2013 executed between the Petitioner and the Respondent No. 1 and in terms of the directions issued by the Central Government vide its notification dated 27.08.2018 for allowing pass through of additional expenditure incurred by the generator on account of events pertaining to change in law in an expeditious manner
Hearing
 
394
44/RP/2018 in 235/MP/2015
GUJARAT URJA VIKAS NIGAM LIMITED (GUVNL)
Memorandum of review Petition
Hearing
 
395
348/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Chamera-II Power Station.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
396
346/MP/2018
UDUPI POWER CORPORATION LTD (UPCL)
Petition under Section 79 (1) (b) of the Electricity Act, 2003 read with Regulation 14 (3)(ii) of the CERC Tariff Regulations, 2014, Article 1.1 (�Change in Law�) & 6.12 of the Power Purchase Agreements (�PPAs�) seeking regulatory certainty with respect to treatment of such cost for mandatory installation of additional systems in compliance with the Environment (Protection) Amendment Rules, 2015 issued by the Ministry of Environment, Forest and Climate Change dated 07.12.2015 for thermal power stations
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
397
345/MP/2018
M.P. Power Management Co. Ltd. (MPPMCL)
Treatment of power drawn by CTU connected 750 MW Rewa Solar Project during non-generation night hours and during shutdown periods and determination of tariff thereof.
Hearing
 
398
339/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(b), 79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the Central Electricity Regulatory Commission ( Grant of Connectivity, Long Term, Medium Term Open Access in Intra State and related matters) Regulations, 2009.
Hearing
 
399
337/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of Transmission Tariff for Asset-I: 3x5 MVA (132/33kV), 1-ph, ICT-I alongwith associated bays at Tezu substation, Asset-II:  4x5 MVA (132/33kV) (01 no spare), 1-ph, ICT-II alongwith associated bays at Tezu substation, Asset-III: 132kV S/C (on D/C Tower) Tezu-Namsai Transmission Line alongwith associated bays at Tezu and Namsai Substation, 4X6.67MVAR, 145kV, 1-ph Bus Reactor, 3X5MVA, 132/33kV, 1-ph ICT-I and 4X5MVA, 132/33kV 1-ph ICT-II (01 no spare phase) at Namsai Substation, from DOCO to 31.03.2019 under �Transmission system associated with Pallatana GBPP and Bongaigaon TPS�.
Order reserved
 
400
335/TT/2018
DAMODAR VALLEY CORPORATION (DVC)
Tariff petition for New Element and then combining with existing Asset Base of Existing
Order reserved
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
401
334/TT/2018
DAMODAR VALLEY CORPORATION (DVC)
Petition for ISTS  (400 kV Transmission Line - LILO DSTPS, LILO RTPS, DSTPS-RTPS , RTPS-RANCHI)
Order reserved
 
402
333/MP/2018
Indian Railways ECR
Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Regulations 6.3A and 6.3B of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 regarding the validity of the Commercial Operations Date of Units I and II of its generating station as declared by Bhartiya Rail Bijlee Company Limited
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
403
330/MP/2018
NHPC LTD
Application under Regulation-31(6) and Regulation-54&55 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of shortfall in energy charges due to reasons beyond control of Teesta Low Dam-III Power Station and recovery of shortfall in capacity charge under Regulation-54&55 due to agitation by GJMM in FY 2017-18.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
404
329/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of the generating station during the FY 2016-17 in respect of  Dhauliganga Power Station.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
405
328/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2017-18 in respect of   Sewa-II Power Station.
Reply / additional information as per ROP to filed by
 
406
327/MP/2018
DHARIWAL INFRASTRUCTURE LIMITED (DIL)
Petition under 79(1)(f) of the Electricity Act, 2003 for claiming compensation on account of occurrence of 'Change in Law' events as per Article 10.1.1 of the Case-1 long-term Power Purchase Agreement dated 27.11.2013 read with Addendum no. 1 dated 20.12.2013 entered into between Dhariwal Infrastructure Limited and Tamil Nadu Generation and Distribution Corporation Limited thereby resulting into additional recurring/non-recurring expenditure by Dhariwal Infrastructure Limited for supply of 100 MW Contracted Capacity from Unit 2 of its 2 x 300 MW Coal based thermal generating station located at Tadali, Chandrapur in the State of Maharashtra to Tamil Nadu Generation and Distribution Corporation Limited.
Additional information as per Interim Order to be filed by Petitioner,Respondent
87/IA/2018
407
325/MP/2018
UDUPI POWER CORPORATION LTD (UPCL)
Petition under Section 142 read with Section 79(1)(b) and (f) of the Electricity Act, 2003 read with Article 7.2(b) of the Power Purchase Agreement dated 26.12.2005
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
408
324/MP/2018
UDUPI POWER CORPORATION LTD (UPCL)
Petition filed under Section 79(1)(b) of the Electricity Act, 2003 read with Article 7(2)(b) of the Power Purchase Agreement dated 26.12.2005.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
409
322/GT/2018
NHPC LTD
Petition under regulation 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 7(4) & 14 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of final tariff for the period 2014-19 in respect of Sewa-II Power Station.
Order reserved
 
410
321/GT/2018
NHPC LTD
Petition under section 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 7(4) & 14 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of final tariff for the period 2014-19 in respect of Chamera-III Power Station.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
411
320/GT/2018
NHPC LTD
Tariff petition for determination of final tariff for the period 2014-19 in respect of Teesta Low Dam-III Power Station
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
412
316/MP/2018
NHPC LTD
Application under Regulation-31(6) and Regulation-54&55 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of shortfall in energy charges due to reasons beyond control of Teesta Low Dam-IV Power Station and recovery of shortfall in capacity charge under Regulation-54&55 due to agitation by GJMM in FY 2017-18.
Order Reserved- Additional information for final order to be filed by Petitioner
 
413
40/RP/2018 in 175/TT/2017
DELHI TRANSCO LIMITED (DTL)
Memorandum of Review Petition
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
414
311/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from Anticipated DOCO to 31.03.2019 for 2 x 500MVA, 400/220kV ICTs along with associated transformer bays & 6 no. 220kV line bays at 400/220kV Indore substation under Western Region System Strengthening Scheme-XIV.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
415
38/RP/2018 in 116/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the Order dated 20.07.2018 passed by this Hon�ble Commission in Petition No. 116/TT/2017 titled Power Grid Corporation of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Limited and Ors.
Hearing
 
416
308/GT/2018
NHPC LTD
Petition under regulation 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 8(1) & 14 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of final tariff for the period 2014-19 in respect of Uri-II Power Station.
Order reserved
 
417
307/MP/2018
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
Petition under Section 79 (1) (f) of the Electricity Act, read with Clause 6.6 of the CERC (Indian Electricity Grid Code) Regulations, 2010 regarding outstanding amount of Reactive Energy Charges.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
418
304/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(b), 79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term, Medium Term Open Access in Intra State and related matters) Regulations, 2009
Hearing
 
419
303/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term, Medium Term Open Access in Intra State and related matters) Regulations, 2009
Hearing
 
420
301/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 (1) (b) & (f) of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreements dated 17.03.2010, 21.03.2013 and 27.11.2013 executed between GMR Warora Energy Limited and the Procurers for compensation due to Change in Law impacting revenues and costs during the Operating Period.
Hearing
 
