Petitions Status
As on 30/11/2018
S. No.
Petition No.
Petitioner
Subject
Status
1
349/MP/2018
Chhattisgarh WR Transmission Limited (CWRTL)
Petition by M/s Chhattisgarh-WR-Transmission Limited (the ?Petitioner/CWTL?) under Section 17(3) and (4) of the Electricity Act, 2003 read with Clause15.8.3 of the Rupee Loan Agreement dated 29.06.2016 along with Clause 11.9 of the Security Trustee Agreement dated 29.06.2016 along with Article 15 of the Transmission Service Agreement dated 23.06.2015, for the purpose of recognition by this Hon?ble Commission of the change in the constitution of the consortium of existing lenders,which were already approved by this Hon?ble Commission vide its order dated 16.08.2016 in Petition No. 109/2016.
Preliminary Scrutiny
2
45/RP/2018 in 213/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Memorandum of Review Petition
Preliminary Scrutiny
3
44/RP/2018 in 235/MP/2015
GUJARAT URJA VIKAS NIGAM LIMITED (GUVNL)
Memorandum of review Petition
Preliminary Scrutiny
4
348/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Chamera-II Power Station.
Preliminary Scrutiny
5
347/MP/2018
NER II Transmission Limited nerii
Petition for approval for creation of security interest under Sections 17(3) & 17(4) of Electricity Act, 2003 over Petitioner No. 1�s Assets in favour of Petitioner No. 2, the Security Trustee, for the benefit of Lenders and their agents for the purpose of financing Petitioner No. 1�s Transmission Project.
Preliminary Scrutiny
6
9/SM/2018
Suo Motu
Non-compliance of the Central Electricity Regulatory Commission (Payment of Fees) Regulations, 2012.
Preliminary Scrutiny
7
346/MP/2018
UDUPI POWER CORPORATION LTD (UPCL)
Petition under Section 79 (1) (b) of the Electricity Act, 2003 read with Regulation 14 (3)(ii) of the CERC Tariff Regulations, 2014, Article 1.1 (�Change in Law�) & 6.12 of the Power Purchase Agreements (�PPAs�) seeking regulatory certainty with respect to treatment of such cost for mandatory installation of additional systems in compliance with the Environment (Protection) Amendment Rules, 2015 issued by the Ministry of Environment, Forest and Climate Change dated 07.12.2015 for thermal power stations
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
8
345/MP/2018
M.P. Power Management Co. Ltd. (MPPMCL)
Treatment of power drawn by CTU connected 750 MW Rewa Solar Project during non-generation night hours and during shutdown periods and determination of tariff thereof.
Preliminary Scrutiny
9
344/MP/2018
Power System Operation Corporation Ltd (POSOCO)
Approval of the additional expenses on account of Wage Revision, Additional Manpower, Certification Linked Incentive, Increase in Performance Related Pay Kitty and additional O&M expenses for the control period 2014-19.
Preliminary Scrutiny
10
343/MP/2018
ACME Jaipur Solar Power Private Limited (AJSPPL)
Tariff Revision on account of change in law i.e. on introduction of GST Laws
Preliminary Scrutiny
11
342/MP/2018
ACME Rewa Solar Energy Private Limited (ARSEPL)
Revision of Tariff pursuant to enactment of CGST Act and allied GST laws
Preliminary Scrutiny
12
341/GT/2018
MEJA URJA NIGAM (P) LIMITED (MUNPL)
Petition Under Section 62 and 79(1)(a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff  of  Meja Thermal Power Station Stage-I (2x660 MW) for the period from anticipated Date of Commercial Operation  of Unit # 1 (i.e. 31.10.2018) to 31.03.2019.
Preliminary Scrutiny
13
340/MP/2018
Rising Sun Energy Pvt Ltd (RSEPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 16.3.1 of the Power Purchase Agreements executed between the Petitioners and NTPC Limited dated 12.05.2016, seeking release of Performance Bank Guarantees arbitrarily and illegally retained by NTPC Limited and seeking extension of time and deferral of the Scheduled Commissioning Date for the commissioning of two 70 MW solar power projects in accordance with Power Purchase Agreements dated 12.05.2016 executed under the National Solar Mission Phase-II, Batch-II, Tranche-I.
Preliminary Scrutiny
14
339/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(b), 79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the Central Electricity Regulatory Commission ( Grant of Connectivity, Long Term, Medium Term Open Access in Intra State and related matters) Regulations, 2009.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
15
338/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: Combined assets: 1) LILO of both circuits of Bamnauli-Samaypur 400kV line at Tughlakabad along with associated bays; 2) 400/220 kV, 2x500 MVA ICT-I & II at 400 /220 kV GIS at Tughlakabad S/s along with associated bays; 3) 400 kV, 125 MVAR Bus reactor at GIS Tughlakabad S/s along with associated bays and Asset-II: 400/220 kV, 2x500 MVA ICT-III & IV at 400 /220 kV GIS at Tughlakabad S/s along with associated bays under �Creation of 400/220 kV Substations in NCT of Delhi during 12th plan period Part-B1 in Northern Region
Preliminary Scrutiny
16
43/RP/2018 in 215/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review and modification of this Hon�ble Commission�s Order dated 09.07.2018 in Petition No. 215/TT/2016 filed by Power Grid Corporation of India Limited.
Preliminary Scrutiny
17
337/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of Transmission Tariff for Asset-I: 3x5 MVA (132/33kV), 1-ph, ICT-I alongwith associated bays at Tezu substation, Asset-II:  4x5 MVA (132/33kV) (01 no spare), 1-ph, ICT-II alongwith associated bays at Tezu substation, Asset-III: 132kV S/C (on D/C Tower) Tezu-Namsai Transmission Line alongwith associated bays at Tezu and Namsai Substation, 4X6.67MVAR, 145kV, 1-ph Bus Reactor, 3X5MVA, 132/33kV, 1-ph ICT-I and 4X5MVA, 132/33kV 1-ph ICT-II (01 no spare phase) at Namsai Substation, from DOCO to 31.03.2019 under �Transmission system associated with Pallatana GBPP and Bongaigaon TPS�.
Preliminary Scrutiny
18
336/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 220kV Kishanganga-Wagoora D/C line Partially on M/C tower along with associated bays at Wagoora S/s under �Transmission system associated with Kishenganga HEP�
Preliminary Scrutiny
19
42/RP/2018 in 264/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review and modification of this Hon�ble Commission�s Order dated 20.07.2018 in Petition No. 264/TT/2017 filed by Power Grid Corporation of India Limited.
Preliminary Scrutiny
20
335/TT/2018
DAMODAR VALLEY CORPORATION (DVC)
Tariff petition for New Element and then combining with existing Asset Base of Existing
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
21
334/TT/2018
DAMODAR VALLEY CORPORATION (DVC)
Petition for ISTS  (400 kV Transmission Line - LILO DSTPS, LILO RTPS, DSTPS-RTPS , RTPS-RANCHI)
Preliminary Scrutiny
22
333/MP/2018
Indian Railways ECR
Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Regulations 6.3A and 6.3B of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 regarding the validity of the Commercial Operations Date of Units I and II of its generating station as declared by Bhartiya Rail Bijlee Company Limited
Preliminary Scrutiny
23
332/MP/2018
Adani Power (Mundra) Limited (APMuL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 13 (�Change in Law�) of the Power Purchase Agreements (�PPAs�) dated 06.02.2007 (Bid‐01) and 02.02.2007 (Bid‐02) executed between Gujarat Urja Vikas Nigam Limited and Adani Power (Mundra) Ltd and the PPAs dated 07.08.2008 executed with Uttar Haryana Bijli Vitran Nigam Limited/ Dakshin Haryana Bijli Vitran Nigam Limited in respect of mandatory installation of additional systems in compliance with the Environment (Protection) Amendment Rules, 2015 issued by the Ministry of Environment, Forest and Climate Change dated 07.12.2015 for thermal power stations
Preliminary Scrutiny
24
331/MP/2018
Maithon Power Limited (MPL)
Petition under Section 79 of the Electricity Act, 2003 for the recovery of unpaid dues and implementation of Orders dated 31.08.2017 in Petition No. 28/MP/2016 read with Order dated 20.03.2018 in Petition No. 192/MP/2016; and Order dated 26.12.2017 in Petition No. 152/GT/2015 for:-
(a) Recovery of unpaid bills and the imposition of Late Payment Surcharge thereon.
(b) Recovery of Ash disposal expenses.
Preliminary Scrutiny
25
330/MP/2018
NHPC LTD
Application under Regulation-31(6) and Regulation-54&55 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of shortfall in energy charges due to reasons beyond control of Teesta Low Dam-III Power Station and recovery of shortfall in capacity charge under Regulation-54&55 due to agitation by GJMM in FY 2017-18.
Preliminary Scrutiny
26
329/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of the generating station during the FY 2016-17 in respect of  Dhauliganga Power Station.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
27
328/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2017-18 in respect of   Sewa-II Power Station.
Preliminary Scrutiny
28
327/MP/2018
DHARIWAL INFRASTRUCTURE LIMITED (DIL)
Petition under 79(1)(f) of the Electricity Act, 2003 for claiming compensation on account of occurrence of 'Change in Law' events as per Article 10.1.1 of the Case-1 long-term Power Purchase Agreement dated 27.11.2013 read with Addendum no. 1 dated 20.12.2013 entered into between Dhariwal Infrastructure Limited and Tamil Nadu Generation and Distribution Corporation Limited thereby resulting into additional recurring/non-recurring expenditure by Dhariwal Infrastructure Limited for supply of 100 MW Contracted Capacity from Unit 2 of its 2 x 300 MW Coal based thermal generating station located at Tadali, Chandrapur in the State of Maharashtra to Tamil Nadu Generation and Distribution Corporation Limited.
Preliminary Scrutiny
29
326/MP/2018
Raipur Rajnandgaon Warora Transmission Limited (RRWTL)
Petition under Section 79 (1) (c) and (f) and other applicable provisions of the Electricity Act, 2003 inter-alia seeking a declaration that the factor/event, namely, delay in obtaining forest clearance for implementing the ?Additional System Strengthening Scheme for Chhattisgarh IPPS - Part B?, is a force majeure event under the TSA dated 19.05.2015 and further seeking extension of time period for achieving the commercial operation date of project and other consequential reliefs under the TSA dated 19.05.2015.
Reply / additional information as per ROP to filed by Petitioner,Respondent
30
325/MP/2018
UDUPI POWER CORPORATION LTD (UPCL)
Petition under Section 142 read with Section 79(1)(b) and (f) of the Electricity Act, 2003 read with Article 7.2(b) of the Power Purchase Agreement dated 26.12.2005
Preliminary Scrutiny
31
324/MP/2018
UDUPI POWER CORPORATION LTD (UPCL)
Petition filed under Section 79(1)(b) of the Electricity Act, 2003 read with Article 7(2)(b) of the Power Purchase Agreement dated 26.12.2005.
Preliminary Scrutiny
32
323/GT/2018
Neyveli Lignite Corporation Ltd (NLC)
NLCIL- NNTPS (Neyveli New Thermal Power Station) 2 X 500 MW-Determination of tariff for the period from the date of anticipated CoD up to 31.03.2019-Petition submission - Reg.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
33
322/GT/2018
NHPC LTD
Petition under regulation 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 7(4) & 14 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of final tariff for the period 2014-19 in respect of Sewa-II Power Station.
Preliminary Scrutiny
34
321/GT/2018
NHPC LTD
Petition under section 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 7(4) & 14 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of final tariff for the period 2014-19 in respect of Chamera-III Power Station.
Preliminary Scrutiny
35
320/GT/2018
NHPC LTD
Tariff petition for determination of final tariff for the period 2014-19 in respect of Teesta Low Dam-III Power Station
Preliminary Scrutiny
36
319/RC/2018
Power System Operation Corporation Ltd (POSOCO)
automatic generation control implementation in India
Preliminary Scrutiny
37
318/MP/2018
SEI Sunshine Power Private Limited SEISunshine
Petition under Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 7 of the 5th amendment of the CERC (Sharing of Inter State Transmission Charges and Losses) Regulation 2010 thereby seeking quashing of the letters dated 28.03.2018, 29.03.2018 and 03.10.2018 issued by PGCIL.
Reply / additional information as per ROP to filed by
38
317/TD/2018
Manikaran Power Limited MPL
Petition under Third and Fourth Proviso to Regulation 7 (b) of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading license and other related matters) Regulations, 2009 for up-gradation of the inter-state trading license from Category �II� to Category �I�.
Preliminary Scrutiny
39
316/MP/2018
NHPC LTD
Application under Regulation-31(6) and Regulation-54&55 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of shortfall in energy charges due to reasons beyond control of Teesta Low Dam-IV Power Station and recovery of shortfall in capacity charge under Regulation-54&55 due to agitation by GJMM in FY 2017-18.
Preliminary Scrutiny
40
41/RP/2018 in 165/GT/2017
THDC India Limited (THDCIL)
Review of tariff order dated 05.09.2018 in petition no 165/GT/2017 for Koteshwar HEP (400 MW)
Preliminary Scrutiny
41
315/GT/2018
SJVN Limited
Petition under Section 62 and 79(1)(a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission(Conduct of Business) Regulations, 1999 for approval of Generation tariff of Rampur Hydro Power Station (412 MW)  for the period from actual COD of first Unit 13.05.2014 to 31.03.2019.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
42
314/GT/2018
SJVN Limited
Petition under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with  Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for  approval of generation tariff of Nathpa Jhakri Hydro Electric Power Station (6x250 MW) for the period 01.04.2014 to 31.03.2019
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
43
313/MP/2018
GRIDCO LTD.
Petition under Section 79 (1) (c), (d) and (f) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010 and Regulation 111 and 114 of CERC (Conduct of Business) Regulations, 1999 for re-determination of Slab Rates for the period January 2016 to March 2016 i.e., Quarter Q4 of F.Y.2015-16 determined vide order dated 12.03.2016.
Preliminary Scrutiny
44
40/RP/2018 in 175/TT/2017
DELHI TRANSCO LIMITED (DTL)
Memorandum of Review Petition
Preliminary Scrutiny
45
312/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
: Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Combined Asset: (i) 1 No. of 12ῼ Series Bus reactor at Mandola 400/220 kV (POWERGRID) Substation along with associated bays, (ii) 1 No. of 12ῼ Series Bus reactor at Ballabhgarh 400/220 kV (POWERGRID) Substation along with associated bays, (iii) 1 no. Series Line Reactor of 12ῼ in Dadri-Mandola 400 kV, Ckt-I  and (iv) 1 no. Series Line Reactor of 12ῼ in Dadri-Mandola 400 kV, Ckt-II
Preliminary Scrutiny
46
311/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from Anticipated DOCO to 31.03.2019 for 2 x 500MVA, 400/220kV ICTs along with associated transformer bays & 6 no. 220kV line bays at 400/220kV Indore substation under Western Region System Strengthening Scheme-XIV.
Preliminary Scrutiny
47
39/RP/2018 in 64/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the order dated 20.07.2018 passed by this Hon'ble Commission in Petition No. 64/TT/2018.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
48
38/RP/2018 in 116/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the Order dated 20.07.2018 passed by this Hon�ble Commission in Petition No. 116/TT/2017 titled Power Grid Corporation of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Limited and Ors.
Preliminary Scrutiny
49
310/GT/2018
SJVN Limited
Petition under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for revision of tariff of Nathpa Jhakri Hydro Electric Power Station (6x250 MW) for the period 01.04.2004 to 31.03.2009.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
50
309/GT/2018
SJVN Limited
Petition under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for revision of tariff of Nathpa Jhakri Hydro Electric Power Station (6x250 MW) for the period 01.04.2009 to 31.03.2014- Truing-up of tariff determined by the CERC order dated 20.06.2014 in Petition No.168/GT/2013
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
51
308/GT/2018
NHPC LTD
Petition under regulation 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 8(1) & 14 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of final tariff for the period 2014-19 in respect of Uri-II Power Station.
Preliminary Scrutiny
52
307/MP/2018
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
Petition under Section 79 (1) (f) of the Electricity Act, read with Clause 6.6 of the CERC (Indian Electricity Grid Code) Regulations, 2010 regarding outstanding amount of Reactive Energy Charges.
Preliminary Scrutiny
53
306/GT/2018
NTPC Limited
Approval of Generation Tariff for Lara STPS (2x800 MW) from anticipated COD of U#1(i.e.30.09.2018 to 31.03.2019)
Preliminary Scrutiny
54
305/TD/2018
Amplus Energy Solutions Private Limited
UPGRADE FROM CAT IV TO II
Order reserved
55
304/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(b), 79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term, Medium Term Open Access in Intra State and related matters) Regulations, 2009
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
56
303/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term, Medium Term Open Access in Intra State and related matters) Regulations, 2009
Hearing
57
302/MP/2018
Power Exchange India Limited (PXIL)
Petition seeking additional time period to comply with the Networth Norms and Shareholding Pattern as prescribed under Regulations 18(i), 19(1) and 20 of the Central Electricity Regulatory Commission (Power Market) Regulations, 2010.
Order reserved
58
301/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 (1) (b) & (f) of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreements dated 17.03.2010, 21.03.2013 and 27.11.2013 executed between GMR Warora Energy Limited and the Procurers for compensation due to Change in Law impacting revenues and costs during the Operating Period.
Preliminary Scrutiny
59
300/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition under Section 79 (1) (b) & (f) of the Electricity Act, 2003 read with Regulation 14 (3) (ii) and Regulation 8 (3) (ii) of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations 2014 and read with statutory framework governing procurement of power through Competitive Bidding and Article 10 and 13of the respective Power Purchase Agreements, executed between GMR Kamalanga Energy Limited and its beneficiaries, seeking compensation on account of Change in Law events impacting revenues and costsduring the Operating Period.