421
300/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition under Section 79 (1) (b) & (f) of the Electricity Act, 2003 read with Regulation 14 (3) (ii) and Regulation 8 (3) (ii) of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations 2014 and read with statutory framework governing procurement of power through Competitive Bidding and Article 10 and 13of the respective Power Purchase Agreements, executed between GMR Kamalanga Energy Limited and its beneficiaries, seeking compensation on account of Change in Law events impacting revenues and costsduring the Operating Period.
Hearing
 
422
299/MP/2018
Bharat Aluminium Company Limited (BALCO)
Petition under Section 79 of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 for clarification regarding construction modalities for BALCO- Dharamjaygarh 400 kV D/C (2nd D/C Line) for the purpose of connectivity to BALCO for 250 MW as a bulk consumer
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
423
298/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Claim of Fixed Charges due to unilateral termination of PPA by WBSEDCL in regard to supply of power from Koderma TPS of DVC
Order reserved
 
424
295/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: Replacement of existing 1 no. 50MVA, 220/132kV ICTs by 160MVA, 220/132kV ICT at Balipara Substation along with replacement of 132kV equipment and Asset-2: 2nd 400/220kV, 315MVA ICT, new 220kVBus arrangement (GIS) with 4 nos. of 220kV Bays at Bongaigaon Substationof POWERGRID along with stringing of 2nd Circuit of 220kV D/C Bongaigaon-Salakati TL and 1 no. of 220kV line bay at Salakati Substation(for 220kV D/C Bongaigaon-Salakati TL) under �North Eastern Region Strengthening Scheme-III� in North-Eastern Region.
Hearing
 
425
294/MP/2018
Azure Power India Private Limited (APIPL)
Petition under Section 79 of the Electricity Act, 2003
Hearing
 
426
293/MP/2018
Azure Power India Private Limited (APIPL)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Limited dated 19.04.2016 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Hearing
 
427
291/MP/2018
West Central Railway (WCR)
Petition under Section 79(1)(c) and 79(1)(h) of Electricity Act 2003 and CERC Open Access Regulations 2008 and CERC Inter-State Transmission Regulation 2009, for Deviation Settlement Account
Hearing
 
428
287/MP/2018
Pranurja Solutions Limited Pranurja
Seeking trading license under Section 14 to operate a power exchange
Hearing
 
429
286/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 for execution of the Orders dated 14.03.2018 passed in Petition No. 13/SM/2017 and 16.03.2018 passed in Petition No. 1/MP/2017; and initiation of proceedings under Section 142 of the Electricity Act, 2003 against Tamil Nadu Generation and Distribution Corporation Ltd. in relation thereto.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
430
283/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 50 MVAR Line reactor at Jaipur (South) in 400 kV D/C Kota- Jaipur (South) line (Part of 400 kV D/C Rapp- Jaipur TL) utilized as Bus reactor at Jaipur (south) substation (DOCO: 05.03.2018) and Asset-II:400KV D/C Kota - Jaipur (South) line along with associated bays at Kota and Jaipur(South) (part of RAPP-Jaipur (S) 400KV D/C line with one ckt LILO at Kota) (Anticipated DOCO: 01.08.2018: Anticipated) under �Transmission system associated with RAPP 7&8, Part-B� in Northern Region�.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
431
282/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff for the period  30.06.2012 to 31.03.2014 in respect of Chamera-III Power Station.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
432
281/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff for the period 29.06.2010 to 31.03.2014 in respect of Sewa-II Power Station.
Order reserved
 
433
280/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff in respect of Teesta Low Dam-III Power Station for the period 01.04.2013 to 31.03.2014.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
434
279/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff for the period 11.10.2013 to 31.03.2014 in respect of Uri-II Power Station.
Order Reserved- Additional information for final order to be filed by
 
435
278/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section  79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the central electricity regulatory commission (grant of connectivity, long term, medium term open access in intra state and related matters) regulations, 2009
Hearing
 
436
277/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset I: Shifting of 1x315 MVA, 400/220kV  ICT from any suitable location (after replacement by 1x500 MVA ICT) and install it at Jamshedpur 400/220Kv Substation as 3rd ICT along-with associated bays, Asset II: Modification of 132kV Bus arrangement with GIS bays at 220/132kV Purnea S/S, , Asset-III: Spare 1 no unit of 765kV,110 MVAR Single Phase Reactor stationed at Sasaram, Asset-IV: 3rd 500 MVA, 400/220kV  ICT at Patna(POWERGRID) substation along-with associated bay Asset V: 01 Nos 500 MVA Single phase spare unit of 765/400 kV ICT at Angul S/S Asset-VI: 01 Nos 500 MVA Single phase spare unit of 765/400 kV ICT at Sundergrah S/S under Eastern Region Strengthening Scheme XII in Eastern Region.
Order reserved
 
437
35/RP/2018 in 261/TT/2015
MB Power (Madhya Pradesh) Limited (MBPMPL)
PETITION FILED UNDER REGULATIONS 103 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REUGLATIONS, 1999 SEEKING REVIEW OF THE ORDER DATED 27.05.2016 PASSED BY THE HON�BLE COMMISSION IN PETITION NO. 261/TT/2015 IN VIEW OF MATERIAL IRREGULARTIES WHILE PASSING THE ORDER DATED 261/TT/2015.
Hearing
74/IA/2018
438
276/GT/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 62 read with Sections 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 and read with principles provided under Section 61 of the Electricity Act, 2003 for determination of Tariff of 2X600 MW Coal Based Power Project at Village-Derang, District-Angul, Odisha for the period commencing from 12.02.2015 for the control period of 2014-19.
Hearing
72/IA/2019
439
275/MP/2018
Tata Power Trading Company Limited (TPTCL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 15 of the Power Purchase Agreement dated 13.12.2011
Hearing
100/IA/2018
440
272/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I - STATCOM  System (+/-) 300MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor), cooling system & STATCOM protection / controller  etc at Ranchi Substation (Anticipated DOCO: 31.07.2018) & Asset II - STATCOM  System (+/-) 200MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor and 2x125 MVAR Capacitor), cooling system & STATCOM protection / controller  etc at Kishanganj Substation (Anticipated DOCO: 31.12.2018) under ?Eastern Region Strengthening Scheme ?XI (ERSS-XI)  ?
Hearing
 
441
267/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for (Asset-1): Central sector portion (1646.039 kms) & (Asset-2): BBMB (2.35 kms) for Establishment of Fibre Optic communication system in Northern region (1648.389 Kms )
Order reserved
 