Preliminary Scrutiny
60
299/MP/2018
Bharat Aluminium Company Limited (BALCO)
Petition under Section 79 of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 for clarification regarding construction modalities for BALCO- Dharamjaygarh 400 kV D/C (2nd D/C Line) for the purpose of connectivity to BALCO for 250 MW as a bulk consumer
Reply / additional information as per ROP to filed by Petitioner,Respondent
61
298/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Claim of Fixed Charges due to unilateral termination of PPA by WBSEDCL in regard to supply of power from Koderma TPS of DVC
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
62
297/MP/2018
bhopal dhule transmission company limited (BDTCL)
Petition under Section 63 and 79(1)(f) read with Section 79(1)(c) of the Electricity Act, 2003 seeking compensatory and declaratory relief under the Transmission Services Agreement dated 07.12.2010 on account of certain Change in Law events inter alia pursuant to the liberty granted by this Hon?ble Commission vide its Order in Petition No. 216/MP/2016 dated 25.06.2018.
Preliminary Scrutiny
63
296/MP/2018
Meenakshi Energy Private Limited (MEPL)
PETITION UNDER SECTION 79 (1) (F) AND SECTION 79 (1) (K) OF THE ELECTRICITY ACT, 2003 READ WITH SECTION 79 (1) (C) OF THE ELECTRICITY ACT, 2003 CHALLENGING THE ILLEGAL AND UNLAWFUL CONDUCT OF POWER GRID CORPORATION OF INDIA LIMITED OF WRONGFULLY RAISING INVOICES FOR TRANSMISSION CHARGES UPON THE PETITIONER IN A MANNER INCONSISTENT WITH APPLICABLE REGULATIONS AND ORDERS OF THIS HON�BLE COMMISSION AND SEEKING DIRECTIONS AGAINST POWER GRID CORPORATION OF INDIA LIMITED TO COMPLY WITH ITS STATUTORY AND CONTRACTUAL OBLIGATIONS.
Order reserved
64
295/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: Replacement of existing 1 no. 50MVA, 220/132kV ICTs by 160MVA, 220/132kV ICT at Balipara Substation along with replacement of 132kV equipment and Asset-2: 2nd 400/220kV, 315MVA ICT, new 220kVBus arrangement (GIS) with 4 nos. of 220kV Bays at Bongaigaon Substationof POWERGRID along with stringing of 2nd Circuit of 220kV D/C Bongaigaon-Salakati TL and 1 no. of 220kV line bay at Salakati Substation(for 220kV D/C Bongaigaon-Salakati TL) under �North Eastern Region Strengthening Scheme-III� in North-Eastern Region.
Preliminary Scrutiny
65
37/RP/2018 in 1/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the order dated 23.07.2018 passed by this Hon'ble Commission in Petition No. 01/TT/2018.
Preliminary Scrutiny
66
36/RP/2018 in 122/MP/2018
Lanco Anpara Power Limited LAPL
Review Petition against Order dated 23.07.2018
Order reserved
67
294/MP/2018
Azure Power India Private Limited (APIPL)
Petition under Section 79 of the Electricity Act, 2003
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
68
293/MP/2018
Azure Power India Private Limited (APIPL)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Limited dated 19.04.2016 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Preliminary Scrutiny
69
292/MP/2018
Gokak Power & Energy Limited (GPEL)
Petition under Section 66 & 79 of the Electricity Act, 2003 read with Regulations 14 & 15 CERC (Terms and Conditions for recognition & issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 for issuance of directions to the Respondents, National Load Despatch Centre and the State Load Despatch Centre, to effect accreditation and registration of the Petitioner under the Renewable Energy Certificates (REC) mechanism and consequent reliefs.
Preliminary Scrutiny
70
291/MP/2018
West Central Railway (WCR)
Petition under Section 79(1)(c) and 79(1)(h) of Electricity Act 2003 and CERC Open Access Regulations 2008 and CERC Inter-State Transmission Regulation 2009, for Deviation Settlement Account
Preliminary Scrutiny
71
290/MP/2018
ACB (India) Limited ACB
A petition under Section 79(1)(c) read with 79(1)(k) of the Electricity Act, 2003 for allowing M/s S V Power Private Limited to use the dedicated transmission line (Petitioner�s plant to Bharari, Bilaspur Pooling station of PGCIL) on sharing basis along with other beneficiaries
Hearing
72
289/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
Petition invoking Section 79(1)(b) and (f) of the Electricity Act, 2003 seeking payment of Capacity Charges and Transmission Charges as per the applicable provisions of the PPAs dated 18.01.2014 and 20.01.2014.
Reply / additional information as per ROP to filed by Petitioner,Respondent
73
288/MP/2018
jabalpur transmission company limited (JTCL)
Petition for approval for creation of security interest under Sections 17(3) & 17(4) of Electricity Act, 2003 over Petitioner No. 1�s Assets in favour of Petitioner No. 2 its Lender and for any subsequent transferees, assigns, novatees thereof and any refinancing lenders to the Project.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
74
287/MP/2018
Pranurja Solutions Limited Pranurja
Seeking trading license under Section 14 to operate a power exchange
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
75
286/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 for execution of the Orders dated 14.03.2018 passed in Petition No. 13/SM/2017 and 16.03.2018 passed in Petition No. 1/MP/2017; and initiation of proceedings under Section 142 of the Electricity Act, 2003 against Tamil Nadu Generation and Distribution Corporation Ltd. in relation thereto.
Hearing
76
285/MP/2018
Maithon Power Limited (MPL)
Petition for inclusion of liquidated damages deducted from Capital Cost and re-computation of trued-up tariff for the period FYs 2011-14 and tariff for FYs 2014-19 pursuant to Order dated 26.12.2017 in Petition No. 152/GT/2015 in respect of Maithon Right Bank Thermal Power Plant (Units I and II)(2 X 525 MW) of Maithon Power Ltd.
Hearing
77
284/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreements dated 17.03.2010 and 21.03.2013 executed between GMR Warora Energy Limited and the Distribution Companies in the States of Maharashtra and Dadra and Nagar Haveli respectively for compensation due to Changes in Law
Reply / additional information as per ROP to filed by Petitioner,Respondent
78
283/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 50 MVAR Line reactor at Jaipur (South) in 400 kV D/C Kota- Jaipur (South) line (Part of 400 kV D/C Rapp- Jaipur TL) utilized as Bus reactor at Jaipur (south) substation (DOCO: 05.03.2018) and Asset-II:400KV D/C Kota - Jaipur (South) line along with associated bays at Kota and Jaipur(South) (part of RAPP-Jaipur (S) 400KV D/C line with one ckt LILO at Kota) (Anticipated DOCO: 01.08.2018: Anticipated) under �Transmission system associated with RAPP 7&8, Part-B� in Northern Region�.
Preliminary Scrutiny
79
282/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff for the period  30.06.2012 to 31.03.2014 in respect of Chamera-III Power Station.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
80
281/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff for the period 29.06.2010 to 31.03.2014 in respect of Sewa-II Power Station.
Preliminary Scrutiny
81
280/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff in respect of Teesta Low Dam-III Power Station for the period 01.04.2013 to 31.03.2014.
Preliminary Scrutiny
82
279/GT/2018
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business), Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) & 9(1) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for determination of final tariff for the period 11.10.2013 to 31.03.2014 in respect of Uri-II Power Station.
Preliminary Scrutiny
83
278/MP/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section  79(1)(c) & 79(1)(f) of the Electricity Act, 2003 read with Regulation 32 and the detailed procedure as envisaged under the central electricity regulatory commission (grant of connectivity, long term, medium term open access in intra state and related matters) regulations, 2009
Reply / additional information as per ROP to filed by Petitioner,Respondent
84
277/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset I: Shifting of 1x315 MVA, 400/220kV  ICT from any suitable location (after replacement by 1x500 MVA ICT) and install it at Jamshedpur 400/220Kv Substation as 3rd ICT along-with associated bays, Asset II: Modification of 132kV Bus arrangement with GIS bays at 220/132kV Purnea S/S, , Asset-III: Spare 1 no unit of 765kV,110 MVAR Single Phase Reactor stationed at Sasaram, Asset-IV: 3rd 500 MVA, 400/220kV  ICT at Patna(POWERGRID) substation along-with associated bay Asset V: 01 Nos 500 MVA Single phase spare unit of 765/400 kV ICT at Angul S/S Asset-VI: 01 Nos 500 MVA Single phase spare unit of 765/400 kV ICT at Sundergrah S/S under Eastern Region Strengthening Scheme XII in Eastern Region.
Preliminary Scrutiny
85
35/RP/2018 in 261/TT/2015
MB Power (Madhya Pradesh) Limited (MBPMPL)
PETITION FILED UNDER REGULATIONS 103 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REUGLATIONS, 1999 SEEKING REVIEW OF THE ORDER DATED 27.05.2016 PASSED BY THE HON�BLE COMMISSION IN PETITION NO. 261/TT/2015 IN VIEW OF MATERIAL IRREGULARTIES WHILE PASSING THE ORDER DATED 261/TT/2015.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
86
276/GT/2018
JINDAL INDIA THERMAL POWER LIMITED (JITPL)
Petition under Section 62 read with Sections 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 and read with principles provided under Section 61 of the Electricity Act, 2003 for determination of Tariff of 2X600 MW Coal Based Power Project at Village-Derang, District-Angul, Odisha for the period commencing from 12.02.2015 for the control period of 2014-19.
Preliminary Scrutiny
87
275/MP/2018
Tata Power Trading Company Limited (TPTCL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 15 of the Power Purchase Agreement dated 13.12.2011
Hearing
88
34/RP/2018 in 229/MP/2017
Power Company of Karnataka Limited PCKL
Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) regulations, 1999 for review of the Order dated 20.07.2018 passed by the Hon�ble Commission in Petition No. 229 / MP / 2017
Preliminary Scrutiny
89
272/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I - STATCOM  System (+/-) 300MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor), cooling system & STATCOM protection / controller  etc at Ranchi Substation (Anticipated DOCO: 31.07.2018) & Asset II - STATCOM  System (+/-) 200MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor and 2x125 MVAR Capacitor), cooling system & STATCOM protection / controller  etc at Kishanganj Substation (Anticipated DOCO: 31.12.2018) under ?Eastern Region Strengthening Scheme ?XI (ERSS-XI)  ?
Preliminary Scrutiny
90
271/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations‟1999 and CERC (Terms and Conditions of Tariff) Regulations ‟2014 for determination of Transmission Tariff from anticipated DOCOs to 31.03.2019 for Assets (07 Nos) under Eastern Region Strengthening Scheme XIV in Eastern Region.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
91
270/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for Procurement of 3 Nos. Spare Converter Transformers (234 MVA, 1-ph, 3 winding) at Bhadrawati  HVDC Back to Back Station - DOCO ? 22.03.2018 (actual) under  ?Installation of Transformer and Procurement of Spare Converter Transformer at Bhadrawati HVDC Back to Back Station? for tariff block 2014-19 in Western Region.
Preliminary Scrutiny
92
269/MP/2018
Adani Power (Mundra) Limited (APMuL)
PETITION UNDER SECTION 142 OF THE ELECTRICITY ACT, 2003
Hearing
93
268/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: One No. 220kv line Bays (205 no. Bay) associated with Baghpat GIS Substation (DOCO: 03.07.2016), Asset-II: One No. 220kv line Bays (210 no. Bay) associated with Baghpat GIS Substation (DOCO: 03.07.2016), Asset-III: One No. 220kv line Bays (206 no. Bay) associated with Baghpat GIS Substation (DOCO: 20.08.2016), Asset-IV: One No. 220kv line Bays (207 no. Bay) associated with Baghpat GIS Substation (DOCO: 26.01.2017) and Asset-V: One No. 220kv line Bays (212 no. Bay) associated with Baghpat GIS Substation (DOCO: 26.01.2017) under �Northern Region System Strengthening Scheme- XIX� in Northern Region�.
Preliminary Scrutiny
94
267/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for (Asset-1): Central sector portion (1646.039 kms) & (Asset-2): BBMB (2.35 kms) for Establishment of Fibre Optic communication system in Northern region (1648.389 Kms )
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
95
266/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 Asset-1: 2 nos. 500 MVA, 400/220kV ICTs along with associated bays at Parli (POWERGRID) Switching Station and 4 nos. 220kV line bays (for LILO of Parli - Harangul 220kV lines and Parli Osmanabad 220kV S/C line), Asset-2: 2 nos. 220kV line bays at Mapusa (Colvale) (POWERGRID Substation (for Mapusa(Colvale) (POWERGRID)-Tuem 220kV D/C line) and Asset-3: 2 nos. 400kV line bays for 400kV D/C Indore (POWERGRID)-Ujjain TL at 765/400 kV Indore (POWERGRID) Substation under WRSS XVI for tariff block 2014-19 period.
Preliminary Scrutiny
96
265/MP/2018
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Petition under section 79 (1) (f) read with Section 142 of the Electricity Act, 2003 for issuance of direction for quashing of the letter dated 02.08.2018 issued by Power Grid Corporation of India Limited (PGCIL) whereby, PGCIL has wrongful and arbitrarily proceeded to impose transmission charges to the tune of Rs. 6.41 Crores upon the Petitioner towards Long Term Access (LTA) capacity 8.4 MW and also, through a subsequent letter dated 14.08.2018 threatened curtailment of Short Term Open Access with effect from 23.08.2018. The same is in direct contravention of the final Order passed by this Hon�ble Commission in Petition No. 190/MP/2016 dated 31.05.2018.
Reply / additional information as per ROP to filed by Petitioner
97
264/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (C), 79(1)(B) AND 79(1)(F) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 AGAINST THE RESPONDENT NO. 1 CHALLENGING THE NOTICE DATED 01/08/2018 FOR TERMINATION OF THE TRANSMISSION SERVICES AGREEMENT EXECUTEDWITH THE PETITIONER
Reply / additional information as per ROP to filed by Petitioner,Respondent
98
263/MP/2018
ENN ENN CORP LTD (ENNENN)
Petition under Section 79(1) of the Electricity Act, 2003 and Section 14 & 15 of Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010, challenging the illegal and arbitrary rejection of grant of REC application of the Petitioner by Respondents
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
99
262/MP/2018
Western Transmission (Gujarat) Limited (WTGL)
Petition by M/s Western Transmission (Gujrat) Limited (the �Petitioner/ WTGL�) under Section 17(3) and (4) of the Electricity Act, 2003 read with Article 14.2 of the Power Transmission Agreement dated 16.01.2009 and Article 17.2.2 of the Transmission Service Agreement dated 17.10.2017 as well as Articles 10.1.14 and 10.1.25 of the debenture trust deed dated 18.06.2018 (the �Debenture Trust Deed� as amended from time to time) enetered into between the WTGL and Catalyst Trusteeship Limited (the �Debenture Trustee� which expression shall, unless it be repugnant to the context or meaning thereof, be deemed to mean and include its successors, substitutes and permitted assigns) acting for the benefit of the debenture holders and also Article 6.1.14 and 6.1.25 of the Common Rupee Loan Agreement dated 27.12.2017 (the �Common Rupee Loan Agreement� as amended from time to time) enetered into between, inter alia, the WTGL and HDFC Bank Limited (the �Term Lender� which expression shall, unless it be repugnant to the subject or context thereof, be deemed to mean and include its successors and also any other banks or financial institutions or any other Person to whom the rights and/ or obligations of the aforementioned Term Lender are assigned, novated and/ or transferred), seeking approval for creation of security interest in the favour of Catalyst Trusteeship Limited acting as Common Security Trustee for the benefit of inter alia the debenture holders, the Term Lenders and the Working Capital Lender (defined below).
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
100
261/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1- 1 no. 765 kV line bay at 765/400kV Bilaspur Pooling Station (for Sipat STPS (NTPC) - Bilaspur PS (PG) 765kV 3rd S/c) under �POWERGRID Works associated with Additional System Strengthening for Sipat STPS� in Western Region.
Preliminary Scrutiny
101
260/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (C), 79(1)(B) AND 79(1)(F) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 AGAINST THE RESPONDENT NO. 1 CHALLENGING THE NOTICE DATED 30/07/2018 FOR REGULATING POWER SUPPLY BY THE PETITIONER TO ITS PROCURERS
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
102
259/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from actual/ anticipated DOCOs to 31.03.2019 for Assets (04 nos) associated with �Eastern Region Strengthening Scheme � XV (ERSS-XV)� in Eastern Region.
Preliminary Scrutiny
103
258/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset 2 Nos 400kV line bays at Srikakulam for termination of Srikakulam Pooling Station - Garividi 400kV Quad D/c line under ''Substation Works Associated With Strengthening Of Transmission System Beyond Vemagiri'' in Southern Region
Preliminary Scrutiny
104
257/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset �(i) LILO of Kurnool-Thiruvalam 765kV D/C line at Cuddapah (ii) Cuddapah-Hindupur 400kV (Quad) D/C line (iii) Establishment of 765/400kV substation at Cuddapah with 2X1500MVA Transformer (GIS) alongwith associated bays and 2X240MVAR Bus Reactors (iv) 2X80MVAR Switchable Line Reactor and 02 nos 400kV line bays at Hindupur Substation under �System Strengthening-XXIV in Southern Region�.
Preliminary Scrutiny
105
256/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for 1 nos 400KV bay each at Salem New (Dharmapuri) and Madhugiri for terminating Salem New (Dharmapuri)- Madhugiri 765KV S/C Line -2 (Initially charged at 400KV) being implemented under tariff based bidding and 1 no. 63MVAR line reactor at Madhugiri end of Salem New (Dharmapuri)- Madhugiri 765KV S/C Line -2 (Initially charged at 400KV) being implemented under tariff based bidding under "Common Transmission scheme associated with ISGS projects in Nagapattinam/Cuddalore area of Tamil Nadu -Part-A1 (b) "  in Southern Region.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
106
255/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 400/220 kV 500MVA ICT-I at Mandola S/s (DOCO: 28.03.2016), Asset-II: 400/220 kV 500MVA ICT-II at Mandola S/s (DOCO: 16.10.2016), Asset-III: 400/220 kV 500MVA ICT-III at Mandola S/s (DOCO: 10.04.2016), Asset-IV: 400/220 kV 500MVA ICT-IV at Mandola S/s (DOCO: 08.05.2016), Asset-V: 400/220 kV 500MVA ICT-I at Ballabhgarh S/s (DOCO: 28.03.2016) and Asset-VI: 400/220 kV 500MVA ICT-II at Ballabhgarh S/s (DOCO: 16.09.2016) under NRSS-XXXII in Northern Region.