442
266/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 Asset-1: 2 nos. 500 MVA, 400/220kV ICTs along with associated bays at Parli (POWERGRID) Switching Station and 4 nos. 220kV line bays (for LILO of Parli - Harangul 220kV lines and Parli Osmanabad 220kV S/C line), Asset-2: 2 nos. 220kV line bays at Mapusa (Colvale) (POWERGRID Substation (for Mapusa(Colvale) (POWERGRID)-Tuem 220kV D/C line) and Asset-3: 2 nos. 400kV line bays for 400kV D/C Indore (POWERGRID)-Ujjain TL at 765/400 kV Indore (POWERGRID) Substation under WRSS XVI for tariff block 2014-19 period.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
443
265/MP/2018
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Petition under section 79 (1) (f) read with Section 142 of the Electricity Act, 2003 for issuance of direction for quashing of the letter dated 02.08.2018 issued by Power Grid Corporation of India Limited (PGCIL) whereby, PGCIL has wrongful and arbitrarily proceeded to impose transmission charges to the tune of Rs. 6.41 Crores upon the Petitioner towards Long Term Access (LTA) capacity 8.4 MW and also, through a subsequent letter dated 14.08.2018 threatened curtailment of Short Term Open Access with effect from 23.08.2018. The same is in direct contravention of the final Order passed by this Hon�ble Commission in Petition No. 190/MP/2016 dated 31.05.2018.
Order reserved
80/IA/2018
444
246/MP/2018
BHILANGAHA HYDRO POWER LIMITED (BHPL)
In the matter of declaration and consequent direction for determination of transmission charges for the 220 kV D/C Bhilangana-III - Ghansali line in terms of the order dated 10.05.2018 passed by the Hon�ble Supreme Court in Civil Appeals No. 2368-70 of 2015
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
445
245/MP/2018
ONGC Tripura Power Company (OTPC)
OTPC Palatana Project - Miscellaneous Petition for Extension of Relaxation in NAPAF Norms
Hearing
 
446
25/RP/2018 in 108/TT/2016
Teestavalley Power Transmission Limited TPTL
Review Petition under Section  94(1)(f) of the Electricity Act, 2003 read with Regulation 103 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations 1999, seeking review/modification of the Order dated 15.05.2018 passed by this Hon'ble Commission in Petition No. 108/TT/2016, in the matter of  approval of transmission tariff of circuit # 2 and circuit # 1(a) of 400 kV D/C Teesta III-Rangpo Section of 400 kV D/C Teesta III ? Kishanganj Transmission Line for the control period 2014-19.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
447
238/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Asset I: Balance portion of 400 kV D/C Baripada - Jamshedpur (DVC) Transmission Line along with bay at Jamshedpur (DOCO: 01.10.2013), Asset II: Reconductring of circuit-II of 400 kV Siliguri-Purnea D/C line (DOCO: 01.06.2013) under Eastern Region Strengthening Scheme-I for Eastern Region.
Order reserved
 
448
234/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For (1):LILO of Circuit-1 of 400 kV D/C Bareily-Mandola Line at Meerut Sub-station (DOCO: 01.10.2012), (2): LILO of Circuit-2 of 400 kV D/C Bareily-Mandola Line at Meerut Sub-station (DOCO: 01.04.2013),(3): 765 kV Bays for Bhiwani-Moga Line at Bhiwani Sub-station;765 kV 240 MVAR Bus Reactor-I alongwith associated bays at Bhiwani sub-station;765/400 kV 1000 MVA ICT-I alongwith associated bays at Bhiwani Sub-station;02 Nos.400 kV Bays for Hisar-Bahadurgarh at Bhiwani Sub-station(DOCO: 01.06.2012), (4): LILO of Hisar-Bawana at Bhiwani alongwith 02 No.400 kV Bays at Bhiwani Sub-station(DOCO:01.07.2012), (5): 765 kV bays for Jattikalan-Bhiwani Line at Bhiwani Sub-station(DOCO:01.10.2012), (6): 765 kV S/C Meerut-Bhiwani Line alongwith associated bays at Meerut & Bhiwani and 765 kV,240 MVAR Line Reactor at Bhiwani Sub-station(DOCO:01.02.2014), (7): 765/400 kV,1000 MVA ICT-II alongwith associated bays at Bhiwani Sub-station(DOCO: 01.10.2012),  (8): 765 kV 240 MVAR Bus Reactor-II alongwith associated bays at Bhiwani Sub-station(DOCO:01.07.2012) and (9):400/220 kV Ballabgarh Substation (re-alignment works)  (DOCO 01.12.2012)   under �765 kV System for Central Part of Northern Grid-Part III�.
Order reserved
 
449
232/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
PETITION UNDER SECTION 79 (1) (F) READ WITH SECTION 79 (1) (K) OF THE ELECTRICITY ACT, 2003 SEEKING ADJUDICATION OF DISPUTE ARISING OUT OF THE LETTER ISSUED BY POWER GRID CORPORATION OF INDIA LIMITED DATED 02.05.2018, 23.07.2018 AND 06.08.2018 WHICH HAVE BEEN ISSUED ILLEGALLY AND ARBITRARILY AND ARE PATENTLY AGAINST THE SCHEME OF THE REGULATORY FRAMEWORK ISSUED BY THE CENTRAL ELECTRICITY REGULATORY COMMISSION IN THIS REGARD.
Hearing
 
450
229/MP/2018
Prayatna Developers Private Limited (PDPL)
Petition under Section 79 (1) (b) and (f) and other applicable provisions of the Electricity Act, 2003.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
451
220/MP/2018
Kerala State Electricity Board Limited (KSEB Ltd.)
Adjudication of disputes on the recovery of transmission charges of Element-II and Element-III of Kudgi Associated Transmission System from the beneficiaries before the Commercial Operation of Kudgi STPS.
Order reserved
 
452
213/MP/2018
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 10 of the Power Purchase Agreements both dated 01.11.2013 entered into between the Petitioner and the Respondents, seeking approval of the cost to be incurred by the Petitioner on account of change in law, for installation/retrofit of ?Electrostatic Precipitators? (ESP), installation of Flue Gas Desulphurisation (FGD), installation of low NOx burners, providing Over Fire Air (OFA) and any other measures for compliance of the notification dated 07.12.2015 issued by the Ministry of Environment and Forests and Climate Change, Government of India in respect of Thermal Power Plants installed/commissioned after 01.01.2003;  and for other claims on account of Change in Law under the Power Purchase Agreements
Order reserved
 
453
211/MP/2018
Azure Power (Rajasthan) Private Limited AzureRajasthan
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Vidyut Vyapar Nigam Limited dated 10.01.2011 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
454
208/MP/2018
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 10 of the Power Purchase Agreement dated 19.08.2013 entered into between the Petitioner and the Respondent, seeking approval of the cost to be incurred by the Petitioner on account of change in law, for installation/retrofit of �Electrostatic Precipitators� (ESP), installation of Flue Gas Desulphurisation (FGD), installation of low NOx burners, providing Over Fire Air (OFA) and any other measures for compliance of the notification dated 07.12.2015 issued by the Ministry of Environment and Forests and Climate Change, Government of India in respect of Thermal Power Plants installed/commissioned after 01.01.2003;  and for other claims on account of Change in Law under the Power Purchase Agreement
Order reserved
 
455
202/MP/2018
LANCO AMARKANTAK POWER LTD. LAMPL
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter-alia, seeking setting aside of communication dated 27.06.2018 issued by Respondent No. 1
Hearing
69/IA/2019
456
200/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Transmission System under NRTSS in Northern Region consisting of Asset-I: 125 MVAR Bus Reactor at Jaipur South (01.01.2013) ,Asset-II : 400 kV Bhiwani Jind TL along with associated bays plus 1 nos. 500 MVA, 400/220 kV  ICT-I and associated bays at Jind Sub-station (01.04.2013), Asset-III: 400/220 kV 500 MVA ICT-II along with associated 400/220 kV bays at Jind Sub-station and one 220 kV Line bays (01.10.2013), and Asset-IV: 1 no. of 400 kV,125 MVAR Bus Reactor at Jind Sub-station alongwith associated bays(01.10.2013).
Order reserved
 