Preliminary Scrutiny
107
254/MP/2018
Gati Infrastructure Pvt. Ltd.
A PETITION UNDER SECTION 79 (1) (c) AND 79 (1) (f) OF THE ELECTRICITY ACT, 2003 SEEKING OPEN ACCESS/ EVACUATION OF THE ENTIRE INSTALLED CAPACITY
Preliminary Scrutiny
108
253/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for ASSET-I: 01x500MVA, 400/220kV/33 ICT and associated bays each at Warangal S/S, Khammam S/S, Gooty S/S and Kadapa S/S under System strengthening-XX�  in Southern region.
Preliminary Scrutiny
109
33/RP/2018 in 6/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review and modification of this Hon�ble Commission�s Order dated 22.06.2018 in Petition No. 06/TT/2018 filed by Power Grid Corporation of India Limited.
Preliminary Scrutiny
110
32/RP/2018 in 241/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review and modification of this Hon�ble Commission�s Order dated 21.06.2018 in Petition No. 241/TT/2016 filed by Power Grid Corporation of India Limited.
Preliminary Scrutiny
111
31/RP/2018 in 110/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94(1)(F) OF THE ELECTRICITY ACT, 2003 READ WITH REGULATION 103 OF THE CERC (CONDUCT OF BUSINESS) REGULATIONS, 1999 FOR REVIEW AND MODIFICATION OF THE ORDER DATED 29.06.2018 IN PETITION NO. 110/TT/2017
Preliminary Scrutiny
112
30/RP/2018 in 26/TT/2016,133/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94(1)(F) OF THE ELECTRICITY ACT, 2003 READ WITH REGULATION 103 OF THE CERC (CONDUCT OF BUSINESS) REGULATIONS, 1999 FOR REVIEW AND MODIFICATION OF THE ORDER DATED 29.06.2018 IN PETITION NO. 133/TT/2017
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
113
251/MP/2018
Adani Power (Mundra) Limited (APMuL)
Petition under Sections 79(1)(f) of the Electricity Act, 2003 read with Article 13 of the PPAs dated 07.08.2008 for payment of compensation pursuant to the relief of Change in Law granted by this Ld. Commission by its Order dated 31.05.2018.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
114
250/RC/2018
MITTAL PROCESSORS PRIVATE LIMITED MPPL
Petition for the regulatory compliance on account of change of name and further necessary changes in documents held in the name of Mittal Processors Pvt. Ltd. to Kreate Energy (I) Pvt. Ltd. under Section 17(3) of the Electricity Act read with Regulation 7(t) of Grant of Trading License Regulations, 2009.
Reply / additional information as per ROP to filed by Petitioner
115
249/MP/2018
Adani Power (Mundra) Limited (APMuL)
Petition under Sections 79 of the Electricity Act, 2003 read with Article 13 of the PPAs dated 07.08.2008 for approval of Carrying Cost in terms of the Order of the Ld. Commission dated 31.05.2018.
Reply / additional information as per ROP to filed by Petitioner,Respondent
116
248/MP/2018
NHPC LTD
Miscellaneous petition for approval of Renovation & Modernization of Loktak Power Station (105MW) in Manipur
Preliminary Scrutiny
117
29/RP/2018 in 216/MP/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
PETITION UNDER SECTION 94 OF THE ELECTRICITY ACT, 2003 READ WITH REGULATION 103(1) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999, READ WITH ORDER 47 RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 FOR REVIEW OF ORDER DATED 25.6.2017 IN PETITION NO.216/MP/2016 PASSED BY THIS HON�BLE COMMISSION.
Preliminary Scrutiny
118
247/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for assets under WRSS XVII for tariff block 2014-19 period.
Preliminary Scrutiny
119
28/RP/2018 in 183/TT/2016
DANS Energy Private Limited (DEPL)
Memorandum of Review Petition
Reply / additional information as per ROP to filed by Petitioner,Respondent
120
246/MP/2018
BHILANGAHA HYDRO POWER LIMITED (BHPL)
In the matter of declaration and consequent direction for determination of transmission charges for the 220 kV D/C Bhilangana-III - Ghansali line in terms of the order dated 10.05.2018 passed by the Hon�ble Supreme Court in Civil Appeals No. 2368-70 of 2015
Preliminary Scrutiny
121
245/MP/2018
ONGC Tripura Power Company (OTPC)
OTPC Palatana Project - Miscellaneous Petition for Extension of Relaxation in NAPAF Norms
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
122
27/RP/2018 in 146/MP/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) regulations, 1999 for review of the Order dated 28.05.2018 passed by the Hon?ble Commission in Petition No. 146/MP/2017 in the matter of Approval under Regulation 54 and Regulation 55 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014, ?Power to Relax‟ and ?Power to remove Difficulty? for one time reimbursement of carrying cost for replacement of porcelain insulators with Polymer Insulators of the assets covered under Petition No. 305/2010 in respect of Northern Region.
Preliminary Scrutiny
123
26/RP/2018 in 222/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review under regulation 103 (1) of the CERC (Conduct of Business) Regulation 1999 of Order dated May 14, 2018 of the Central Electricity Commission in Petition No. 222/TT/2016.
Preliminary Scrutiny
124
25/RP/2018 in 108/TT/2016
Teestavalley Power Transmission Limited TPTL
Review Petition under Section  94(1)(f) of the Electricity Act, 2003 read with Regulation 103 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations 1999, seeking review/modification of the Order dated 15.05.2018 passed by this Hon'ble Commission in Petition No. 108/TT/2016, in the matter of  approval of transmission tariff of circuit # 2 and circuit # 1(a) of 400 kV D/C Teesta III-Rangpo Section of 400 kV D/C Teesta III ? Kishanganj Transmission Line for the control period 2014-19.
Preliminary Scrutiny
125
244/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for  determination of Transmission Tariff  of Asset-I: Chittorgarh � Ajmer   765 KV D/C line along with associated bays and 240 MVAR Switchable Line reactors at both end under �Green Energy Corridors:  Inter State Transmission  Scheme (ISTS)- Part-B� in Northern Region.
Preliminary Scrutiny
126
243/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Expansion and Replacement of existing SCADA/EMS System at SLDC�s of Northern Region (NR ULDC Phase-II)�.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
127
242/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of Transmission Tariff for Asset-I: 2X80 MVAR,400 KV Switchable Line Reactors for 400 KV D/C Agra-Sikar TL at Agra Substation (DOCO: 01.08.2017) Asset-II: 63 MVAR Line Reactor (to be used as Bus Reactor) connected to 400 KV Lower Subansiri-BNC-I Line Bay along with associated bays at � 800 KV Biswanath Chariali HVDC Converter terminal (DOCO: 21.07.2017)   and Asset-III: 63 MVAR Line Reactor (to be used as Bus Reactor) connected to 400 KV Lower Subansiri-BNC-III Line Bay at � 800 KV Biswanath Chariali HVDC Converter terminal (DOCO: 11.12.2017)  from  DOCO to 31.03.2019 under the transmission system associated with �NORTH EAST � NORTHERN/WESTERN INTERCONNECTOR  � I PROJECT��
Preliminary Scrutiny
128
241/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 765kV, 2 x 330 MVAR Switchable Line Reactors to be charged as Bus Reactor at Dharamjaigarh end in both ckt of Jharsuguda- Dharamjaigarh 765 kV D/C Line  under ?Common System Associated with East Coast Energy Private Limited and NCC Power Projects Limited LTOA Generation Projects in Srikakulam Area ? B? in Western Region.
Preliminary Scrutiny
129
240/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation 8(1) of CERC (Terms and Conditions of Tariff) Regulations�2014 for interim true up of Transmission Tariff from actual DOCO to 31.03.2019 for 05 Nos of Assets under Transmission System for Phase-I Generation Projects in Jharkhand and West Bengal Part-B� in Northern Region.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
130
239/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCOs to 31.03.2019 for Asset I: 01 Nos of OPGW link under Central Sector (10.70 Km); Asset-II: 05 Nos of OPGW link under DVC Sector portion (52.527 Km); Asset-III: 04 Nos of OPGW link under WBSETCL Sector (4.794 Km); Asset-IV: 01 Nos of OPGW link under BSPTCL Sector (6.00 km); Asset-V: 02 Nos of OPGW link under OPTCL Sector (5.50 Km) and Asset-VI: 01 Nos of OPGW link under DVC Sector (69.182 Km) under the project fibre optical communication system in lieu of existing Unified Load Dispatch and Communication(ULDC) Microwave links in Eastern Region.
Preliminary Scrutiny
131
238/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Asset I: Balance portion of 400 kV D/C Baripada - Jamshedpur (DVC) Transmission Line along with bay at Jamshedpur (DOCO: 01.10.2013), Asset II: Reconductring of circuit-II of 400 kV Siliguri-Purnea D/C line (DOCO: 01.06.2013) under Eastern Region Strengthening Scheme-I for Eastern Region.
Preliminary Scrutiny
132
237/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for  determination of Transmission Tariff  from anticipated DOCO to 31.03.2019 for 05 nos of Transmission Assets under �North Eastern Region Strengthening Scheme-IV (NERSS-IV)� for 2014-19 Tariff Block Period in North-Eastern Region.
Preliminary Scrutiny
133
236/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval of Transmission Tariff for assets under WRSS V
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
134
235/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 2 Nos 765 kV line Bays alongwith 2 nos. 330 MVAr Line reactor at Vindhyachal Pooling Station and 2 Nos 765 kV line Bays alongwith 2 nos. 330 MVAr Line reactor at Jabalpur Pooling Station for 765 kV D/C Vindhyachal Pooling Station-Jabalpur Pooling Station TL (TBCB) under �Substation Extensions for Transmission system associated with Vindhyachal-V Project of NTPC (Part-B)� for tariff block 2014-19 period.
Preliminary Scrutiny
135
234/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For (1):LILO of Circuit-1 of 400 kV D/C Bareily-Mandola Line at Meerut Sub-station (DOCO: 01.10.2012), (2): LILO of Circuit-2 of 400 kV D/C Bareily-Mandola Line at Meerut Sub-station (DOCO: 01.04.2013),(3): 765 kV Bays for Bhiwani-Moga Line at Bhiwani Sub-station;765 kV 240 MVAR Bus Reactor-I alongwith associated bays at Bhiwani sub-station;765/400 kV 1000 MVA ICT-I alongwith associated bays at Bhiwani Sub-station;02 Nos.400 kV Bays for Hisar-Bahadurgarh at Bhiwani Sub-station(DOCO: 01.06.2012), (4): LILO of Hisar-Bawana at Bhiwani alongwith 02 No.400 kV Bays at Bhiwani Sub-station(DOCO:01.07.2012), (5): 765 kV bays for Jattikalan-Bhiwani Line at Bhiwani Sub-station(DOCO:01.10.2012), (6): 765 kV S/C Meerut-Bhiwani Line alongwith associated bays at Meerut & Bhiwani and 765 kV,240 MVAR Line Reactor at Bhiwani Sub-station(DOCO:01.02.2014), (7): 765/400 kV,1000 MVA ICT-II alongwith associated bays at Bhiwani Sub-station(DOCO: 01.10.2012),  (8): 765 kV 240 MVAR Bus Reactor-II alongwith associated bays at Bhiwani Sub-station(DOCO:01.07.2012) and (9):400/220 kV Ballabgarh Substation (re-alignment works)  (DOCO 01.12.2012)   under �765 kV System for Central Part of Northern Grid-Part III�.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
136
233/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset-LILO of existing Neyveli TS-II �Pondicherry 400KV S/c at NNTPS generation switchyard under �Transmission system for evacuation of power from 2X500MW Neyveli Lignite Corp. Ltd TS-1(Replacement) (NNTPS)� in Southern Region.
Preliminary Scrutiny
137
232/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
PETITION UNDER SECTION 79 (1) (F) READ WITH SECTION 79 (1) (K) OF THE ELECTRICITY ACT, 2003 SEEKING ADJUDICATION OF DISPUTE ARISING OUT OF THE LETTER ISSUED BY POWER GRID CORPORATION OF INDIA LIMITED DATED 02.05.2018, 23.07.2018 AND 06.08.2018 WHICH HAVE BEEN ISSUED ILLEGALLY AND ARBITRARILY AND ARE PATENTLY AGAINST THE SCHEME OF THE REGULATORY FRAMEWORK ISSUED BY THE CENTRAL ELECTRICITY REGULATORY COMMISSION IN THIS REGARD.
Reply / additional information as per ROP to filed by Petitioner,Respondent
138
230/MP/2018
EASTERN REGIONAL LOAD DESPATCH CENTRE (ERLDC)
Petition under Section 142 of the Electricity Act, 2003 for violation of Regulation 10 of the DSM Regulations 2014 and for persistent default in payment of ERLDC charges stipulated under CERC (RLDC Fees & Charges and related matters) Regulations 2015.
Preliminary Scrutiny
139
229/MP/2018
Prayatna Developers Private Limited (PDPL)
Petition under Section 79 (1) (b) and (f) and other applicable provisions of the Electricity Act, 2003.
Preliminary Scrutiny
140
228/MP/2018
NTPC Limited
Petition for Extension of cut off date of Koldam Hydro Electric Power Project, from 31.03.2018 to 31.03.2020.
Preliminary Scrutiny
141
227/MP/2018
DB Power Limited (DBPL)
Petition under Section 142 read with Section 149 of the Electricity Act, 2003 and Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 inter alia seeking initiation of appropriate action against the Respondents for non-compliance of the Order dated 19.12.2017 passed by the Commission in Petition No. 229/MP/2016
Reply / additional information as per ROP to filed by Petitioner,Respondent
142
226/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 27.07.2016, executed between the Parampujya Solar Energy Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
143
225/MP/2018
DB Power Limited (DBPL)
Petition under Section 142 read with Section 149 of the Electricity Act, 2003 and Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999  inter alia seeking initiation of appropriate action against the Respondents for non-compliance of the Order dated 19.12.2017 passed by the Commission in Petition No. 101/MP/2017
Preliminary Scrutiny
144
224/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
Pe�tition invoking Section 79(1)(b) and Section 79(1)(f) of the Electricity Act, 2003 seeking directions for applicability of the provisions of PPAs dated 18.01.2014 and 20.01.2014 for the purpose of calculation of penalties for maintaining the Availability below 80% for a Contract Year.
Order reserved
145
223/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of energy charges in case of shortfall in generation due to reasons beyond control of Teesta Low Dam-III Power Station in FY 2014-15.
Preliminary Scrutiny
146
222/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of energy charges in case of shortfall in generation due to reasons beyond control of Teesta Low Dam-III Power Station in FY 2016-17.
Preliminary Scrutiny
147
221/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recovery of energy charges in case of shortfall in generation due to reasons beyond control of Teesta Low Dam-III Power Station in FY 2015-16.
Preliminary Scrutiny
148
220/MP/2018
Kerala State Electricity Board Limited (KSEB Ltd.)
Adjudication of disputes on the recovery of transmission charges of Element-II and Element-III of Kudgi Associated Transmission System from the beneficiaries before the Commercial Operation of Kudgi STPS.
Preliminary Scrutiny
149
219/TD/2018
NTPC Limited
APPLICATION FOR LICENCE FOR INTER STATE TRADING
Preliminary Scrutiny
150
24/RP/2018 in 97/MP/2017
HARYANA POWER PURCHASE CENTRE HPPC
Petition for review the Order dated 31.5.2018 passed by the Hon�ble Commission in Petition No. 97/MP/2017 and IA No. 21 of 2018
Order reserved
151
214/MP/2018
Adani Power (Mundra) Limited (APMuL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 13 of the PPAs dated 07.08.2008 in Order dated 28.03.2018 in Case No. 104/MP/2017
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
152
213/MP/2018
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 10 of the Power Purchase Agreements both dated 01.11.2013 entered into between the Petitioner and the Respondents, seeking approval of the cost to be incurred by the Petitioner on account of change in law, for installation/retrofit of ?Electrostatic Precipitators? (ESP), installation of Flue Gas Desulphurisation (FGD), installation of low NOx burners, providing Over Fire Air (OFA) and any other measures for compliance of the notification dated 07.12.2015 issued by the Ministry of Environment and Forests and Climate Change, Government of India in respect of Thermal Power Plants installed/commissioned after 01.01.2003;  and for other claims on account of Change in Law under the Power Purchase Agreements
Reply / additional information as per ROP to filed by Petitioner,Respondent
153
212/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 19.07.2016, executed between the Parampujya Solar Energy Pvt. Ltd. and Solar Energy Corporation of India, for seeking approval of Change in Law events due to enactment of the GST Laws
Hearing
154
211/MP/2018
Azure Power (Rajasthan) Private Limited AzureRajasthan
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Vidyut Vyapar Nigam Limited dated 10.01.2011 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Hearing
155
210/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Ltd. and Solar Energy Corporation of India Ltd. for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
156
209/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 23.08.2016, executed between the Parampujya Solar Energy Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
157
208/MP/2018
DB Power Limited (DBPL)
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity Act, 2003 and Article 10 of the Power Purchase Agreement dated 19.08.2013 entered into between the Petitioner and the Respondent, seeking approval of the cost to be incurred by the Petitioner on account of change in law, for installation/retrofit of �Electrostatic Precipitators� (ESP), installation of Flue Gas Desulphurisation (FGD), installation of low NOx burners, providing Over Fire Air (OFA) and any other measures for compliance of the notification dated 07.12.2015 issued by the Ministry of Environment and Forests and Climate Change, Government of India in respect of Thermal Power Plants installed/commissioned after 01.01.2003;  and for other claims on account of Change in Law under the Power Purchase Agreement
Reply / additional information as per ROP to filed by Petitioner,Respondent
158
207/MP/2018
Wardha Solar (Maharashtra) Private Limited (WSMPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreement dated 22.09.2016, executed between Wardha Solar (Maharashtra) Private Limited and Solar Energy Corporation of India Limited, for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
159
206/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 26.12.2016, executed between Parampujya Solar Energy Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
160
205/MP/2018
Himachal Baspa Power Company Limited (HBPCL)
Petition under Section 79(1) (c) of the Electricity Act, 2003 read with the Indian Electricity Grid Code seeking direction for scheduling overload capacity
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
161
204/MP/2018
Eingur Wind Energy Private Limited (EWE)
PETITION UNDER SECTIONS 66, 79 AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 READ WITH THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010
Preliminary Scrutiny
162
202/MP/2018
LANCO AMARKANTAK POWER LTD. LAMPL
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter-alia, seeking setting aside of communication dated 27.06.2018 issued by Respondent No. 1
Interim order issued
163
201/TD/2018
Reliance Energy Trading Limited (RETL)
Surrender the inter-State Trading Licence
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
164
200/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Transmission System under NRTSS in Northern Region consisting of Asset-I: 125 MVAR Bus Reactor at Jaipur South (01.01.2013) ,Asset-II : 400 kV Bhiwani Jind TL along with associated bays plus 1 nos. 500 MVA, 400/220 kV  ICT-I and associated bays at Jind Sub-station (01.04.2013), Asset-III: 400/220 kV 500 MVA ICT-II along with associated 400/220 kV bays at Jind Sub-station and one 220 kV Line bays (01.10.2013), and Asset-IV: 1 no. of 400 kV,125 MVAR Bus Reactor at Jind Sub-station alongwith associated bays(01.10.2013).
Preliminary Scrutiny
165
199/MP/2018
maheshwaram transmission limited (mtl)
Petition under Sections 63 and 79(1)(f) of the Electricity Act, 2003 read with the statutory framework and Article 12 of the Transmission Service Agreement dated 10.06.2015 executed between Maheshwaram Transmission Limited and its Long-Term Transmission Customers for claiming compensation due to Changes in Law.
Order reserved Petitioner
166
198/MP/2018
HPCL BIOFUELS LIMITED (HBL)
Petition to extend/revalidate accreditation under REC Mechanism
Reply / additional information as per ROP to filed by Petitioner,Respondent
167
197/MP/2018
Bharat Aluminium Company Limited (BALCO)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking recovery of the Escalable Energy Charges due to rectification in escalation rates of Domestic Coal falling within the scope of the Power Purchase Agreement dated 08.03.2013 (PTC-PPA) executed between the Petitioner and the Respondent No. 2 and as per the terms of the back to back Power Purchase Agreement executed by PTC with Kerala State Electricity Board (�KSEB-PPA�) dated 13.06.2013
Preliminary Scrutiny
168
196/MP/2018
A D Hydro Power Limited (ADHPL)
Petition under Section 142 of the Electricity Act 2003 for action against Respondent No. 1 for continuous noncompliance with the order dated 20.06.2017 of CERC in regard to the payment of the Petitioner.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
169
195/MP/2018
CROSS BORDER POWER TRANSMISSION COMPANY LTD (CPTC)
Modification of Transmission licence no. 12/Transmission/2010/CERC did 01.12.2010 granted to Cross Border Power Transmission Company Ltd for 400 KV D/C Muzaffarpur - Sursand Transmission line & 2 nos 220 KV line bays at Muzaffarpur S/S
Hearing
170
194/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
 For the assets of �Transmission System associated with Mundra Ultra Mega Power Project�
a. covered in CERC order dated 01.12.2014 in Petition no. 72/TT/2012
b. covered in CERC order dated 15.10.2015 in Petition no. 296/TT/2013
c. covered in CERC order dated 31.12.2015 in Petition no. 101/TT/2014
d. covered in CERC order dated 15.03.2016 in Petition no. 57/TT/2013
Hearing
171
23/RP/2018 in 229/MP/2016
DB Power Limited (DBPL)
PETITION UNDER SECTION 94(1)(f) OF THE ELECTRICITY ACT, 2003 READ WITH REGULATION 103 OF THE CERC (CONDUCT OF BUSINESS REGULATIONS), 1999 FOR REVIEW OF THE ORDER DATED 19.12.2017
Hearing
172
22/RP/2018 in 101/MP/2017
DB Power Limited (DBPL)
Petition under Section 94(1)(f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) Regulations, 1999 for review of the order dated 19.12.2017 passed by the Hon?ble Commission in Petition No. 101/MP/2017
Preliminary Scrutiny
173
193/MP/2018
ReNew Wind Energy (TN2) Private Limited
Revision of Tariff as a result of introduction of Goods and Services Tax
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
174
192/MP/2018
Phelan Energy India RJ Private Limited (PEIRJ)
Revision of Tariff as a result of introduction of Goods and Services Tax
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
175
191/MP/2018
Azure Clean Energy Private Limited (ACEPL)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 28.03.2014 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Reply / additional information as per ROP to filed by Petitioner,Respondent
176
190/MP/2018
Azure Greentech Private Limited (Azuregreentech)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 28.03.2014 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Reply / additional information as per ROP to filed by Petitioner,Respondent
177
189/MP/2018
ACME Rewa Solar Energy Private Limited (ARSEPL)
A Petition under Section 79(1)(b) of the Electricity Act, 2003 for the approval of �Change in Law� and consequent revision in capital cost due to introduction of the Central Goods and Services Tax Act, 2017 promulgated by the Department of Revenue, Ministry of Finance notified by way of notification dated 28.06.2017.
Reply / additional information as per ROP to filed by Petitioner,Respondent
178
188/MP/2018
Azure Solar Private Limited (Azurespl)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Vidyut Vyapar Nigam Limited dated 25.01.2012 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Reply / additional information as per ROP to filed by Petitioner,Respondent
179
187/MP/2018
ReNew Wind Energy (TN2) Private Limited
Revision of Tariff as a result of introduction of Goods and Services Tax
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
180
186/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER 79 (1)(B), 79(1)(F) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ISSUING DIRECTIONS TO THE RESPONDENTS TO REFUND THE AMOUNTS DEDUCTED ON VARIOUS HEADS CONTRARY AGAINST THE TERMS AND CONDITIONS OF THE POWER PURCHASE AGREEMENT DATED 31.07.2012 BETWEEN THE PETITIONER AND RESPONDENT.
Hearing
181
185/MP/2018
Azure Sunshine Private Limited (AzureSunshine)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 28.03.2014 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Reply / additional information as per ROP to filed by Petitioner,Respondent
182
184/MP/2018
Azure Power Mars Private Limited (AzureMars)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 05.02.2015 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central level and change in the rate of Service Tax, resulting in additional recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Reply / additional information as per ROP to filed by Petitioner,Respondent
183
183/MP/2018
Maruti Clean Coal and Power Limited (MCCPL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 seeking extension of Scheduled Delivery Date on account of force majeure events falling within the scope of the Power Purchase Agreement dated 01.11.2013 (PTC-PPA) executed between the Petitioner and the Respondent No. 5 and as per the terms of the back to back Power Purchase Agreement executed by PTC with Jaipur Vidyut Vitran Nigam Limited (�JVVNL�), Ajmer Vidyut Vitran Nigam Limited (�AVVNL�), Jodhpur Vidyut Vitran Nigam Limited (�JVVNL�) [hereinafter referred to as the �Procurer PPA�] dated 01.11.2013.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
184
182/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1- 400 kV, 125 MVAr Bus Reactor at Bina (DOCO-16.03.2016) under Installation of Bus Reactor & ICT in Western Region
Hearing
185
181/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Main SCADA EMS System (05 assets) under project � �Expansion/ Upgradation of SCADA/ EMS System of SLDCs of Eastern Region�.
Hearing
186
180/MP/2018
Suzlon Energy Limited (SEL)
Section 79(1)(f) of the Electricity Act, 2003 
(b) Clause 3.11 read with Clause 4.5 of the MNRE Guidelines for implementation of Scheme for selection of 3000 MW Grid Connected Solar PV Power Projects under Phase-II, Batch-II, Tranch-I for �State Specific Bundling Scheme� read with
(c) Article 11 (Force Majeure) and Article 16.3 (Dispute Resolution) of the Power Purchase Agreements dated 02.08.2016 executed between Solar Power Developers of Suzlon Energy Ltd. being (i) Aalok Solarfarms Ltd. (ii)  Abha Solarfarms Ltd. (iii) Shreyas Solarfarms Ltd. and (iv) Heramba Renewables Ltd. with NTPC Ltd.
Hearing
187
178/MP/2018
ACME Jodhpur Solar Power Private Limited (AJSPPL)
A Petition under Section 79(1)(b) of the Electricity Act, 2003 for the approval of �Change in Law� and consequent revision in capital cost due to introduction of the Central Goods and Services Tax Act, 2017 promulgated by the Department of Revenue, Ministry of Finance notified by way of notification dated 28.06.2017.
Reply / additional information as per ROP to filed by Petitioner,Respondent
188
21/RP/2018 in 110/MP/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94 OF THE ELECTRICITY ACT, 2003 READ WITH REGULATIONS 103, 111 AND 114 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 READ WITH ORDER 47, RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 FOR REVIEW OF ORDER DATED 3.4.2018 READ WITH CORRIGENDUM DATED 26.4.2018 PASSED BY THIS HON'BLE COMMISSION IN PETITION NO.110/MP/2018.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
189
177/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of Transmission Tariff for Asset-I: 132kV D/C Silchar-Hailakandi (AEGCL) Transmission line (Balance portion beyond LILO point) alongwith associated bays at Hailakandi (AEGCL) Substation from DOCO to 31.03.2019 under �Transmission system associated with Pallatana GBPP and Bongaigaon TPS�.
Hearing
190
175/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations 2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for 08 nos Transmission assets under �North Eastern Region Strengthening Scheme-VII (NERSS-VII)� for 2014-19 Tariff Block Period in North-Eastern Region.
Tariff order u/r 7(7) of 2014 Tariff Regulation
191
174/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for assets under Conversion of Fixed Line Reactors to Switchable Line Reactors in Southern Region.
Hearing
192
173/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
PETITION FOR APPROVAL OF TRANSMISSION TARIFF For
Asset I - STATCOM  System (+/-) 300MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor), cooling system & STATCOM protection / controller  etc at Rourkela Substation (Anticipated DOCO: 01.04.2018) & Asset II - STATCOM  System (+/-) 200MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor and 2x125 MVAR Capacitor), cooling system & STATCOM protection / controller  etc at Jeypore Substation (Anticipated DOCO: 01.05.2018) under ?Eastern Region Strengthening Scheme ?XI (ERSS-XI)  ?
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
193
172/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I:  Combined Assets of (1) 400 kV D/C Ajmer (New)- Ajmer (RVPN) TL along with associated bays at both ends ; (2) 400 kV, 125 MVAR Bus Rector along with associated bay at Ajmer (New) Substation; (3) 765/400 kV, 3X500 MVA ICT-I along with associated bays at Ajmer (New) Substation; (4) 400 kV D/C Chittorgarh (New)- Chittorgarh (RVPN) TL along with associated bays at both ends ; (5) 765 kV, 240 MVAR Bus Reactor along with associated bay at Chittorgarh (New) Substation ;(6) 400 kV, 125 MVAR Bus Reactor along with associated bay at Chittorgarh (New) Substation;(7) 765/400 kV, 3X500 MVA ICT-I along with associated bays at Chittorgarh (New) Substation; (8) 765/400 kV, 3X500 MVA ICT-II along with associated bays at Chittorgarh (New); Asset-II: Combined Assets of (1) 765 kV, 240 MVAR Bus Rector along with associated bay at Ajmer (New) Substation; (2) 765/400 kV, 3X500 MVA ICT-II along with associated bays at Ajmer (New) Substation ;Asset-III: 2 X 400 kV D/C(Quad)Tirunelveli Pooling Stataion -Tuticorin Pooling station line  along with new 400/230KV (GIS) Tirunelveli Pooling substation with 2X 125MVAR 400KV Bus reactors & associated bays at 400/230KV Tuticorin Pooling station  ; Asset-IV: 2X500MVA 400/230KV transformers along with associated bays & equipments at new 400/230KV (GIS) Tirunelveli Pooling substation, under Transmission System Associated with "Green Energy Corridors: Inter State Transmission Scheme (ISTS)- Part A� in Northern Region & Southern Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
194
171/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset: Replacement of 01 No. of 1x315 MVA, 400/220 kV ICT with 1x500 MVA, 400/220 kV ICT (2nd) at 400 kV Maithon S/S under Transmission System for �Eastern Region System Strengthening Scheme-IX� in Eastern Region.
Hearing
195
170/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Filing of petition for determination of transmission tariff for NLC- KaraiKal 230 kV  D/c line (through LILO of the 230kV Neyveli- Bahour S/c line at Karaikal) under NLC- Karaikal 230kV D/c line in Southern Region
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
196
169/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Truing up of fees and charges for assets under Fibre Optic Communication System in Lieu of existing Unified Load Despatch & Communication (ULDC) Microwave Links in Southern Region
Order reserved
197
168/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for assets under Fiber Optic Communication system for central sector Sub-stations & Generating Stations� in Southern Region.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
198
167/MP/2018
SEMBCORP GAYATRI POWER LIMITED (SGPL)
Petition under Section 79(1)(C) of the Electricity Act, 2003 seeking permission of the Hon'ble Central Electricity Regulatory Commission to transfer and / or assign the rights and obligations of Sembcorp Gayatri Power Limited under the Transmission Service Agreement dated 11.06.2014 to Sembcorp Energy India Limited, as stipulated under the scheme of amalgamation.
Hearing
199
166/MP/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under section 79(1)(f) read with section 79 (1) (c) of the Electricity Act, 2003
Hearing
200
165/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 02.08.2016, executed between the Parampujya Solar Energy Pvt. Ltd. (PSEPL) and Solar Energy Corporation of India Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
201
164/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 27.07.2016, executed between Parampujya Solar Energy Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
202
163/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations‟1999 and CERC (Terms and Conditions of Tariff) Regulations ‟2014 for determination of Transmission Tariff from actual DOCO to 31/03/2019 For Asset: Modification of 132 kV bus arrangement including switchgear to Double main (DM) scheme with GIS at 220/132 kV Birpara Substation under Eastern Region Strengthening Scheme XIV in Eastern Region.
Tariff order u/r 7(7) of 2014 Tariff Regulation
page separator
S. No.
Petition No.
Petitioner
Subject
Status
203
162/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset: 02 Nos 400kV line bays at Ranchi 400kV Sub-station for Raghunathpur TPS � Ranchi 400kV D/C transmission line under Common Scheme for 765 kV Pooling Stations and Network for NR, Import by NR from ER and from NER/SR/WR via ER and Common scheme for network for WR and Import by WR from ER and from NER/SR/WR via ER in Eastern Region.
Additional information as per Interim Order to be filed by Petitioner,Respondent
204
20/RP/2018 in 13/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94 OF THE ELECTRICITY ACT, 2003 READ WITH REGULATIONS 103, 111 AND 114 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 READ WITH ORDER 47, RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 FOR REVIEW OF ORDER DATED 22.2.2018 PASSED BY THIS HON'BLE COMMISSION IN PETITION NO.13/TT/2017.
Additional information as per Interim Order to be filed by Petitioner,Respondent
205
19/RP/2018 in 62/MP/2017
POWERGRID NM Transmission Limited (PNMTL)
Review of this Hon�ble Commission�s Order dated 26.03.2018 in Petition No. 62/MP/2017 filed by POWERGRID NM Transmission Limited (erstwhile Nagapattinam-Madhugiri Transmission Company Limited).
Reply / additional information as per ROP to filed by Petitioner,Respondent
206
18/RP/2018 in 168/MP/2017
WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (WBSETCL)
PETITION FOR REVIEW UNDER SECTION 94 (1) (f) OF THE ELECTRICITY ACT, 2003 R/W ORDER 47 RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 AND REGULATION 103 (1) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999, SEEKING REVIEW OF ORDER DATED 29.01.2018 PASSED IN PETITION NO. 168/MP/2017
Order reserved
207
161/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1:  1 no. 400 kV Line bay (at POWERGRID, Sikar end) along with 50 MVAR Non- Switchable line reactor for Ckt-I of 400 kV D/C Bikaner (RVPNL)- Sikar (PG) line and  Asset 2: 1 no. 400 kV Line bay (at POWERGRID, Sikar end) along with 50 MVAR Non- Switchable line reactor for Ckt-II of 400 kV D/C Bikaner (RVPNL)- Sikar (PG) line under ? Line bays associated with various Regional Strengthening Schemes in NR? Scheme.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
208
160/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: Replacement of 1X100MVA, 220/132kV ICT-II by 1X200MVA, 220/132kV ICT-II at Raebareli S/s (DOCO: 19.02.2018), Asset-II: Replacement of 1X100MVA, 220/132kV ICT-III by 1X200MVA, 220/132kV ICT-III at Raebareli S/s (DOCO: 01.12.2017) under �Augmentation of Transformation Capacity at Raebareli & Sitarganj 220/132kV Substations�
Order reserved
209
159/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 125 MVAR Bus Reactor at 400/220 kV Manesar Substation Extension under ?Bus Reactor Scheme in Northern Region, Phase-II?.