457
197/MP/2018
Bharat Aluminium Company Limited (BALCO)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking recovery of the Escalable Energy Charges due to rectification in escalation rates of Domestic Coal falling within the scope of the Power Purchase Agreement dated 08.03.2013 (PTC-PPA) executed between the Petitioner and the Respondent No. 2 and as per the terms of the back to back Power Purchase Agreement executed by PTC with Kerala State Electricity Board (�KSEB-PPA�) dated 13.06.2013
Hearing
 
458
196/MP/2018
A D Hydro Power Limited (ADHPL)
Petition under Section 142 of the Electricity Act 2003 for action against Respondent No. 1 for continuous noncompliance with the order dated 20.06.2017 of CERC in regard to the payment of the Petitioner.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
459
194/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
 For the assets of �Transmission System associated with Mundra Ultra Mega Power Project�
a. covered in CERC order dated 01.12.2014 in Petition no. 72/TT/2012
b. covered in CERC order dated 15.10.2015 in Petition no. 296/TT/2013
c. covered in CERC order dated 31.12.2015 in Petition no. 101/TT/2014
d. covered in CERC order dated 15.03.2016 in Petition no. 57/TT/2013
Order reserved
 
460
191/MP/2018
Azure Clean Energy Private Limited (ACEPL)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 28.03.2014 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
461
190/MP/2018
Azure Greentech Private Limited (Azuregreentech)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 28.03.2014 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
462
188/MP/2018
Azure Solar Private Limited (Azurespl)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Vidyut Vyapar Nigam Limited dated 25.01.2012 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
463
186/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER 79 (1)(B), 79(1)(F) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ISSUING DIRECTIONS TO THE RESPONDENTS TO REFUND THE AMOUNTS DEDUCTED ON VARIOUS HEADS CONTRARY AGAINST THE TERMS AND CONDITIONS OF THE POWER PURCHASE AGREEMENT DATED 31.07.2012 BETWEEN THE PETITIONER AND RESPONDENT.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
464
185/MP/2018
Azure Sunshine Private Limited (AzureSunshine)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 28.03.2014 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
465
184/MP/2018
Azure Power Mars Private Limited (AzureMars)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 05.02.2015 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
466
183/MP/2018
Maruti Clean Coal and Power Limited (MCCPL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking extension of Scheduled Delivery Date on account of force majeure events falling within the scope of the Power Purchase Agreement dated 01.11.2013 (PTC-PPA) executed between the Petitioner and the Respondent No. 5 and as per the terms of the back to back Power Purchase Agreement executed by PTC with Jaipur Vidyut Vitran Nigam Limited (�JVVNL�), Ajmer Vidyut Vitran Nigam Limited (�AVVNL�), Jodhpur Vidyut Vitran Nigam Limited (�JVVNL�) [hereinafter referred to as the �Procurer PPA�] dated 01.11.2013.
Order Reserved- Additional information for final order to be filed by Petitioner
 
467
182/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1- 400 kV, 125 MVAr Bus Reactor at Bina (DOCO-16.03.2016) under Installation of Bus Reactor & ICT in Western Region
Order reserved
 
468
180/MP/2018
Suzlon Energy Limited (SEL)
Section 79(1)(f) of the Electricity Act, 2003 
(b) Clause 3.11 read with Clause 4.5 of the MNRE Guidelines for implementation of Scheme for selection of 3000 MW Grid Connected Solar PV Power Projects under Phase-II, Batch-II, Tranch-I for �State Specific Bundling Scheme� read with
(c) Article 11 (Force Majeure) and Article 16.3 (Dispute Resolution) of the Power Purchase Agreements dated 02.08.2016 executed between Solar Power Developers of Suzlon Energy Ltd. being (i) Aalok Solarfarms Ltd. (ii)  Abha Solarfarms Ltd. (iii) Shreyas Solarfarms Ltd. and (iv) Heramba Renewables Ltd. with NTPC Ltd.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
469
175/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations 2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for 08 nos Transmission assets under �North Eastern Region Strengthening Scheme-VII (NERSS-VII)� for 2014-19 Tariff Block Period in North-Eastern Region.
Order reserved
 
470
173/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
PETITION FOR APPROVAL OF TRANSMISSION TARIFF For
Asset I - STATCOM  System (+/-) 300MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor), cooling system & STATCOM protection / controller  etc at Rourkela Substation (Anticipated DOCO: 01.04.2018) & Asset II - STATCOM  System (+/-) 200MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor and 2x125 MVAR Capacitor), cooling system & STATCOM protection / controller  etc at Jeypore Substation (Anticipated DOCO: 01.05.2018) under ?Eastern Region Strengthening Scheme ?XI (ERSS-XI)  ?
Order reserved
 
471
19/RP/2018 in 62/MP/2017
POWERGRID NM Transmission Limited (PNMTL)
Review of this Hon�ble Commission�s Order dated 26.03.2018 in Petition No. 62/MP/2017 filed by POWERGRID NM Transmission Limited (erstwhile Nagapattinam-Madhugiri Transmission Company Limited).
Hearing
 
472
158/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from Anticipated/ Actual DOCO to 31.03.2019 For Asset 1: 400/220kV, 3 X 105 MVA ICT alongwith associated bays at Hamirpur Substation, Asset  2:  220kV, 2Nos Line Bays at Hamirpur Substation. Asset   3:  220kV, 2Nos Line bays at Jallandhar Substation, Asset 4: 1 X 500 MVA, 400/220 kV ICT-IV  at GIS Gurgaon Substation Under �Augmentation of Transformers in Northern Region�Part B� in Northern Region
Order reserved
 
473
157/MP/2018
Prayatna Developers Private Limited (PDPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 18.05.2016 executed between Prayatna Developers Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Additional information as per Interim Order to be filed by Petitioner,Respondent
2/IA/2019
474
154/MP/2018
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Miscellaneous Petition u/s 79 to adjudicate dispute between Petitioner and Respondent in accordance to BPT agreement dated 21.11.2011
Reply / additional information as per ROP to filed by Petitioner
 
475
153/MP/2018
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Miscellaneous petition u/s 79 to adjudicate dispute between the petitioner and the respondent as per bulk agreement dated 06.09.2011
Reply / additional information as per ROP to filed by Petitioner
 
476
149/GT/2018
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter �V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of tariff of PARE Hydro Electric Power Plant (PHEP) (2 X 55 = 110 MW) for the period from COD to 31.03.2019;
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
477
145/TT/2018
Essar Power Transmission Company Limited (EPTCL)
Approval under Regulation of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of transmission tariff from the anticipated DOCO to 31.03.2019 for 400 kV D/C Mahan-Sipat and 2x50 MV AR line reactors at Mahan Pooling Substatyion and 1x80 MVAR, 420 kV switchable bus reactor at Mahan TPS along with its associated 400 kV bay
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
478
144/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2014-15 in respect of  Rangit Power Station.
Order Reserved- Additional information for final order to be filed by Petitioner
 