Order reserved
210
158/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from Anticipated/ Actual DOCO to 31.03.2019 For Asset 1: 400/220kV, 3 X 105 MVA ICT alongwith associated bays at Hamirpur Substation, Asset  2:  220kV, 2Nos Line Bays at Hamirpur Substation. Asset   3:  220kV, 2Nos Line bays at Jallandhar Substation, Asset 4: 1 X 500 MVA, 400/220 kV ICT-IV  at GIS Gurgaon Substation Under �Augmentation of Transformers in Northern Region�Part B� in Northern Region
Hearing
211
157/MP/2018
Prayatna Developers Private Limited (PDPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 18.05.2016 executed between Prayatna Developers Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Reply / additional information as per ROP to filed by Petitioner,Respondent
212
156/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
Petition invoking Section 79(1)(b) and (f) of the Electricity Act, 2003 seeking compensation/ relief for increased expenses due to certain events of Change in Law as per the applicable provisions of the PPAs dated 18.01.2014 and 20.01.2014.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
213
155/MP/2018
BSES YAMUNA POWER Ltd. (BYPL)
Petition under Section 79 (1) (a) & (f) and other applicable provisions of the Electricity Act, 2003 read with Regulation 110 & 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner and Respondent NTPC Ltd. regarding excess recovery of Annual Fixed Costs for various generating stations of the Respondent during FY 2014-19
Hearing
214
154/MP/2018
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Miscellaneous Petition u/s 79 to adjudicate dispute between Petitioner and Respondent in accordance to BPT agreement dated 21.11.2011
Hearing
215
153/MP/2018
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Miscellaneous petition u/s 79 to adjudicate dispute between the petitioner and the respondent as per bulk agreement dated 06.09.2011
Hearing
216
152/MP/2018
BSES Rajdhani Power Limited (BRPL)
Petition under Section 79 (1) (a) & (f) and other applicable provisions of the Electricity Act, 2003 read with Regulation 110 & 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner and Respondent NTPC Ltd. regarding excess recovery of Annual Fixed Costs for various generating stations of the Respondent during FY 2014-19
Hearing
217
151/MP/2018
Shree Cement Limited (SCL)
Down gradation of Trading License from Category-I to Category-II
Order Reserved- Additional information for final order to be filed by Petitioner
218
150/TT/2018
DAMODAR VALLEY CORPORATION (DVC)
Petition for determination of tariff for Transmission & distribution System Activities of DVC Network for the period from 01.04.2014 to 31.03.2019
Reply / additional information as per ROP to filed by Petitioner,Respondent
219
149/GT/2018
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter �V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of tariff of PARE Hydro Electric Power Plant (PHEP) (2 X 55 = 110 MW) for the period from COD to 31.03.2019;
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
220
147/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Aurangabad(POWERGRID) -Padghe (POWERGRID) 765kV D/C line & Padghe (POWERGRID)-Padghe/kudus (MSETCL) 400kV D/C (QUAD) line along with associated bays and Establishment of 765/400 kV 2x1500MVA Padghe GIS SS under System Strengthening in North/West Part of Western Region for IPP Projects in Chhattisgarh (IPP-E).
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
221
145/TT/2018
Essar Power Transmission Company Limited (EPTCL)
Approval under Regulation of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of transmission tariff from the anticipated DOCO to 31.03.2019 for 400 kV D/C Mahan-Sipat and 2x50 MV AR line reactors at Mahan Pooling Substatyion and 1x80 MVAR, 420 kV switchable bus reactor at Mahan TPS along with its associated 400 kV bay
Tariff order u/r 7(7) of 2014 Tariff Regulation
222
144/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2014-15 in respect of  Rangit Power Station.
Hearing
223
143/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Sewa-II Power Station.
Hearing
224
142/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Parbati-III Power Station.
Hearing
225
141/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Chamera-III Power Station.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
226
140/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2015-16 in respect of  Chamera-III Power Station.
Hearing
227
139/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2015-16 in respect of  Dhauliganga Power Station.
Hearing
228
138/MP/2018
DCM SHRIRAM LIMITED (DCMSHRIRAM)
PETITION UNDER SECTION 79 OF THE ELECTRICITY ACT 2003 READ WITH REGUALTION 14 & 15 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010 CHALLENGING THE ILLEGAL AND ARBITRARY REJECTION OF GRANT OF REC APPLICATION OF THE PETITIONER BY THE RESPONDENT.
Hearing
229
137/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31/03/2019 for Asset-I: 1X160 MVA ICT-I alongwith associated bays at Daltonganj Sub-station, 1X160 MVA ICT-II alongwith associated bays at Daltonganj Sub-station and 2X132kV Line bays at Daltonganj Sub-station Asset-II: 02 Nos of 132 kV line bays at Daltonganj Sub-station under ERSS XVII Part A in Eastern Region.
Order reserved
230
17/RP/2018 in 89/MP/2016
BSES YAMUNA POWER Ltd. (BYPL)
Review of the Order dated 02.11.2017 passed by this Hon?ble Commission in Petition No. 89/MP/2016 titled as ?BSES Rajdhani Power Limited & Anr. v. Pragati Power Corporation Limited & Anr.?.
Order reserved
231
135/MP/2018
KUDGI TRANSMISSION LIMITED (KTL)
Petition seeking payment of transmission tariff between the date of commissioning and date of charging of Element 2 and Element 3 of transmission assets of Kudgi Transmission Limited
Hearing
232
133/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Implementation of Regulation 30 (6) of the Central Electricity Regulatory Commission (Terms & Conditions of Tariff) Regulations, 2014.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
233
132/MP/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under section 19(1)(c) of the Electricity Act, 2003 for declaration of LILO of 400 kV S/c Vindhyachal-Korba Transmission line of the Petitioner at Mahan.
Hearing
234
131/MP/2018
Sasan Power Limited (SPL)
Petition under Section 79 of the Electricity Act, 2003 read with the statutory framework governing procurement of power through competitive bidding and Power Purchase Agreement dated 07.08.2007 for (i) revision in tariff in exercise of the general regulatory powers; and (ii) compensation on account of increased cost incurred by Sasan Power Limited consequent to Procurer Event of Default.
Reply / additional information as per ROP to filed by Petitioner,Respondent
235
130/MP/2018
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Regulation 3(13) of CERC (Terms and Conditions of Tariff) Regulation 2014 , Regulation 111 and 115 of  the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 3(13) of the Tariff Regulations?2014 for eExtention of cut off date  of Vindhyachal Super Thermal Power Station, Stage-V (1X500MW) from  31.03.2018 to  31.03.2019.
Hearing
236
129/MP/2018
SHALIMAR VISUALS PRIVATE LIMITED (SVPL)
PETITION UNDER SECTIONS 66, 79 AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 READ WITH THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010.
Reply / additional information as per ROP to filed by Petitioner,Respondent
237
128/MP/2018
North East Transmission Company Ltd. (NETC)
PETITION UNDER SECTION 79 (1) (d) READ WITH SECTIONS 62 AND 64 OF THE ELECTRICITY ACT, 2003 AND REGULATIONS 29 (A) AND 54 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014 AND REGULATION 111 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 FOR REVISION AND ADJUSTMENT OF THE TRANSMISSION CHARGES DETERMINED BY THE HON?BLE COMMISSION VIDE ORDER DATED 16.8.2016 IN PETITION NO. 213/TT/2015
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
238
16/RP/2018 in 152/GT/2015
Maithon Power Limited (MPL)
Review Petition under Regulation 103 (1) of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 read with Section 94 (1)(f) of the Electricity Act, 2003 seeking review of the Order dated 26th December 2017 (?Impugned Order?) passed by this Hon?ble Commission in Petition No. 152/GT/2015 filed by MPL.
Order reserved
239
127/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset -I: Combined Asset of 400kV D/C Orai-Orai (UPPTCL) line and associated bays at both ends ; 1000MVA, 765/400kV ICT-I along with associated bays at Orai(GIS) Sub-station ; 330MVAR, 765kV Bus Reactor-I along with bay at Orai Sub-station; Asset -II: 330MVAR, 765kV Bus Reactor-II along with bay at Orai Sub-station ;Asset -III: 1000MVA, 765/400kV ICT-II along with associated bays at Orai(GIS) Sub-station; Asset -IV: 765kV D/C Orai-Aligarh Line with associated bays including 240MVAR Line Reactor in both Ckt at both end; Asset -V: Combined Asset of LILO of 765kV S/C Kanpur-Jhatikara Line at Aligarh with associated bays; 330MVAR, 765kV Bus Reactor-I along with bay at Aligarh Sub-station; 330MVAR Switchable L/R in 765kV S/C Kanpur-Aligarh Line at Aligarh; Asset -VI: Combined Asset of 330MVAR, 765kV Bus Reactor-II along with bay at Aligarh Sub-station; LILO of 765kV S/C Agra-Meerut Line at Aligarh with associated bays; Asset -VII: Bay extension at Jhatikara end   to convert line reactor of 765 kV S/C Kanpur-Jhatikara TL into switchable line reactor ; Asset -VIII: Conversion of existing line reactor at Gwalior end of Satna-Gwalior Ckt-1 TL (to be LILO at Orai) in to switchable line reactor  ; Asset -IX: 765 KV D/c Jabalpur Pooling station - Orai TL along with 2*330 MVAR Line Reactor along with Bay Extension at 765/400 kV Jabalpur Pooling Station & 02 nos 765 Jabalpur Line bays along with 2*330 MVAR line reactor at Orai S/s;Asset -X: LILO of one circuit of 765 KV Satna-Gwalior TL along with 765 kV Satna Line Bay at Orai Sub Station & 240 MVAR Line Reactor at Orai S/s and 765 kV Gwalior bay at Orai S/s under �Inter-Regional System Strengthening Scheme in WR & NR (Part-B)� in Northern Region & Western Region.
Interim order under preparation
page separator
S. No.
Petition No.
Petitioner
Subject
Status
240
126/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

for 3x110 MVAR Line reactor for 765kV D/C Raipur PS -  Wardha Line 1 Ckt#2 to be charged as Bus reactor at Wardha SS under Integration of Pooling stations in Chhattisgarh with central part of WR for IPP generation projects in Chhattisgarh (IPP C).
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
241
125/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Determination of Tariff for  Asset ? I 400kV DC Allahabad ? Kanpur Line along with associated bays at both ends including 2X50 MVAR Line Reactor at Kanpur end
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
242
124/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 220kV Kishanganga-Amargarh D/C line on M/C tower under ?Transmission system associated with Kishenganga HEP?
Order reserved
243
123/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
 
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
For the assets of �Transmission System associated with Sasan Ultra Mega Power Project(UMPP)�
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
244
121/MP/2018
MY HOME POWER PRIVATE LIMITED (MHPPL)
Down Grading of inter state trading licence from Category II to CategoryIII
Order reserved
245
118/MP/2018
TRN ENERGY PRIVATE LIMITED
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation on account of events pertaining to change in law as per the terms of Power Purchase Agreement dated 25.07.2013 (PTC-PPA) executed between the Petitioner and the Respondent No. 6 and as per the terms of the back to back Power Purchase Agreement executed by PTC with Paschimanchal Vidyut Vitran Nigam Ltd (�PaVVNL�), Purvanchal Vidyut Vitran Nigam Ltd (�PuVVNL�), Madhyanchal Vidyut Vitran Nigam Ltd (�MVVNL�), Dakshinanchal Vidyut Vitran Nigam Ltd (�DVVNL�) [hereinafter referred to as the �Procurer(s) PPA�] dated 25.07.2013.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
246
116/MP/2018
Maruti Clean Coal and Power Limited (MCCPL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation on account of events pertaining to change in law events.
Reply / additional information as per ROP to filed by Petitioner,Respondent
247
115/MP/2018
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Section 79 (1) (a) & (f) and other applicable provisions of the Electricity Act, 2003 read with Regulation 110 & 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner and Respondent NTPC Ltd. regarding excess recovery of Annual Fixed Costs for various generating stations of the Respondent during FY 2014-19
Hearing
248
114/MP/2018
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Sections 79(1)(b), 79(1)(c) and 79(1)(f) of the Electricity Act, 2003, read with the relevant provisions of the IEGC, 2010 for the implementation of the order of this Hon?ble Commission in Proceeding No. L-1/219/2017/CERC dated 05.05.2017 and for seeking issuance of consequential directions to the Respondents for complying with the detailed operating procedure qua reserve shut down of the Unit(s) of the 2 x 660 MW Mahatma Gandhi Thermal Power Plant at Matenhali, Dist. Jhajjhar, Haryana.
Reply / additional information as per ROP to filed by Petitioner,Respondent
249
111/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: ?300 MVAR STATCOM at 400kV Aurangabad substation, Asset 2: ?200 MVAR STATCOM at 400kV Gwalior Substation, Asset 3: ?300 MVAR STATCOM at 400kV Satna substation and Asset 4: ?300 MVAR STATCOM at 400kV Solapur substation under ?Installation of  STATCOMs in Western Region?.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
250
110/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset ASSET-1: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Arasur Substation,  ASSET-2: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Karaikudi Substation, ASSET-3: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Tirunelveli Substation, ASSET-4: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Pondicherry Substation, ASSET -5: 1X500 MVA 400/220kV ICT along with bays and equipment at Kozhikode Substation under �Augmentation of transformation capacity in Southern Region�.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
251
109/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of True up 2009-14 and tariff2014-19 of Two nos. of 63 MVAR 400 kV Line Reactor at 400kV Balia (PG) Sub-Station (Extension) (actual DOCO : 1.2.2014), under Northern region system strengthening scheme-XXIV in Northern region
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
252
108/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
For Transmission System Associated with NRSS-XIII in Northern Region consisting of Asset-I:400 kV D/C (Quad) Gurgaon-Manesar Transmission Line along with associated bays (DOCO 01.09.2012),Asset-II : 400/220 kV 500 MVA ICT-I at Manesar S/S along with associated bays (DOCO 01.06.2012),Asset-III: 400/220 kV 500 MVA ICT-II at Manesar S/S along with associated bays (DOCO 01.08.2012) and Asset-IV:125 MVAR Bus Reactor at Manesar (DOCO 01.10.2012).
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
253
107/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for communication system for DVC under Expansion/ Up gradation of SCADA/ EMS System of SLDCs of Eastern Region (BSPTCL & DVC).
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
254
106/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for Asset: 400kV D/C (Quad) Nabinagar-II � Gaya transmission line with 02 nos associated bays at Gaya Sub-station associated with Transmission System for Nabinagar-II TPS under Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
255
105/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
IN THE MATTER OF: Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated/actual DOCOs to 31.03.2019 for Asset I: Combined asset of (a) 400 KV D/C Sasaram - Daltonganj Transmission Line alongwith 2 x 50 MVAR Line Reactors   at  Daltonganj  Sub-station; (b) 400 /220 KV, 315 MVA ICT -I  alongwith bays at Daltonganj Sub-station; (c) 400 KV 80 MVAR BR at Daltonganj Sub-station; & (d) 400 /220 KV, 315 MVA ICT -II  alongwith bays at Daltonganj Sub-station; Asset II: 04 Nos 220 KV Bays at Daltonganj Sub-station; Asset III: Provision of Circuit Breakers for making line reactors at Biharshariff Sub-station switchable; Asset IV: 01 no. 80 mVAR Bus Reactor At Duburi Sub station; Asset V: LILO of 2nd Ckt. Of 400kV D/C Jamshedpur-Rourkela TL at Chaibasa S/s (non-bussed at Chaibasa); and Asset VI: 01 No. 500MVA, 3 phase 400/220kV, Transformer (2nd) and associated bays at Pandiabilli GIS under Eastern Region Strengthening Scheme-III (ERSS-III) in Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
256
102/TT/2018
Essar Power Transmission Company Limited (EPTCL)
Application for determination of transmission tariff (annual fixed cost) for the 2   400 kV Bays at Jhanor Gandhar GPS of NTPC Ltd which form part of the inter-state transmission system of EPTCL
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
257
101/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of CERC (Terms and Conditions of Tariff) Regulations, 2009 and CERC (Terms and Conditions of Tariff) Regulations� 2014 for determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

  For the assets of �Transmission System associated with Krishnapatnam UMPP - PART B

a. covered in CERC order dated 24.11.2015 in petition no. 299/TT/2013
b. covered in CERC order dated 29.02.2016 in petition no. 96/TT/2014
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
258
15/RP/2018 in 98/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review petition under Section 94 (1) (f) of the Electrcity Act, 2003
Reply / additional information as per ROP to filed by Petitioner,Respondent
259
100/MP/2018
Megha Engineering & Infrastructures Ltd (MEIL)
Petition filed under Section 79(1)(f) read with Section 79(1)(k) of the Electricity Act, 2003 along with Regulation 68 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking indulgence of the Hon?ble Central Electricity Regulatory Commission to direct NTPC Vidyut Vyapar Nigam Limited to comply with the Order dated 11.10.2017 in Petition No. 16/MP/2014 by computing the delay suffered by the Generation Project due to force majeure eventualities and revise the Schedule Commercial Operation Date for the Generation Project.
Hearing
260
99/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations?  2014 for  determination of  (i) Truing up Transmission tariff for 2009-14 tariff  block and (ii) Transmission tariff for 2014-19  tariff block For (a) Kalpakkam PFBR-Sirucheri 230 kV D/C Line (b) Kalpakkam PFBR-Arani 230 kV D/C Line under Transmission System associated with Kalpakkam PFBR (500 MW) in Southern Region.
Order reserved
261
98/MP/2018
ONGC Tripura Power Company (OTPC)
Request for Extension of Cut-off Date for Project due to delay in civil works of plant township
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
262
96/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
Petition under Section 79 (1) (c), Section 79 (1) (f) and Section 79 (1) (k) of the Electricity Act, 2003 read with the Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium term Open Access in inter-state transmission and related matters) Regulations, 2009 along with Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking directions against Power Grid Corporation of India Limited for (i) payment of amounts due to the Petitioner in compliance of the Order dated 15.12.2017 of this Hon�ble Commission in Petition No. 141/TT/2015; and (ii) return of Bank Guarantee of INR 60 Crores furnished as per the extant regulations r/w the Transmission Agreement dated 14.06.2010 and Long Term Access Agreement dated 17.06.2011.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
263
92/MP/2018
Shiga Energy Private Limited (SEPL)
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter-alia, seeking a direction to Respondent No. 1 to pay a sum of Rs. 112.39 crores, being the financial loss suffered by the Petitioner, on account of delay in commencement of the Long Term Access granted to the Petitioner, due to delay in implementation of the Transmission system falling in the scope of Respondent No. 1?s obligations, along with interest on the same till the date of payment of the amount by Respondent No. 1 to the Petitioner.
Reply / additional information as per ROP to filed by Petitioner,Respondent
264
91/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79(1)(b) read with Section 79(1)(f) and other applicable provisions of the Electricity Act, 2003 seeking adjudication of disputes and differences under the Power Purchase Agreement dated 31.07.2012 as amended on 19.12.2014 and 23.01.2018 in regard to non-payment of tariff and unilateral deduction of the monthly energy bills of the Petitioner by the Respondents
Hearing
265
90/MP/2018
RAPP Transmission Company Limited (RTCL)
Petition under Section 142 and Section 146 of the Electricity Act, 2003 against Nuclear Power Corporation of India Limited?s willful, deliberate, contumacious and continuous non-compliance of this Hon?ble Commission?s Order in Petition No. 43/MP/2016 dated 21.09.2016
Hearing
266
89/MP/2018
ARAVALI POWER COMPANY PRIVATE LIMITED (APCPL)
Petition for revision of the Normative Annual Plant Availability Factor
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
267
87/MP/2018
M.R. Industries (MRIndustries)
ACCESS IN INTER-STATE TRANSMISSION) REGULATIONS, 2008, FURTHER READ WITH REGULATION 4 OF THE RERC (INTRA-STATE ABT) REGULATIONS, 2006AND REGULATION 4.2 OF THE STATE GRID CODE SEEKING DIRECTIONS FOR PREPARATION OF UI ACCOUNT FOR UNDER-DRAWAL AGAINST COLLECTIVE TRANSACTIONS WITHIN SPECIFIED TIME AND FOR PAYMENT OF UI CHARGES
Hearing
268
78/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Unilateral Surrender of 400 MW Power by MPPMCL from MTPS & CTPS of DVC in violation of provision of PPA
Hearing
269
77/MP/2018
TRN ENERGY PRIVATE LIMITED
Petition under Section 79 (1) (b) read with Section 79(1) (f) of the Electricity Act, 2003
seeking directions for applicability of the provisions of PTC-PPA signed between
Petitioner & the Respondent No.6 and Procurer�s PPA signed between Respondent
No.6 & Respondent No. 1 to 5, both dated 25.07.2013 for the purposes of calculation of
Penalties due to less than 80% availability for a Contract Year.
ROP Issued
270
76/MP/2018
BHILANGAHA HYDRO POWER LIMITED (BHPL)
PETITION UNDER REGULATION 14,5 (3) & (4) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010.
Hearing
271
75/MP/2018
OLAM AGRO INDIA PVT. LTD.
Petition seeking directions against National Load Dispatch Centre in the matter of issuance of Renewable Energy Certificates to the Petitioner for the specified period
Reply / additional information as per ROP to filed by Petitioner,Respondent
272
73/MP/2018
Sneha Kinetic Power Projects Pvt. Ltd (SKPPPL)
Petition under Section 79 (1) (f) and (c) and other applicable provisions of the Electricity Act, 2003 read with Regulation 12 of Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014, against the arbitrary acts and omissions of Teestavalley Power Transmission Limited.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
273
72/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding ("Competitive Bidding Guidelines") and (a) Article 10 of the PPA dated 09.11.2011 between GMR Kamalanga Energy Ltd. and Bihar State Electricity Board and (b) Article 13 of the PPA dated 12.03.2009 between GMR Energy Ltd. (on behalf of GMR Kamalanga Energy Limited) and PTC India Ltd. with back to back PPA between PTC India Ltd. and Haryana Distribution companies, for compensation due to Change in Law
Reply / additional information as per ROP to filed by Petitioner,Respondent
274
71/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding ("Competitive Bidding Guidelines") and (a) Article 10 of the PPA dated 17.03.2010 between Maharashtra State Electricity Distribution Company Ltd. and EMCO Energy Limited; (b) Article 10 of the PPA dated 21.03.2013 between Electricity Department of Union Territory of Dadra and Nagar Haveli and EMCO Energy Limited and (c) Article 10 of the PPA dated 27.11.2013 between GMR Energy Trading Limited and the Tamil Nadu Generation and Distribution Corporation Limited through EMCO Energy Limited.
Reply / additional information as per ROP to filed by Petitioner,Respondent
275
70/MP/2018
Godavari Biorefineries Limited (GBL)
Petition is filed praying for a direction from this Hon'ble Commission to the Respondent to refund the Back Up Supply Charges collected from the Petitioner, during the course of grant of Inter State Open Access to the Petitioner, ny contravening and violating Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008.
Hearing
276
68/MP/2018
NTPC Tamil Nadu Energy Company Limited (NTECL)
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and with Regulations 36 & 54 of CERC (Terms and Condition of Tariff) Regulation, 2014 for Revision  of NAPAF for Vallur Thermal Power Station (3X500MW) for the period from 01.04.2017 to 31.03.2019.
Hearing
277
67/MP/2018
NTPC Tamil Nadu Energy Company Limited (NTECL)
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and with Regulation 54 of CERC (Terms and Condition of Tariff) Regulation, 2014 for Relaxation of cut off date of Vallur Thermal Power Station (3X500MW)
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
278
13/RP/2018 in 187/MP.2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) regulations, 1999 for review of the Order dated 11.10.2017 passed by the Hon?ble Commission in Petition No. 187 / MP / 2015
Hearing
279
63/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset: 02 nos of 400 kV bays at Purulia S/S under Eastern Region Strengthening Scheme VII (ERSS VII) in Eastern Region.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
280
62/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 400 kV D/C Kishenpur- New Wanpoh Line alongwith associated bays at both ends under ?Northern Region System Strengthening Scheme XVI? in Northern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
281
61/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of    Transmission Tariff from DOCO to 31.03.2019 Asset-I: 2 nos. 400 kV Malerkotla Bays at 400/220 kV GIS Substation at Kurukshetra under ?Provision of 400kV bays for lines under Northern Region System Strengthening Scheme-XXXI(Part-B)?.
Hearing
282
59/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset-I: LILO of both Circuit of 400 kV D/C Rourkela-Raigrah (02nd Line) alongwith 04 Nos of 400 kV Line bays at Jharsuguda (Sundargarh) Substation; Asset-II: Split Bus arrangement at 400 kV Bus at Jharsuguda  (Sundargarh) Substation and Asset-III: 02 Nos of 400 kV Line bays for termination of OPGC (IB TPS) - Jharsuguda 400 kV D/C line (Under TBCB) at Jharsuguda (Sundargarh) under work associated with common transmission system for Phase-II Generation project in Odisha under Eastern Region.
Hearing
283
54/MP/2018
Neyveli Lignite Corporation Ltd (NLC)
NLCIL- BTPS (Barsingsar Thermal Power station)� Non Implementation of ABT from COD - Consequential short admittance of bills by Rajasthan Discoms despite NLCIL efforts for resolution�Miscellaneous Petition for adjudication   -  submitted - Reg.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
284
53/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 06 Nos of Link under central sector (562.873) Asset-II: 07 Nos of OPGW links (664.53 Km) and Asset-III: 07 Nos links under Central Sector (1076.57 km) under central sector under the project Fibre Optic communication system in ER under Expansion of wide-band communication network in Eastern Region.
Order reserved
285
49/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I: 400kV Transmission Line for Swapping of Kahalgaon # 1 bay with Sasaram # 1 bay at Biharsharif Sub-station; Asset II: 400KV Transmission Line for Swapping of Purnea(1&2) Bays with Sasaram bays(3&4) at Biharsharif Sub-station and Asset III: Split Bus arrangement with tie line Breaker for 400KV Biharsharif Sub-station under Split Bus arrangement for various substations in Eastern Region.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
286
11/RP/2018 in 88/TT/2017
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED (MPPTCL)
Petition for review the Order dated 19.12.2017 passed by the Hon�ble Commission in Petition No 88/TT/2017
Order reserved
287
10/RP/2018 in 039/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for Review of Order dated 12.12.2017 passed in Petition No. 39/TT/2015 under Section 94 of the Electricity Act, 2003
Order reserved
288
46/MP/2018
NTPC Limited
Petition for revision of  the Normative Annual Plant Availability Factor in respect of NTPC?s Power Stations on account of shortage of coal availability.
Hearing
289
43/GT/2018
NHPC LTD
Petition under Regulation 79(1) & 86 of CERC (Conduct of Business) Regulations, 1999, Section 62(1) (a) of the Electricity Act, 2003 and Regulation- 6 (1) (ii), 7(1) & 14(1) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for approval of generation tariff of Kishanganga HE Project (330 MW) for the period 31.01.2018 (Anticipated COD of Unit#1&2) to 31.03.2019.
Additional information as per Interim Order to be filed by Petitioner,Respondent
290
36/MP/2018
RANA SUGARS LIMITED RSL
Issuance of Pending RECs and Re-accreditation of project under the REC mechansim
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
291
35/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition under Section 79 (1) (f) read with CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 seeking refund of the POC charges for 260 MW in Eastern Region granted under the Bulk Power Transmission Agreement dated 01.07.2016.
Hearing
292
29/MP/2018
INOX WIND INFRASTRUCTURE SERVICES LIMITED (IWISL)
Seeking Facilitation and long term open access to the SPV incorporated by the Petitioner to implement the wind power projects awarded to it under the scheme of Government of India (Ministry of New and Renewable Energy) dated 28.10.2016 for setting up of 1000 MW ISTS Connected Wind Power Projects.
Hearing
293
27/MP/2018
Krishna Windfarms Developers Private Limited (KWFDPL)
Petition under Section 79 (1) (f) read with Section 79 (1) (b) of the Electricity Act, 2003 in relation to the disputes arising out of the Power Purchase Agreement dated 03.08.2016 between Petitioner herein i.e. Krishna Windfarms Developers Private Limited and Solar Energy Corporation of India Limited.
Hearing
294
24/TT/2018
Karnataka Power Transmission Corporation Limited KPTCL
Approval under Regulation 86 of CERC (Conduct of business) Regulation, 1999 for determination of Tariff for Transmission Lines connecting between Karnataka and other neighboring states
Hearing
295
23/MP/2018
nrssxxix transmission company limited (NRSSXXIX)
Petition under Section 79(1)(c), Section 18 and Section 17(3) of the Electricity Act, 2003 and invoking all other enabling powers of the Hon?ble Central Electricity Regulatory Commission permitting the amendment of the Transmission License dated 14.11.2014 granted to the NRSS XXIX Transmission Limited for establishing Transmission System for Northern Region System Strengthening Scheme NRSS-XXIX on Build, Own, Operate and Maintain basis and accordingly allowing carving out of Jalandhar ? Samba transmission line from the purview of the aforesaid Transmission License and to vest the same into the favour of a separate entity i.e. NRSS XXIX (JS) Transmission Limited.
Hearing
296
22/MP/2018
Mirra and Mirra Industries (MMI)
PETITION UNDER SECTIONS 66, 79 AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 READ WITH THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
297
5/RP/2018 in 70/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the order dated 21.11.2017
passed by this Hon'ble Commission in Petition No. 70/TT/2017.
Order reserved
298
19/MP/2018
TALETTUTAYI SOLAR PROJECTS FOUR PVT. LTD TT4
MEMORANDUM OF ORIGINAL PETITION FILED UNDER SECTION 79 (1) (f) OF THE ELECTRICITY ACT, 2003 (�THE ACT�) AND THE OTHER APPLICABLE PROVISIONS OF THE ACT IN RELATION TO THE DISPUTES HAVING ARISEN UNDER THE POWER PURCHASE AGREEMENT DATED APRIL 11, 2016 BETWEEN THE PARTIES
Hearing
299
4/RP/2018 in MP/419/2014
RAICHUR SHOLAPUR TRANSMISSION COMPANY PRIVATE LIMITED (RSTCPL)
REVISION PETITION ON BEHALF OF RAICHUR SHOLAPUR TRANSMISSION COMPANY LIMITED FOR REVIEW OF THE ORDER DATED 27.06.2016 PASSED BY THE CENTRAL ELECTRICITY REGULATORY COMMISSION IN PETITION NO.419/MP/2014 UNDER REGULATION 103(1) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 PURSUANT TO THE ORDER DATED 01.12.2017 PASSED BY THE HON�BLE APPELLATE TRIBUNAL FOR ELECTRICITY IN APPEAL NO.193/ 2016.
Hearing
300
18/MP/2018
Adani Green Energy Limited (AGEL)
Petition under Section 79 (1) (c) and (f) and other applicable provision of the Electricity Act, 2003 read with Regulation 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in the inter-State transmission and related matters) Regulations, 2009 against the action of the respondent in threatening to cancel the open access and encashment of bank guarantee.
Hearing
301
17/MP/2018
NTPC Vidyut Vyapar Nigam Limited (NVVN)
PETITION UNDER SECTION 79 (1) (f) READ WITH SECTION 79 (1) (a) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES BETWEEN THE PETITIONER AND THE RESPONDENTS 1 TO 3
Hearing
302
1/SM/2018
Suo Motu
Addional tax burden on transmision licensees on introduction of goods and service tax compensation cess.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
303
8/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: Main SCADA EMS System of SLDC of Manipur (DOCO-09.11.2016), Asset-2: Main SCADA EMS System of SLDC of Mizoram (DOCO-10.04.2017), Asset-3: Main SCADA EMS System of SLDC of Arunachal Pradesh (Anticipated DOCO-15.11.2017) and Asset-4: Main SCADA EMS System of SLDC of Nagaland (Anticipated DOCO-30.11.2017) under project ? ?Expansion/ Upgradation of SCADA/ EMS System of SLDCs of North Eastern Region? for the period 2014-19 block.
Order reserved
304
5/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Establishment of Fibre Optic Communication System under Master Communication Plan in Western Region
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
305
3/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations �1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 �Bunching of Tirunelveli � Edamon section of the Tirunelveli � Muvathapuza (Cochin) 400kV quad D/c line initially(and temporarily) at 220kV with existing  Tirunelveli � Edamon 400kV twin D/c line (400KV line charged at 220Kv) under Transmission System associated with Kudamkulam Atomic Power Project�  in Southern Region..
Order reserved
306
269/MP/2017
Korba West Power Company Limited (KWPCL)
Petition under Section 79 (1) (c) and Section 79 (1) (f) of the Electricity Act, 2003 read with Clause 9 of the BPTA, Clause 11 of the TSA and Regulation 32 of CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 for deferment of operationalization of LTA on account of Force majeure events.
Hearing
307
267/MP/2017
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION (TANGEDCO)
The practical difficulties and financial implications due to the implementation of the Detailed Operating Procedure dated 05.05.2017.
Order reserved
308
262/MP/2017
Jindal Power Limited (JPL)
Petition seeking amendment to the transmission license granted to the Petitioner vide an order dated 09.05.2011, passed in Petition No. 105 of 2010, for including the 2 x 400kV bays and bus sectionalizer bays and part of 400/220 kV sub-station equipment at Raipur Sub-station of PGCIL
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
309
255/MP/2017
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
PETITION UNDER SECTIONS 79(1)(b) AND 79(1)(f) OF THE ELECTRICITY ACT, 2003 READ WITH ARTICLE 10 OF THE PPA AND PSA
Hearing
310
254/MP/2017
BSES Rajdhani Power Limited (BRPL)
Re-setting of the Rate of Late Payment Surcharge under Clause 45 of the Tariff Regulations 2014-19
Order reserved
311
253/MP/2017
sks power generation (chhattisgarh) limited (SPGCL)
Petition seeking surrender/ relinquishment of LTA of 513 MW (149 MW in WR and 364 MW in NR) out of the total LTA quantum of 683 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010.
Pending as per directions of the Commission
312
251/GT/2017
UDUPI POWER CORPORATION LTD (UPCL)
Application under Regulations 20, 25 & 27 of the  of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999; Regulations 2, 6 and 7 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations 2014 and under Section 62 and 79(1)(b) of the Electricity Act, 2003 for determination of tariff for the 2x600 MW thermal power plant set up by  Udupi Power  Corporation Limited in Udupi Taluk, Udupi District, Karnataka for the period, from 01.04.2014 to 31.03.2019.
Hearing
313
250/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1 : 765 kV Line bays at Jabalpur Pooling Station for 765 kV D/C Gadarwara STPS (NTPC) - Jabalpur pooling Station TL under  " POWERGRID Works associated with Part A of Transmission system for Gadarwara STPS of NTPC" in Western Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
314
247/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 1X500MVA, 765/400kV Transformer as spare ICT at Agra Sub-station, Asset-II: 1X500MVA, 765/400kV Transformer as spare ICT at Fatehpur Sub-station, Asset-III: 765/400 KV,500MVA, single phase  Auto Transformer as spare ICT at Jhatikra S/S and Asset-IV: 765/400 KV, 333MVA, single phase  Auto Transformer as spare ICT at Bhiwani S/S  under �Spare Transformer for 765/400KV ICTs in NR�.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
315
243/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff  of  Bongaigaon Thermal Power Station (3X250 MW) for the period from Date of Commercial Operation of Unit-1 (i.e. 01.04.2016) to 31.03.2019.
Interim order under preparation
316
242/MP/2017
Aryan M.P. Power Generation Private Limited AMPPGPL
Petition for declaring the letter of invocation of Bank Guarantee dated 23.10.2017 and thereafter the encashment of the Bank Guarantee dated 23.02.2010 of an amount of Rs. 56.1 Crores issued by Axis Bank Ltd. as illegal and for return of the said encashed amount along with damages.