479
137/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31/03/2019 for Asset-I: 1X160 MVA ICT-I alongwith associated bays at Daltonganj Sub-station, 1X160 MVA ICT-II alongwith associated bays at Daltonganj Sub-station and 2X132kV Line bays at Daltonganj Sub-station Asset-II: 02 Nos of 132 kV line bays at Daltonganj Sub-station under ERSS XVII Part A in Eastern Region.
Order reserved
 
480
135/MP/2018
KUDGI TRANSMISSION LIMITED (KTL)
Petition seeking payment of transmission tariff between the date of commissioning and date of charging of Element 2 and Element 3 of transmission assets of Kudgi Transmission Limited
Hearing
 
481
133/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Implementation of Regulation 30 (6) of the Central Electricity Regulatory Commission (Terms & Conditions of Tariff) Regulations, 2014.
Hearing
 
482
132/MP/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under section 19(1)(c) of the Electricity Act, 2003 for declaration of LILO of 400 kV S/c Vindhyachal-Korba Transmission line of the Petitioner at Mahan.
Order reserved
 
483
114/MP/2018
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Sections 79(1)(b), 79(1)(c) and 79(1)(f) of the Electricity Act, 2003, read with the relevant provisions of the IEGC, 2010 for the implementation of the order of this Hon?ble Commission in Proceeding No. L-1/219/2017/CERC dated 05.05.2017 and for seeking issuance of consequential directions to the Respondents for complying with the detailed operating procedure qua reserve shut down of the Unit(s) of the 2 x 660 MW Mahatma Gandhi Thermal Power Plant at Matenhali, Dist. Jhajjhar, Haryana.
Order reserved
 
484
111/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: ?300 MVAR STATCOM at 400kV Aurangabad substation, Asset 2: ?200 MVAR STATCOM at 400kV Gwalior Substation, Asset 3: ?300 MVAR STATCOM at 400kV Satna substation and Asset 4: ?300 MVAR STATCOM at 400kV Solapur substation under ?Installation of  STATCOMs in Western Region?.
Order reserved
 
485
105/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
IN THE MATTER OF: Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated/actual DOCOs to 31.03.2019 for Asset I: Combined asset of (a) 400 KV D/C Sasaram - Daltonganj Transmission Line alongwith 2 x 50 MVAR Line Reactors   at  Daltonganj  Sub-station; (b) 400 /220 KV, 315 MVA ICT -I  alongwith bays at Daltonganj Sub-station; (c) 400 KV 80 MVAR BR at Daltonganj Sub-station; & (d) 400 /220 KV, 315 MVA ICT -II  alongwith bays at Daltonganj Sub-station; Asset II: 04 Nos 220 KV Bays at Daltonganj Sub-station; Asset III: Provision of Circuit Breakers for making line reactors at Biharshariff Sub-station switchable; Asset IV: 01 no. 80 mVAR Bus Reactor At Duburi Sub station; Asset V: LILO of 2nd Ckt. Of 400kV D/C Jamshedpur-Rourkela TL at Chaibasa S/s (non-bussed at Chaibasa); and Asset VI: 01 No. 500MVA, 3 phase 400/220kV, Transformer (2nd) and associated bays at Pandiabilli GIS under Eastern Region Strengthening Scheme-III (ERSS-III) in Eastern Region.
Order reserved
 
486
100/MP/2018
Megha Engineering & Infrastructures Ltd (MEIL)
Petition filed under Section 79(1)(f) read with Section 79(1)(k) of the Electricity Act, 2003 along with Regulation 68 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking indulgence of the Hon?ble Central Electricity Regulatory Commission to direct NTPC Vidyut Vyapar Nigam Limited to comply with the Order dated 11.10.2017 in Petition No. 16/MP/2014 by computing the delay suffered by the Generation Project due to force majeure eventualities and revise the Schedule Commercial Operation Date for the Generation Project.
Order reserved
 
487
92/MP/2018
Shiga Energy Private Limited (SEPL)
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter-alia, seeking a direction to Respondent No. 1 to pay a sum of Rs. 112.39 crores, being the financial loss suffered by the Petitioner, on account of delay in commencement of the Long Term Access granted to the Petitioner, due to delay in implementation of the Transmission system falling in the scope of Respondent No. 1?s obligations, along with interest on the same till the date of payment of the amount by Respondent No. 1 to the Petitioner.
Reply / additional information as per ROP to filed by Petitioner,Respondent
15/IA/2018
488
91/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79(1)(b) read with Section 79(1)(f) and other applicable provisions of the Electricity Act, 2003 seeking adjudication of disputes and differences under the Power Purchase Agreement dated 31.07.2012 as amended on 19.12.2014 and 23.01.2018 in regard to non-payment of tariff and unilateral deduction of the monthly energy bills of the Petitioner by the Respondents
Reply / additional information as per ROP to filed by Petitioner,Respondent
68/IA/2018 ,72/IA/2018
489
87/MP/2018
M.R. Industries (MRIndustries)
ACCESS IN INTER-STATE TRANSMISSION) REGULATIONS, 2008, FURTHER READ WITH REGULATION 4 OF THE RERC (INTRA-STATE ABT) REGULATIONS, 2006AND REGULATION 4.2 OF THE STATE GRID CODE SEEKING DIRECTIONS FOR PREPARATION OF UI ACCOUNT FOR UNDER-DRAWAL AGAINST COLLECTIVE TRANSACTIONS WITHIN SPECIFIED TIME AND FOR PAYMENT OF UI CHARGES
Hearing
 
490
78/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Unilateral Surrender of 400 MW Power by MPPMCL from MTPS & CTPS of DVC in violation of provision of PPA
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
491
76/MP/2018
BHILANGAHA HYDRO POWER LIMITED (BHPL)
PETITION UNDER REGULATION 14,5 (3) & (4) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010.
Order reserved
 
492
70/MP/2018
Godavari Biorefineries Limited (GBL)
Petition is filed praying for a direction from this Hon'ble Commission to the Respondent to refund the Back Up Supply Charges collected from the Petitioner, during the course of grant of Inter State Open Access to the Petitioner, ny contravening and violating Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008.
Hearing
 
493
61/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of    Transmission Tariff from DOCO to 31.03.2019 Asset-I: 2 nos. 400 kV Malerkotla Bays at 400/220 kV GIS Substation at Kurukshetra under ?Provision of 400kV bays for lines under Northern Region System Strengthening Scheme-XXXI(Part-B)?.
Order reserved
 