Order reserved
317
241/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Determination of tariff of Muzaffarpur Thermal Power Station        Stage-I Unit-2 (110 MW) for the Period 15.10.2010 to 31.03.2014
Hearing
318
240/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Approval of tariff of MTPS Stage-I (2x110 MW) from 01.04.2014 to 31.03.2019.
Hearing
319
238/MP/2017
Darbhanga Motihari Transmission Company Limited (DMTCL)
Petition u/s 61, 63 and 79 of Electricity Act, 2003 to be read with the other laid down statutory framework
for seeking extension in Project scheduled commercial operation date and increase in transmission
charges due to unforeseen and uncontrollable events post award of ERSS-VI Transmission Scheme implemented by Darbhanga-Motihari Transmission Co. Ltd. under Tariff Based Competitive Bidding guidelines.
Order reserved
320
237/MP/2017
Suzlon Energy Limited (SEL)
Petition preferred under Section 94 (1)(f) of the Electricity Act, 2003 read with Regulation 111 and 116 of Central Electricity Regulatory Commission (Conduct of Business Regulations),1999 for seeking extension of time prescribed for implementation of the Hon�ble Central Electricity Regulatory Commission�s Order dated 5 January, 2016 in Petition No. 420/MP/2014 in the matter of �Endangering grid security due to non-implementation of contingency demand disconnection scheme for sudden loss of wind generation, non-availability of LVRT protection, non-scheduling of wind generation as per CERC (Indian Electricity Grid Code) Regulations, 2010 (IEGC) 6.5.23 (i), lack of necessary demand estimation as per IEGC Regulation 5.3 and not providing real time SCADA data to LDC.�, and for seeking relief to specific provisions of the aforementioned Order.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
321
236/MP/2017
DAMODAR VALLEY CORPORATION (DVC)
Petition against the decision of MPPMCL for Unilateral surrender of 100 MW from DSTPS in violation of provision of PPA between DVC & MPPMCL
Hearing
322
234/MP/2017
M.P. Power Management Co. Ltd. (MPPMCL)
Petition under Section 79 of the Electricity Act, 2003 for direction to Rajasthan Rajya Vidyut Prasaran Nigam Ltd to make payment of outstanding amount to the petitioner on account of overdrawal of power from Chambal - Satpura Complex/Chambal project & payment of O&M/capital expenditure of the Chambal - Satpura Complex/Chambal project and scheduling of respective shares of both the States in Chambal project (Hydel Power Plants)
Hearing
323
228/MP/2017
Bhushan Power & Steel Ltd. (BPSL)
Petition under Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 32 of the CERC (Grant of Connectivity, Long Term Open Access in intra State Transmission and related matters) Regulations, 2009 alongwith affidavit.
Hearing
324
227/MP/2017
LANCO AMARKANTAK POWER LTD. LAMPL
Petition under Section 79(1) (c) read with Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999
Order reserved
325
224/MP/2017
North East Transmission Company Ltd. (NETC)
PETITION UNDER SECTIONS 79(1)(d) OF THE ELECTRICITY ACT, 2003 READ WITH REGULATIONS 54 AND 55 OF THE CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014.
Hearing
326
222/MP/2017
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79(1)(b), 79(1)(f) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES WITH THE RESPONDENT WITH REGARD TO THE TARIFF PAYABLE UNDER THE POWER PURCHASE AGREEMENT DATED 27/11/2013
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
327
217/TT/2017
Jaypee Powergrid Limited (JPL)
APPROVAL UNDER REGULATION 86 OF CERC (CONDUCT OF BUSINESS) REGULATIONS, 1999 AND REGULATION 6 OF CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2009 AND CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014 FOR DETERMINATION OF:

I) TRUING UP TRANSMISSION TARIFF FOR 2009-14 TARIFF BLOCK AND
II) TRANSMISSION TARIFF FOR 2014-19 TARIFF BLOCK FOR 

ASSET ? I 
LILO OF 400 KV DC BASPA-NAPTHA-JHAKRI TRANSMISSION LINE

ASSET ? II 
KARCHAM WANGTOO ABDULLAPUR 400 KV DC QUAD TRANSMISSION LINE
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
328
39/RP/2017 in 146/GT/2015
Neyveli Lignite Corporation Ltd (NLC)
NLCIL- TSII Expn (2 X 250 MW)  - Petition seeking review of Tariff under CERC(Terms and Conditions of Tariff) Regulations 2014 � Reg
Order reserved
329
210/MP/2017
KUDGI TRANSMISSION LIMITED (KTL)
Petition for revision of Tariff for events occurring after the Bid Due Date
Order reserved
330
209/MP/2017
A D Hydro Power Limited (ADHPL)
Petition for Approval of Transmission Charges, Transmission Losses and other Conditions for use of the 176.5 km long 220KV Double Circuit Dedicated Transmission Line of Allain Duhangan Hydro Project- In Remand of proceedings arising out of Petition No. 259/MP/2010 by Hon'ble Supreme Court of India.
Hearing
331
38/RP/2017 in 135/GT/2015
NLC Tamilnadu Power Ltd (NTPL)
Petition for review of the Order dated 11.7.2017 passed by the Hon?ble Commission in Petition No. 135/GT/2015 in the matter regarding approval of tariff of Coal based NLC Tamil Nadu Power Ltd (TPS 2 x 500 MW) for the period from the date of the declaration of commercial operation of Unit I &II till 31.3.2019.
Order reserved
332
200/MP/2017
Nirani Sugars Ltd. (niranisugars)
PAYMENT OF OUTSTANDING DUES TOWARDS THE POWER SOLD
Hearing
333
199/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Kudgi Super Thermal Power Station Stage-I (3 X 800 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e. 25.07.2017) to 31.03.2019.
Interim order under preparation
page separator
S. No.
Petition No.
Petitioner
Subject
Status
334
198/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of    Transmission Tariff  for Asset-I:�800kV 3000MW HVDC POLE-III and LILO of Bishwanath Chariali � Agra HVDC line for parallel operation of the HVDC station at Alipurduar, Asset-II:�800kV 3000MW HVDC POLE-IV alongwith Earth electrode station and Earth Electrode line at Alipurduar and Agra end, Asset-III:LILO of Bongaigaon � Siliguri 400kV D/c line (quad) (under pvt. Sector) alongwith associated bays at Alipurduar, Asset-IV:LILO of Birpara-Salakati 220kV D/c line alongwith associated bays at new pooling station in Alipurduar, Asset-V:1x315MVA 400/220kV, ICT-I at Alipurduar, Asset-VI:1x315 MVA 400/220kV ICT-II at Alipurduar, Asset-VII:1x125MVAr 400kV Bus Reactor-I at Alipurduar and Asset-VIII:1x125MVAr 400kV Bus Reactor-II at Alipurduar from anticipated DOCO to 31.03.2019 under the transmission system associated with �Transmission system for development of pooling station in Northern part of West Bengal and transfer of power from Bhutan to NR/WR�.
Reply / additional information as per ROP to filed by Petitioner
335
197/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Feroze Gandhi Unchahar Thermal Power Station Stage-IV (1 X 500 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e. 31.07.2017) to 31.03.2019.
Interim order under preparation
336
195/MP/2017
NRSS XXXI (B) Transmission Limited (NRSSXXXIB)
Petition u/s 61, 63 and 79 of Electricity Act, 2003 to be read with the other laid down statutory framework for seeking extension in Project scheduled commercial operation date and increase in transmission charges due to unforeseen and uncontrollable events post award of NRSS XXXI (B) Transmission Scheme under Tariff Based Competitive Bidding guidelines of Transmission Projects.
Hearing
337
194/MP/2017
North Karanpura Transco Limited NKTL
Petition under Sections 61, 63, 79(1)(c) and 79(1)(f) of the Electricity Act, 2003 read with Article 16 of TSA and the tariff-based competitive bidding guidelines for transmission service, for claiming relief under TSA dated 14.03.2016 relating to implementation of the transmission Project Elements
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
338
32/RP/2017 in GT/325/2014
NTPC Limited
Review of the order dated 10.04.2017 in respect of determination of tariff of Jhanor Gandhar GPS (657.39 MW)  for the period from 01.04.2014 to 31.03.2019.
Order reserved
339
187/MP/2017
Essar Power M.P. Ltd. (EPMPL)
Petition for Relinquishment of 750 MW of LTA out of total LTA of 1200 MW granted under BPTA dated 07.01.2009
Reply / additional information as per ROP to filed by Petitioner,Respondent
340
180/MP/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Section 41 of the Electricity Act, 2003 read alongwith Central Electricity Regulatory Commission (Sharing of Revenue derived from utilization of Transmission Assets for other business) Regulations, 2007 for intimation to engage in other business for optimum utilization of transmission assets.
Hearing
341
178/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Solapur Super Thermal Power Station   (2 X 660 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e.  31.08.2017)  to 31.03.2019.
Interim order under preparation
342
171/GT/2017
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
In the matter of approval for filing petition in CERC for approval of Generation Tariff for shared Hydro Projects of Rajasthan & Madhya Pradesh installed in Rajasthan namely Rana Pratap Sagar Hydel Power station for the Financial year 2012-13 & 2013-14 in accordance with the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulation 2009.
Hearing
343
170/GT/2017
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
In the matter of approval for filing petition in CERC for approval of Generation Tariff for shared Hydro Projects of Rajasthan & Madhya Pradesh installed in Rajasthan namely Jawahar Sagar Hydel Power station for the Financial year 2012-13 & 2013-14 in accordance with the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulation 2009.
Hearing
344
169/MP/2017
sks power generation (chhattisgarh) limited (SPGCL)
Petition seeking surrender/ relinquishment of 170 MW (170 MW in WR) out of the total LTA quantum of 683 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010.
Pending as per directions of the Commission
345
164/MP/2017
IL & FS Tamil Nadu Power Company Limited (IL&FS)
PETITION UNDER SECTIONS 79(1)(C) AND 79(1)(F) OF THE ELECTRICITY ACT, 2003
Pending as per directions of the Commission
page separator
S. No.
Petition No.
Petitioner
Subject
Status
346
162/MP/2017
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (C), (D), (F) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 SEEKING DIRECTIONS AGAINST THE RESPONDENT IN RELATION TO THE MEDIUM TERM OPEN ACCESS FOR TRANSFER OF POWER FROM THE WESTERN REGION TO THE NORTHERN REGION
Order reserved
347
144/MP/2017
Neyveli Lignite Corporation Ltd (NLC)
Seeking upward revision of Technical Minimum of NLCIL  Stations
Hearing
348
139/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79 of the Electricity Act 2003 read with Regulation 54 and 55 of the CERC (Terms and Conditions of Tariff) Regulations 2014 seeking Appropriate Relief due to Extreme Practical Difficulty faced by the Petitioner in implementing Regulation 30 (6) of the said Regulation and Directions issued by the Hon?ble Commission in its Order dated 25.01.2016 and For Consequential Directions
Hearing
349
136/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation 86 of CERC  Conduct of Business Regulations1999 and CERC Terms and Conditions of Tariff Regulations 2014 for  determination of    Transmission Tariff  from 01.04.2014 to 31.03.2019
Reply / additional information as per ROP to filed by Petitioner,Respondent
350
129/MP/2017
SIMHAPURI ENERGY LIMITED (SEL)
Petition seeking surrender of 146 MW (135 MW in WR and 11 MW in SR) out of the total LTA quantum of 546 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010 read with Annexure-I as modified vide amendments dated 02.01.2012 and 17.10.2012.
Pending as per directions of the Commission
351
128/GT/2017
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Approval of tariff of Tripura Gas based Power Plant (TGBP), 101 MW for the period from COD of its Gas Turbine Unit to 31.03.2019
Order reserved
352
10/SM/2017
Suo Motu
Non-compliance of the provision of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of Transmission Licence and other related matters) Regulations, 2009.
Order reserved
353
124/MP/2017
Kanchanjunga Power Company Private Limited KPCPL
Petition under section 79(1)(f) read with section 79(1)(c) & (d), section 38, section 39, section 40 and section 60 of the Electricity Act, 2003 concerning the unjust, arbitrary and illegal terms imposed by Himachal Pradesh Power Transmission Corporation Limited and Allain Duhangan Hydro Power Limited for transmission of power by the Petitioner on inter-state transmission lines operated by them.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
354
122/MP/2017
Essar Power Gujarat Limited (EPGL)
Petition for Relinquishment of 250 MW of Long Term Access Agreement dated 04.12.2011 under Regulation 18 read with Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in inter-state Transmission System and related maters) Regulation, 2009, of the identified transmission system by the Essar Power Gujarat Limited (4x660-Phase-II) Thermal Power Plant at District Jamnagar in the State of Gujarat.
Hearing
355
119/MP/2017
Rajasthan Sun Technique Energy Private Ltd RSTEPL
The Power Purchase Agreement 8th January 2011 (?PPA?) entered into between NTPC Vidyut Vyapar Nigam Limited and Rajasthan Sun Technique Energy Pvt Ltd./Extension of Scheduled Commissioning Date
Hearing
356
117/MP/2017
DB Power Limited (DBPL)
Petition under Section 79(1) (b) read with Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 inter alia seeking direction to the Respondent to pay the Tariff considering 01.08.2015 to 31.03.2016 as the First Contract Year in terms of Schedule 8 of the Power Purchase Agreement 19.08.2013 executed between the Petitioner and the Respondent
Hearing
357
26/RP/2017 in 085/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94(1)(f) OF THE ELECTRICITY ACT, 2003 FOR REVIEW  AND MODIFICATION OF THE FINAL ORDER DATED 24.02.2017 PASSED BY THIS HON'BLE COMMISSION IN PETITION NO. 85/TT/2015
Order reserved
358
114/MP/2017
DANS Energy Private Limited (DEPL)
PETITION UNDER SECTION 79 (1) (c) READ WITH SECTIONS 28 AND 29 OF THE ELECTRICITY ACT, 2003 AND THE APPLICABLE REGULATIONS NOTIFIED BY THE HON�BLE COMMISSION
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
359
107/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For combined assets Asset-1: 400 kV D/C Parbati Pooling Point �Amritsar line alongwith associates bays and Asset-2 : 80 MVAR bus reactor at Parbati Pooling Point along with associated bays under transmission system associated with PARBATI-III-HEP in Northern Region.

And 

Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Final and Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

Asset-3 : LILO of 2nd ckt of Parbati-II-Koldam T/L at Pooling station and LILO at Parbati-III (Portion c-d ), Asset-4 : LILO of 2nd ckt of Parbati-II-Koldam T/L at Pooling Station along with associated bays and LILO of Parbati-III (Portion e-f) under transmission system associated with PARBATI-III-HEP in Northern Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
360
19/RP/2017 in 94/TT/2011
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Petition seeking review of order dated 16.11.12, 02.01.2013, 17.02.2016 and 23.02.2016 passed by the Hon'bie Commission in Petition No. 94/TT /2011.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
361
18/RP/2017 in 92/TT/2011
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Petition Seeking Review of Order dated 16.11.2012 passed by the Hon'ble CERC in 92/TT/2011.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
362
95/MP/2017
Welspun Energy Private Limited (WelspunEnergy)
Petition under Section 79 of the Electricity Act, 2003 in relation to disputes arising out  of the Power Purchase Agreement dated 26.07.2016 between Petitioner herein, i.e. Welspun Energy Private Limited and Solar Energy Corporation of India Limited
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
363
94/MP/2017
Bharat Aluminium Company Limited (BALCO)
A petition under Section 79 (1)(f) of the Electricity Act, 2003 read with the relevant provisions of CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010 for seeking quashing of notices dated 16.03.2017, 24.03.2017, 06.04.2017 and e-mail dated 19.04.2017 sent by the Power Grid Corporation of India Ltd and refund of the payments made under protest by the Petitioner against the impugned invoices
Reply / additional information as per ROP to filed by Petitioner,Respondent
364
16/RP/2017 in TT/384/2014
NTPC Limited
Review of the Order dated 16.01.2017 passed by the Hon�ble Commission approving the transmission tariff for a section of the 400 kV (Quad) 2xS/C Parbati-Koldam transmission line Circuit-II (starting from LILO point of Parbati (Banala) Pooling Station to Koldam HEP) in Northern Region for Tariff block 2014-19 period under Regulation 86 of Central Electricity Regulatory Commission (Conduct of business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014.
Reply / additional information as per ROP to filed by Petitioner,Respondent
365
15/RP/2017 in 156/TT/2015
NHPC LTD
Petition under Section 94(1) (f) of the Electricity Act, 2003, for Review of tariff order dated 29.12.2016 passed by the Central Commission in Petition No. 156/TT/2015.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
366
74/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Petition Under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of MTPS Stage-II (2x195 MW) from anticipated COD of Unit-1 to 31.03.2019
Order reserved
367
68/MP/2017
DB Power (Madhya Pradesh) Limited (DBPMPL)
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter alia seeking setting aside/quashing of invocation & encashment by the Respondent of  the Bank Guarantee furnished by the Petitioner in relation to the grant of LTA to the Petitioner qua its proposed Thermal Power Project in Singrauli District, Madhya Pradesh and consequent direction to the Respondent to reimburse the encashed amount along with interest to the Petitioner.
Hearing
368
66/MP/2017
NTPC Limited
Petition under Part 7 Regulation 4 of the CERC (Indian Electricity Grid Code) Regulations 2010 (as amended) read with Regulation 111 of CERC (Conduct of Business) Regulations, 1999 in regard to provision 6.3 A of the Grid Code.
Order Reserved- Additional information for final order to be filed by Petitioner
page separator
S. No.
Petition No.
Petitioner
Subject
Status
369
38/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset-I: 01 No. of 01x125 MVAR Bus Reactor (1st) and associated bay equipments at 400 KV Durgapur S/S, Asset-II: 01 No. of 1x125 MVAR Bus Reactor (2nd) and associated bay equipments at 400 KV Durgapur S/S   , Asset-III: 01 Nos of 125 MVAr Bus Reactor (1st) at Rengali Substation, Asset-IV: 01 Nos of 125 MVAr Bus Reactor (2nd) at Rengali Substation, Asset-V: Installation of 01x125 MVAR Bus Reactor by replacing existing 1x50 MVAR Bus Reactor at 400 KV Rourkela S/S Asset-VI: Installation of 01x125 MVAR Bus Reactor in Parallel with existing 50(3X16.67) MVAR Bus Reactor at Biharsharif S/S Asset-VII: Installation of 2x125 MVAR Bus Reactor in Parallel with existing 2X50 MVAR Bus Reactor at Jamsedpur S/S Asset-VIII: Procurement of one 500 MVA, Single phase unit of 765/400 kV ICT for Eastern Region to be stationed at Gaya Sub-station (diverted to Ranchi) Asset-IX: Installation of 1X125 MVAR Bus Reactor at 400 kV Gazuwaka S/S Asset-X: Converting 2X80 MVAr Line reactor to 2X80 MVAr switchable line reactor  at Gorakhpur end for 400 kV Barh-II-Gorakhpur transmission line under Eastern Region Strengthening Scheme IX in Eastern Region.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
370
10/RP/2017 in TT/384/2014
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition under section 94(1)(f) of the Electricity Act, 2003 read with regulation 103 of The Central Electricity Regulatory Commission (Conduct of Business), Regulation 1999
Reply / additional information as per ROP to filed by Petitioner,Respondent
371
9/RP/2017 in TT/312/2014
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition for review of order dated 19.12.2016 passed by this Hon'ble Commission in 312/TT/2014 titled as PKTCL Vs HPSEB and Others
Hearing
372
8/RP/2017 in TT/312/2014
NTPC Limited
REVIEW OF THE ORDER DATED 19.12.2016 PASSSED BY CERC I PETITION NO. 312/TT/2014
Hearing
373
4/RP/2017 in 156/TT/2015
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition for review of order dated 29.12.2016 passed by this Hon;ble Commission in 156/TT/2015 titled as "PKTCL Vs RRVPNL & Ors"
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
374
23/GT/2017
BHARTIYA RAIL BIJLEE COMPANY LTD. (BRBCL)
Approval of tariff  of Nabinagar Thermal Power Project (4X250 MW) for the period from anticipated Date of Commercial Operation  of Unit-1  to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
375
21/MP/2017
Essar Power (Jharkhand) Ltd EPJL
Petition for Relinquishment of 1100 MW of Long Term Access agreed under the Bulk Power Transmission Agreement dated 24.02.2010 under Regulation 18 read with Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009, of the subject Transmission Lines by the ESSAR Power Jharkhand Limited (3x600 MW) Thermal Power Plant, Chandwa Tehsil, District Latehar in the State of Jharkhand.
Pending as per directions of the Commission
376
16/TT/2017
Bhakra Beas Management Board (BBMB)
Determination of Tariff of BBMB Transmission systems & SLDC functions for the period 2014-19
Order reserved
377
11/MP/2017
GMR CHHATTISGARH ENERGY LIMITED (GCEL)
Petition under Section 79(1)(c) of the Electricity Act, 2003, read with the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and the Detailed Procedure for grant of LTA, seeking deferment of operationalization of Long Term Access of 430 MW in Northern Region as per the BPTA dated 31.03.2010 and Petition under Section 79(1)(c) of the Electricity Act, 2003, read with the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and the Detailed Procedure for grant of LTA, seeking relinquishment of Long Term Access of 386 MW in Western Region out of the total quantum of 816 MW as per the BPTA dated 31.03.2010
Hearing
378
7/GT/2017
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business) Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for revision of generation tariff from 24.03.2014 to 31.03.2014 in respect of Parbati-III Power Station.
Order reserved
379
6/GT/2017
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business) Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 7 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Tariff for period 2014-19 in respect of Parbati--III Power Station.
Order reserved
380
5/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79(1)(f) and 79(1)(b) of the Electricity Act, 2003 in connection with the disputes and differences arising under the Power Purchase Agreement dated 12.05.2008 between the Petitioner and Respondent no. 1.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
381
4/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79(1)(f) and 79(1)(b) of the Electricity Act, 2003 in connection with the disputes and differences arising under the Power Purchase Agreement dated 18.07.2008 between the Petitioner and Respondent no. 1.
Hearing
382
249/GT/2016
Teesta Urja Limited (TUL)
Determination of Tariff of 1200 MW Teesta III Hydro Electric Project Sikkim
ROP Issued
383
248/MP/2016
KUDGI TRANSMISSION LIMITED (KTL)
Revision of SCOD due to reasons beyond the control of the TSP
Order reserved
384
246/MP/2016
Coastal Energen Private Limited (CEPL)
Relinquishment of 542 MW LTOA.
Pending as per directions of the Commission
385
244/MP/2016
NTPC Limited
Measurement of GCV of Coal received at the plant site of NTPC Power Stations
Pending as per direction of Higher Court / APTEL
386
66/RP/2016 in 41/IA/2016 in TT/528/2014
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Review Petition seeking recall of order dated 17.02.2016.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
387
65/RP/2016 in 32/IA/2016 in 018/TT/2015
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Application seeking recall of order dated 23.02.2016.
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
388
220/MP/2016
West Bengal State Electricity Distribution Company Limited WBSEDCL
Petition under Section 79 (1) (f) of the Electricity Act, 2003 seeking adjudication of dispute between West Bengal State Electricity Distribution Company Limited and NTPC Ltd.and Damodar Valley Corporation relating to over invoicing and recovery of Rs. 1192.67Crores.
Hearing
389
217/MP/2016
Thermal Powertech Corporation India Limited TPCIL
Petition seeking compensation on account of Changes in Law under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreement dated 01.04.2013 entered into between Thermal Powertech Corporation India Ltd and the Distribution Companies in the States of Andhra Pradesh and Telangana
Pending as per directions of the Commission
390
211/MP/2016
Jindal Power Limited (JPL)
Petition under Section 19 of the Electricity Act, 2003 read with Regulation 14 and Regulation 7 of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading license and other related matters) Regulations, 2009 seeking revocation of the Inter State Trading License granted to M/s Global Energy Private Limited.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
391
197/MP/2016
DAMODAR VALLEY CORPORATION (DVC)
Requirement of revenue in relation of Pension & Gratuity of employees and retired employees during the tariff period 2014-19
Hearing
392
176/MP/2016
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (f) OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES ARISING UNDER THE POWER PURCHASE AGREEMENT DATED 31/07/2012 BETWEEN THE PETITIONER AND THE RESPONDENTS
Pending as per direction of Higher Court / APTEL
393
169/MP/2016
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79 (1) (b) and (f) of the Electricity Act, 2003 for adjudication of claims towards compensation arising out of Change In Law and consequential reliefs as per provisions of the PPA dated 31.07.2012 between the Petitioner and Respondents herein.
Pending as per direction of Higher Court / APTEL
394
142/GT/2016
NTPC Limited
Tariff Petition for approval of tariff for Mouda-II (2x660 MW) from anticipated COD of U#1 to 31.3.2019
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
395
137/MP/2016
GMR Kamalanga Energy Limited (GKEL)
Petition for relinquishment of Long Term Open Access
Pending as per directions of the Commission
396
91/MP/2016
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Section 79 (1) (f) and (k) of the Electricity Act, 2003 read with Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations 2014 along with Regulation 111 and Regulation 115 of the CERC (Conduct of Business) Regulations, 1999, seeking re-determination of gross station heat rate of Badarpur Thermal Power Station as provided under Regulations 36 (C) (a) (ii) of the CERC (Terms & Conditions of Tariff) Regulations 2014 along with Affidavit
Hearing
397
86/MP/2016
BSES YAMUNA POWER Ltd. (BYPL)
Seeking decommissioning and/or closure of BTPS Stage-I
Order reserved
398
81/TT/2016
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval under Sections 61, 62 and 79 (1) (c) & 79 (1) (d) of the Electricity Act, 2003 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of Annual Fixed Cost and determination of tariff for the licensed transmission business for the financial years 2015-16, 2016-17, 2017-18 and 2018-19 for 400 kV Srinagar-Srinagar PH line as per Hon?ble Central Electricity Regulatory Commission?s order dated 31 January 2013 against Petition number 133/ MP/2012
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
399
80/TT/2016
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval under Sections 61, 62 and 79 (1)(c) & 79 (1) (d) of the Electricity Act, 2003 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of Annual Fixed Cost and determination of tariff for the licensed transmission business for the financial years 2015-16, 2016-17, 2017-18 and 2018-19 for 400 KV Srinagar Substation as per Hon'ble Central Electricity Regulatory Commission's order dated 31 January 2013 against Petition number 133/MP/2012.
Reply / additional information as per ROP to filed by Petitioner,Respondent
400
64/MP/2016
BSES Rajdhani Power Limited (BRPL)
Petition under Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 30(7) of CERC (Terms and Conditions of Tariff), Regulations, 2014 seeking adjudication of dispute between Petitioners, i.e., BSES Rajdhani Power Limited & BSES Yamuna Power Limited with NTPC Ltd.
Pending as per direction of Higher Court / APTEL
401
38/MP/2016
Lanco Babandh Power Ltd
Petition u/s 79(1) ( c) read  with  79(1) (f) and 79 (1) (k) of the E. Act, 2003 inter alia seeking a decalration that the factors/ events namely dely in forest clearance of land for main plant cancellation of  allocated coal block to the Petitioner, non-signing of Fual supply agreement dely ihn acquisition /procurement of land for mkain plant, delay in approval of Land for Ash Pond by state of Odhisa, dely in clearance for construction of dedicated transmission line from Ministry of Power in the construction of the  2 x 660 MW Coal based thermal Power Plant located in dhenkenal district Odisha for Force majeure events under BPTA dated 24.02.2010 seeking extension of time period for achieving the Commercial Operation date of the project and other consequential reliefs under the BPTA dated 24.02.2010
Hearing
402
33/MP/2016
NTPC Limited
Petition under section 79(1)(a)  of the Electricity Act, 2003 read with CERC (Terms and Conditions of  Tariff) Regulations, 2014 for relief on account of a Change in Law affecting the Badarpur Thermal Power Station.
Hearing
403
51/MP/2016
Bharat Aluminium Company Limited (BALCO)
An application for Regulatory Compliance of order dated 30.10.2014 passed in Petition No.134/MP/2011 and Order dat ed 09.10.2015 passed in Petition No. 124/RC/2015 under Section 142 and 146 of the Electricity Act, 2003
Pending as per direction of Higher Court / APTEL
page separator
S. No.
Petition No.
Petitioner
Subject
Status
404
10/MP/2016
Jaiprakash Power  Ventures Limited
Petition u/s 79(1) (f) and Sec- 19 of E. Act, 2003 read with Regulations 14 of CERC(procedures, Terms and Condtions for grant of trading license and other realted matters) Regualtions, 2009 seeking refund of the Late payment of Surchages illegally retained by the Respondent No. 1 under Power Purchase Agreement dat ed 30.0.5 2011 alongnwith interest and initiation of proceedings for revocation of the Inter State Trading License of the Respondent No.1
Pending as per direction of Higher Court / APTEL
405
03/MP/2016
M/s Vendanta Limited (Formerly Sesa  Sterlite Limited)
Petition  for the relinquishment of the Long Term Open Access under the Bulk Power Transmission Agreement dated 5th July, 2010 under Regulation 2010 read with Regulation 32 of the CERC(Grant of Connectivity, Long Terms Access and Medium Terms Open Access in inter State Transmission and related  matters ) Regulations, 2009
Pending as per directions of the Commission
406
311/MP/2015
Tata Power Delhi Distribution Limited (TPDDL)
Petition praying for appropriate directions restraining the Respondent from recovering the Energy Charge Rate strictly in terms of the Tariff Regulations framed b y this Honble Commission
Hearing
407
309/GT/2015
Pragati Power Corporation Limited (PPCL)
Filing of Petition under Sec 62 and 79(1) (a) & (b) of the Electricity Act, 2003, CERC (Terms and  Conditions of Tariff) regulations, 2009 and sec-86 of CERC(CB)  Regulations, 1999 for True up of  Generation Tariff of  Pragati-III CCPS 1371.2 MW pwoer plant  of Pragati Power Corporation Limited for the period from COD of GT#1 up to 31.03.2014 of MYT 2009-2014
Hearing
408
305/MP/2015
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
Petition under Section 79 of the Electricity Act, 2003 read with  provisions of the Power Supply agreement dated 05.1.2011 and Power Purchase Agreement dated 25.03.2011 for directions to make Energy Charges as pass-through based on the actual fuel cost incurred by the Petitioner
Order Reserved- Additional information for final order to be filed by Petitioner,Respondent
409
303/MP/2015
M/s Vedanta Limiited
Petition for the relinquishment of the long term open access under the bulk power transmission agreement dated  5.1.2011 under Regulaiton 18 read with Regulation 32 of the CERC (Grant of Connectivity, Long Term Access and Medium Term Access in inter-State transmission and related matters) Regulations, 2009
Pending as per directions of the Commission
410
014/SM/2015
Suo Motu
Notice under Section 19 of the Electricity Act 2003 for revocation of the inter-State transmission licence granted to Talcher II Transmission Company Ltd. Talcher II Transmission Company Ltd.
Pending as per direction of Higher Court / APTEL
411
13/SM//2015
Suo Motu
Revocation of transmission licence under Section 19 of the Electricity Act, 2003 granted to North Karanpur Transmission Compnay Limited
Pending as per direction of Higher Court / APTEL
page separator
S. No.
Petition No.
Petitioner
Subject
Status
412
221/GT/2015
Pragati Power Corporation Limited (PPCL)
Tariff Petition under section 62 and 79(1) (a) & (b) of the Electricity Act, 2003 and CERC Tariff Regulation 2014 for determination of Generation Tariff of Pragati-III CCPS 137.2 MW Power plant of Pragati Power Corporation Limited for the period  from 01-04-2014 to 31-03-2019 of current MYT
Hearing
413
183/MP/2015
Meenakshi Energy Private Limited (MEPL)
For adjudication of disputes over  an increas in tariff sought by the Petitioner for its Power plant selling to AP and telangana
Pending as per direction of Higher Court / APTEL
414
092/MP/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition seeking directions with regard to difficulties in impementing some of the directions given in the Order dated 16.02.2015 in Petition Nos 92/MP/2014 alongwith IA Nos. 43/2014, 51/2014, 54/2014, 56/2014 & 59/2014, Petition NO 376/MP/2014, Petition NO 382/MP/2014, Petition NO 393/MP/2014 and Review petition No. 25/RP/2014.
Order reserved
415
064/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
APPROVAL OF TRANSMISSION TARIFF FOR ËSSAR GUJARAT TPS AND EXTENSION OF BACHAO SUBSTATION UNDER TRANSMISSION SYSTEM FOR CONNECTIVITY OF ESSAR POWER GUJARAT LIMITED IN WESTERN REGION FOR TARIFF BLOCK 2014-19
Hearing
416
018/SM/2015
Suo Motu
Suo motu Petition in the matter of declaration of commercial operation of Units 20 to 50 of Mundra Ultra Mega Power Project developed by Coastal Gujarat Power Ltd
Hearing
417
MP/463/2014
GMR Vemagiri Power Generation Limited.
Petition under Section 79(I)(f) of the Electricity Act, 2003 for a direction to the Respondents to pay Additional Fixed Charge of Rs.0.439/KWH for the balance period of PPA.
Pending as per direction of Higher Court / APTEL
418
GT/130/2014
NTPC Limited
Petition Under section 62 and 79(I)(a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity regulatory Commission (Conduct of Business) regulations, 1999 for approval of tariff of Barh Super thermal Power Station Stage-II (2X660 MW) for the period  from anticipated Date of Commercial operation of 1st Unit (Unit-IV) to 31.03.2019.
Hearing
419
MP/041/2014
Aurum Renewables Energy Pvt. Ltd. AREPL
Petition for adjustment of capacity utilization, adjustment of tariff, extension of time for execution of project and other consequential reliefs.
Pending as per direction of Higher Court / APTEL
420
MP/014/2014
KVK ENERGY VENTURES PVT. LTD. (KVKENERGY)
petition for adjustment of Tariff, extension of time for execution of project and other consequential reliefs.
Pending as per direction of Higher Court / APTEL
421
MP/327/2013
DIWAKAR SOLAR PROJECTS PRIVATE LIMITED (DIWAKAR_SOLAR)
For adjustment of tariff, extension of time for execution of project and other consequential reliefs.
Pending as per direction of Higher Court / APTEL
page separator
S. No.
Petition No.
Petitioner
Subject
Status
422
009/2009
MPPTCL
Payment of interest on the excess amount recovered as per order dated 23.10.2000 and order dated 30.09.2008 in Petition No.10/2000 and order dated 23.03.2007 in Petition No. 6/2004 in respect of wheeling charges payable to Gridco for wheeling of Central Sector Power from NTPC power station is in Eas
Pending as per direction of Higher Court / APTEL
423
130/2009
Suo Motu
Maintenance of Grid Discipline-non-compliance of provisions of the Indian Electricity Grid Code by TNEB
Pending as per direction of Higher Court / APTEL
424
081/2009
Suo Motu
Maintenance of Grid Discipline – Non  ‐compliance of provisions of the Indian Electricity Grid Code by Tamil Nadu Electricity Board.
Pending as per direction of Higher Court / APTEL
425
080/2009
Suo Motu
Maintenance of Grid Discipline-Compliance of provisions of  the Indian Electricity Grid Code by Transmission Coporation of Andhra Pradesh Ltd.
Pending as per direction of Higher Court / APTEL
426
121/2007
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Revision of tariff for the block years 2001-04 and 2004-09 in terms of  the interpretation of tariff regulations by Appellate Tribunal for Electricity.
Pending as per direction of Higher Court / APTEL
427
131/2007
Suo Motu
Default in payment of Unscheduled Interchanges (UI) charges for the energy drawn in excess of her drawal schedule (UP).
Pending as per direction of Higher Court / APTEL