494
27/MP/2018
Krishna Windfarms Developers Private Limited (KWFDPL)
Petition under Section 79 (1) (f) read with Section 79 (1) (b) of the Electricity Act, 2003 in relation to the disputes arising out of the Power Purchase Agreement dated 03.08.2016 between Petitioner herein i.e. Krishna Windfarms Developers Private Limited and Solar Energy Corporation of India Limited.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
495
19/MP/2018
TALETTUTAYI SOLAR PROJECTS FOUR PVT. LTD TT4
MEMORANDUM OF ORIGINAL PETITION FILED UNDER SECTION 79 (1) (f) OF THE ELECTRICITY ACT, 2003 (�THE ACT�) AND THE OTHER APPLICABLE PROVISIONS OF THE ACT IN RELATION TO THE DISPUTES HAVING ARISEN UNDER THE POWER PURCHASE AGREEMENT DATED APRIL 11, 2016 BETWEEN THE PARTIES
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
496
17/MP/2018
NTPC Vidyut Vyapar Nigam Limited (NVVN)
PETITION UNDER SECTION 79 (1) (f) READ WITH SECTION 79 (1) (a) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES BETWEEN THE PETITIONER AND THE RESPONDENTS 1 TO 3
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
497
253/MP/2017
sks power generation (chhattisgarh) limited (SPGCL)
Petition seeking surrender/ relinquishment of LTA of 513 MW (149 MW in WR and 364 MW in NR) out of the total LTA quantum of 683 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010.
Hearing
87/IA/2017
498
251/GT/2017
UDUPI POWER CORPORATION LTD (UPCL)
Application under Regulations 20, 25 & 27 of the  of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999; Regulations 2, 6 and 7 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations 2014 and under Section 62 and 79(1)(b) of the Electricity Act, 2003 for determination of tariff for the 2x600 MW thermal power plant set up by  Udupi Power  Corporation Limited in Udupi Taluk, Udupi District, Karnataka for the period, from 01.04.2014 to 31.03.2019.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
499
247/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 1X500MVA, 765/400kV Transformer as spare ICT at Agra Sub-station, Asset-II: 1X500MVA, 765/400kV Transformer as spare ICT at Fatehpur Sub-station, Asset-III: 765/400 KV,500MVA, single phase  Auto Transformer as spare ICT at Jhatikra S/S and Asset-IV: 765/400 KV, 333MVA, single phase  Auto Transformer as spare ICT at Bhiwani S/S  under �Spare Transformer for 765/400KV ICTs in NR�.
Order reserved
 
500
243/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff  of  Bongaigaon Thermal Power Station (3X250 MW) for the period from Date of Commercial Operation of Unit-1 (i.e. 01.04.2016) to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
501
241/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Determination of tariff of Muzaffarpur Thermal Power Station        Stage-I Unit-2 (110 MW) for the Period 15.10.2010 to 31.03.2014
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
502
240/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Approval of tariff of MTPS Stage-I (2x110 MW) from 01.04.2014 to 31.03.2019.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
503
236/MP/2017
DAMODAR VALLEY CORPORATION (DVC)
Petition against the decision of MPPMCL for Unilateral surrender of 100 MW from DSTPS in violation of provision of PPA between DVC & MPPMCL
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
504
210/MP/2017
KUDGI TRANSMISSION LIMITED (KTL)
Petition for revision of Tariff for events occurring after the Bid Due Date
Hearing
 
505
199/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Kudgi Super Thermal Power Station Stage-I (3 X 800 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e. 25.07.2017) to 31.03.2019.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
506
197/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Feroze Gandhi Unchahar Thermal Power Station Stage-IV (1 X 500 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e. 31.07.2017) to 31.03.2019.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
507
178/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Solapur Super Thermal Power Station   (2 X 660 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e.  31.08.2017)  to 31.03.2019.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
 
508
169/MP/2017
sks power generation (chhattisgarh) limited (SPGCL)
Petition seeking surrender/ relinquishment of 170 MW (170 MW in WR) out of the total LTA quantum of 683 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010.
Hearing
43/IA/2017
509
164/MP/2017
IL&FS Tamil Nadu Power Company Limited ITPCL
PETITION UNDER SECTIONS 79(1)(C) AND 79(1)(F) OF THE ELECTRICITY ACT, 2003
Hearing
 
510
139/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79 of the Electricity Act 2003 read with Regulation 54 and 55 of the CERC (Terms and Conditions of Tariff) Regulations 2014 seeking Appropriate Relief due to Extreme Practical Difficulty faced by the Petitioner in implementing Regulation 30 (6) of the said Regulation and Directions issued by the Hon?ble Commission in its Order dated 25.01.2016 and For Consequential Directions
Hearing
 
511
136/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation 86 of CERC  Conduct of Business Regulations1999 and CERC Terms and Conditions of Tariff Regulations 2014 for  determination of    Transmission Tariff  from 01.04.2014 to 31.03.2019
Hearing
 
512
129/MP/2017
SIMHAPURI ENERGY LIMITED (SEL)
Petition seeking surrender of 146 MW (135 MW in WR and 11 MW in SR) out of the total LTA quantum of 546 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010 read with Annexure-I as modified vide amendments dated 02.01.2012 and 17.10.2012.
Hearing
 
513
124/MP/2017
Kanchanjunga Power Company Private Limited KPCPL
Petition under section 79(1)(f) read with section 79(1)(c) & (d), section 38, section 39, section 40 and section 60 of the Electricity Act, 2003 concerning the unjust, arbitrary and illegal terms imposed by Himachal Pradesh Power Transmission Corporation Limited and Allain Duhangan Hydro Power Limited for transmission of power by the Petitioner on inter-state transmission lines operated by them.
Hearing
49/IA/2018 ,82/IA/2019
514
119/MP/2017
Rajasthan Sun Technique Energy Private Ltd RSTEPL
The Power Purchase Agreement 8th January 2011 (?PPA?) entered into between NTPC Vidyut Vyapar Nigam Limited and Rajasthan Sun Technique Energy Pvt Ltd./Extension of Scheduled Commissioning Date
Hearing
 
515
107/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For combined assets Asset-1: 400 kV D/C Parbati Pooling Point �Amritsar line alongwith associates bays and Asset-2 : 80 MVAR bus reactor at Parbati Pooling Point along with associated bays under transmission system associated with PARBATI-III-HEP in Northern Region.

And 

Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Final and Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

Asset-3 : LILO of 2nd ckt of Parbati-II-Koldam T/L at Pooling station and LILO at Parbati-III (Portion c-d ), Asset-4 : LILO of 2nd ckt of Parbati-II-Koldam T/L at Pooling Station along with associated bays and LILO of Parbati-III (Portion e-f) under transmission system associated with PARBATI-III-HEP in Northern Region.
Hearing
 
516
68/MP/2017
DB Power (Madhya Pradesh) Limited (DBPMPL)
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter alia seeking setting aside/quashing of invocation & encashment by the Respondent of  the Bank Guarantee furnished by the Petitioner in relation to the grant of LTA to the Petitioner qua its proposed Thermal Power Project in Singrauli District, Madhya Pradesh and consequent direction to the Respondent to reimburse the encashed amount along with interest to the Petitioner.
Order reserved
 
517
23/GT/2017
BHARTIYA RAIL BIJLEE COMPANY LTD. (BRBCL)
Approval of tariff  of Nabinagar Thermal Power Project (4X250 MW) for the period from anticipated Date of Commercial Operation  of Unit-1  to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
518
21/MP/2017
Essar Power (Jharkhand) Ltd (EPJL)
Petition for Relinquishment of 1100 MW of Long Term Access agreed under the Bulk Power Transmission Agreement dated 24.02.2010 under Regulation 18 read with Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009, of the subject Transmission Lines by the ESSAR Power Jharkhand Limited (3x600 MW) Thermal Power Plant, Chandwa Tehsil, District Latehar in the State of Jharkhand.
Hearing
9/IA/2017
519
11/MP/2017
GMR CHHATTISGARH ENERGY LIMITED (GCEL)
Petition under Section 79(1)(c) of the Electricity Act, 2003, read with the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and the Detailed Procedure for grant of LTA, seeking deferment of operationalization of Long Term Access of 430 MW in Northern Region as per the BPTA dated 31.03.2010 and Petition under Section 79(1)(c) of the Electricity Act, 2003, read with the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and the Detailed Procedure for grant of LTA, seeking relinquishment of Long Term Access of 386 MW in Western Region out of the total quantum of 816 MW as per the BPTA dated 31.03.2010
Hearing
 
520
5/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79(1)(f) and 79(1)(b) of the Electricity Act, 2003 in connection with the disputes and differences arising under the Power Purchase Agreement dated 12.05.2008 between the Petitioner and Respondent no. 1.
Hearing
 
521
4/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79(1)(f) and 79(1)(b) of the Electricity Act, 2003 in connection with the disputes and differences arising under the Power Purchase Agreement dated 18.07.2008 between the Petitioner and Respondent no. 1.
Hearing
29/IA/2019
522
249/GT/2016
Teesta Urja Limited (TUL)
Determination of Tariff of 1200 MW Teesta III Hydro Electric Project Sikkim
Order Reserved- Additional information for final order to be filed by Petitioner
 
523
246/MP/2016
Coastal Energen Private Limited (CEPL)
Relinquishment of 542 MW LTOA.
Hearing
 
524
244/MP/2016
NTPC Limited
Measurement of GCV of Coal received at the plant site of NTPC Power Stations
Hearing
86/IA/2017
525
220/MP/2016
West Bengal State Electricity Distribution Company Limited WBSEDCL
Petition under Section 79 (1) (f) of the Electricity Act, 2003 seeking adjudication of dispute between West Bengal State Electricity Distribution Company Limited and NTPC Ltd.and Damodar Valley Corporation relating to over invoicing and recovery of Rs. 1192.67Crores.
Hearing
 
526
217/MP/2016
Thermal Powertech Corporation India Limited TPCIL
Petition seeking compensation on account of Changes in Law under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreement dated 01.04.2013 entered into between Thermal Powertech Corporation India Ltd and the Distribution Companies in the States of Andhra Pradesh and Telangana
Reply / additional information as per ROP to filed by Petitioner
 
527
203/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I:400kV D/C Meja-Allahabad transmission line alongwith associated bays at Allahabad  under ?Transmission System Associated With Meja TPS? in Northern Region.
Order reserved
 
528
183/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Assets (03 nos) under Sikkim Generation Projects- Part-B  in Eastern Region.
Order reserved
 
529
137/MP/2016
GMR Kamalanga Energy Limited (GKEL)
Petition for relinquishment of Long Term Open Access
Hearing
 
530
91/MP/2016
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Section 79 (1) (f) and (k) of the Electricity Act, 2003 read with Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations 2014 along with Regulation 111 and Regulation 115 of the CERC (Conduct of Business) Regulations, 1999, seeking re-determination of gross station heat rate of Badarpur Thermal Power Station as provided under Regulations 36 (C) (a) (ii) of the CERC (Terms & Conditions of Tariff) Regulations 2014 along with Affidavit
Order Reserved- Additional information for final order to be filed by Petitioner
 
531
81/TT/2016
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval under Sections 61, 62 and 79 (1) (c) & 79 (1) (d) of the Electricity Act, 2003 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of Annual Fixed Cost and determination of tariff for the licensed transmission business for the financial years 2015-16, 2016-17, 2017-18 and 2018-19 for 400 kV Srinagar-Srinagar PH line as per Hon?ble Central Electricity Regulatory Commission?s order dated 31 January 2013 against Petition number 133/ MP/2012
Hearing
 
532
80/TT/2016
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval under Sections 61, 62 and 79 (1)(c) & 79 (1) (d) of the Electricity Act, 2003 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of Annual Fixed Cost and determination of tariff for the licensed transmission business for the financial years 2015-16, 2016-17, 2017-18 and 2018-19 for 400 KV Srinagar Substation as per Hon'ble Central Electricity Regulatory Commission's order dated 31 January 2013 against Petition number 133/MP/2012.
Hearing
 
533
64/MP/2016
BSES Rajdhani Power Limited (BRPL)
Petition under Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 30(7) of CERC (Terms and Conditions of Tariff), Regulations, 2014 seeking adjudication of dispute between Petitioners, i.e., BSES Rajdhani Power Limited & BSES Yamuna Power Limited with NTPC Ltd.
Hearing
85/IA/2017 ,84/IA/2017
534
38/MP/2016
Lanco Babandh Power Ltd
Petition u/s 79(1) ( c) read  with  79(1) (f) and 79 (1) (k) of the E. Act, 2003 inter alia seeking a decalration that the factors/ events namely dely in forest clearance of land for main plant cancellation of  allocated coal block to the Petitioner, non-signing of Fual supply agreement dely ihn acquisition /procurement of land for mkain plant, delay in approval of Land for Ash Pond by state of Odhisa, dely in clearance for construction of dedicated transmission line from Ministry of Power in the construction of the  2 x 660 MW Coal based thermal Power Plant located in dhenkenal district Odisha for Force majeure events under BPTA dated 24.02.2010 seeking extension of time period for achieving the Commercial Operation date of the project and other consequential reliefs under the BPTA dated 24.02.2010
Reply / additional information as per ROP to filed by Petitioner,Respondent
36/IA/2019 ,6/IA/2018
535
51/MP/2016
Bharat Aluminium Company Limited (BALCO)
An application for Regulatory Compliance of order dated 30.10.2014 passed in Petition No.134/MP/2011 and Order dat ed 09.10.2015 passed in Petition No. 124/RC/2015 under Section 142 and 146 of the Electricity Act, 2003
Pending as per direction of Higher Court / APTEL
 
536
10/MP/2016
Jaiprakash Power  Ventures Limited
Petition u/s 79(1) (f) and Sec- 19 of E. Act, 2003 read with Regulations 14 of CERC(procedures, Terms and Condtions for grant of trading license and other realted matters) Regualtions, 2009 seeking refund of the Late payment of Surchages illegally retained by the Respondent No. 1 under Power Purchase Agreement dat ed 30.0.5 2011 alongnwith interest and initiation of proceedings for revocation of the Inter State Trading License of the Respondent No.1
Hearing
 
537
03/MP/2016
M/s Vendanta Limited (Formerly Sesa  Sterlite Limited)
Petition  for the relinquishment of the Long Term Open Access under the Bulk Power Transmission Agreement dated 5th July, 2010 under Regulation 2010 read with Regulation 32 of the CERC(Grant of Connectivity, Long Terms Access and Medium Terms Open Access in inter State Transmission and related  matters ) Regulations, 2009
Hearing
 
538
311/MP/2015
Tata Power Delhi Distribution Limited (TPDDL)
Petition praying for appropriate directions restraining the Respondent from recovering the Energy Charge Rate strictly in terms of the Tariff Regulations framed b y this Honble Commission
Hearing
 
539
309/GT/2015
Pragati Power Corporation Limited (PPCL)
Filing of Petition under Sec 62 and 79(1) (a) & (b) of the Electricity Act, 2003, CERC (Terms and  Conditions of Tariff) regulations, 2009 and sec-86 of CERC(CB)  Regulations, 1999 for True up of  Generation Tariff of  Pragati-III CCPS 1371.2 MW pwoer plant  of Pragati Power Corporation Limited for the period from COD of GT#1 up to 31.03.2014 of MYT 2009-2014
Order reserved
 
540
305/MP/2015
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
Petition under Section 79 of the Electricity Act, 2003 read with  provisions of the Power Supply agreement dated 05.1.2011 and Power Purchase Agreement dated 25.03.2011 for directions to make Energy Charges as pass-through based on the actual fuel cost incurred by the Petitioner
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
24/IA/2019
541
303/MP/2015
M/s Vedanta Limiited
Petition for the relinquishment of the long term open access under the bulk power transmission agreement dated  5.1.2011 under Regulaiton 18 read with Regulation 32 of the CERC (Grant of Connectivity, Long Term Access and Medium Term Access in inter-State transmission and related matters) Regulations, 2009
Hearing
 
542
014/SM/2015
Suo Motu
Notice under Section 19 of the Electricity Act 2003 for revocation of the inter-State transmission licence granted to Talcher II Transmission Company Ltd. Talcher II Transmission Company Ltd.
Pending as per direction of Higher Court / APTEL
 
543
13/SM//2015
Suo Motu
Revocation of transmission licence under Section 19 of the Electricity Act, 2003 granted to North Karanpur Transmission Compnay Limited
Pending as per direction of Higher Court / APTEL
 
544
221/GT/2015
Pragati Power Corporation Limited (PPCL)
Tariff Petition under section 62 and 79(1) (a) & (b) of the Electricity Act, 2003 and CERC Tariff Regulation 2014 for determination of Generation Tariff of Pragati-III CCPS 137.2 MW Power plant of Pragati Power Corporation Limited for the period  from 01-04-2014 to 31-03-2019 of current MYT
Order reserved
 
545
183/MP/2015
Meenakshi Energy Private Limited (MEPL)
For adjudication of disputes over  an increas in tariff sought by the Petitioner for its Power plant selling to AP and telangana
Hearing
 
546
156/TT/2015
Parbati Koldam Transmission Company Limited (PKTCL)
Petition for determination of transmission tariff for section of 400 KV (Quad) 2XS/C parbati- koldam Transmission Line, starting from parbati-II  HEP to LILO point of parbati (Banala) pooling Station for Circuit-I and from Parbati-II HEP to LILO point of parbati-III HEP for Circuit-II for control period of 2014-2019 .
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
547
055/MP/2015
Jindal India Thermal Power Limited.
Petition for the relinquishment of the Long term Open Access under the Bulk Power Transmission Agreement dated 13.05.2010 under Regulation 18 read with Regulation 32 of the CERC (Grant of Connectivity, Long Term Access and Medium Term Open Access in Inter- State Transmission and related matters) Regulations, 2009.
Hearing
 
548
MP/463/2014
GMR Vemagiri Power Generation Limited.
Petition under Section 79(I)(f) of the Electricity Act, 2003 for a direction to the Respondents to pay Additional Fixed Charge of Rs.0.439/KWH for the balance period of PPA.
Hearing
40/IA/2019 ,39/IA/2019
549
GT/130/2014
NTPC Limited
Petition Under section 62 and 79(I)(a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity regulatory Commission (Conduct of Business) regulations, 1999 for approval of tariff of Barh Super thermal Power Station Stage-II (2X660 MW) for the period  from anticipated Date of Commercial operation of 1st Unit (Unit-IV) to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
 
550
MP/085/2014
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petitions  read with appropriate provisions of the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in Inter-State Transmission and related matters) Regulations, 2009 and CERC (Sharing of Interstate Transmission Charges and Losses) Regulations, 2010. And in the matter of Non- payment of transmission charges pertaining to LTA of 119.19 MW power from Mejia Unit#8 (DVC) by Damodar Valley Corporation (DVC), Kolkata.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
25/IA/2019 ,43/IA/2019
page separator
S. No.
Petition No.
Petitioner
Subject
Status
Related IA's
551
MP/041/2014
Aurum Renewables Energy Pvt. Ltd. AREPL
Petition for adjustment of capacity utilization, adjustment of tariff, extension of time for execution of project and other consequential reliefs.
Pending as per direction of Higher Court / APTEL
 
552
MP/014/2014
KVK ENERGY VENTURES PVT. LTD. (KVKENERGY)
petition for adjustment of Tariff, extension of time for execution of project and other consequential reliefs.
Pending as per direction of Higher Court / APTEL
 
553
MP/010/2014
Shamanur Sugars Limited.
For a direction from this honourable Commission to the respondent to refund the Back up supply Charges collected from the petitioner, during the course of grant of Inter State open access to the Petitioner, by contravening and violating CERC (Open access in Inter-State transmission) Regulations, 2008.
Hearing
 
554
MP/327/2013
DIWAKAR SOLAR PROJECTS PRIVATE LIMITED (DIWAKAR_SOLAR)
For adjustment of tariff, extension of time for execution of project and other consequential reliefs.
Pending as per direction of Higher Court / APTEL
 
555
082/MP/2013
Dhrudesh Metalsteel Private Limited.
Levy of back up supply charges and withholding of UI Charges during the grant of Inter State Open Access.
Hearing
 
556
124/MP/2012
M/S Falcon Tyres Limited.
Illegal Lavy of UI charges and back up energy supply charges under Inter State Open access in violation of Central Electricity Regulatory Commissions Regulations.
Hearing
 
557
091/TT/2012
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Transmission Tariff of PARABATI-III HEP in NR.
Order reserved
 
558
1/MP/2012
M/S Sadashiva Sugars Limited
Levy of UI charges in Violation of Central Electricity Regulatory Commission (Unscheduled Interchange Charges and Related Matters) Regulations, 2009 and back supply charges under the Karnataka Electricity Regulatory Commission (Open Access) Regulations, 2004 for an Inter State Open access transaction.
Hearing
 
559
009/2009
MPPTCL
Payment of interest on the excess amount recovered as per order dated 23.10.2000 and order dated 30.09.2008 in Petition No.10/2000 and order dated 23.03.2007 in Petition No. 6/2004 in respect of wheeling charges payable to Gridco for wheeling of Central Sector Power from NTPC power station is in Eas
Pending as per direction of Higher Court / APTEL
 
560
130/2009
Suo Motu
Maintenance of Grid Discipline-non-compliance of provisions of the Indian Electricity Grid Code by TNEB
Pending as per direction of Higher Court / APTEL
 
561
081/2009
Suo Motu
Maintenance of Grid Discipline – Non  ‐compliance of provisions of the Indian Electricity Grid Code by Tamil Nadu Electricity Board.
Pending as per direction of Higher Court / APTEL
 
562
080/2009
Suo Motu
Maintenance of Grid Discipline-Compliance of provisions of  the Indian Electricity Grid Code by Transmission Coporation of Andhra Pradesh Ltd.
Pending as per direction of Higher Court / APTEL
 
563
131/2007
Suo Motu
Default in payment of Unscheduled Interchanges (UI) charges for the energy drawn in excess of her drawal schedule (UP).
Pending as per direction of Higher Court / APTEL