Petitions Status
As on 31/05/2018
S. No.
Petition No.
Petitioner
Subject
Status
1
175/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations 2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for 08 nos Transmission assets under �North Eastern Region Strengthening Scheme-VII (NERSS-VII)� for 2014-19 Tariff Block Period in North-Eastern Region.
Preliminary Scrutiny
2
174/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for assets under Conversion of Fixed Line Reactors to Switchable Line Reactors in Southern Region.
Preliminary Scrutiny
3
173/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
PETITION FOR APPROVAL OF TRANSMISSION TARIFF For
Asset I - STATCOM  System (+/-) 300MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor), cooling system & STATCOM protection / controller  etc at Rourkela Substation (Anticipated DOCO: 01.04.2018) & Asset II - STATCOM  System (+/-) 200MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2x125 MVAR reactor and 2x125 MVAR Capacitor), cooling system & STATCOM protection / controller  etc at Jeypore Substation (Anticipated DOCO: 01.05.2018) under ?Eastern Region Strengthening Scheme ?XI (ERSS-XI)  ?
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
4
172/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I:  Combined Assets of (1) 400 kV D/C Ajmer (New)- Ajmer (RVPN) TL along with associated bays at both ends ; (2) 400 kV, 125 MVAR Bus Rector along with associated bay at Ajmer (New) Substation; (3) 765/400 kV, 3X500 MVA ICT-I along with associated bays at Ajmer (New) Substation; (4) 400 kV D/C Chittorgarh (New)- Chittorgarh (RVPN) TL along with associated bays at both ends ; (5) 765 kV, 240 MVAR Bus Reactor along with associated bay at Chittorgarh (New) Substation ;(6) 400 kV, 125 MVAR Bus Reactor along with associated bay at Chittorgarh (New) Substation;(7) 765/400 kV, 3X500 MVA ICT-I along with associated bays at Chittorgarh (New) Substation; (8) 765/400 kV, 3X500 MVA ICT-II along with associated bays at Chittorgarh (New); Asset-II: Combined Assets of (1) 765 kV, 240 MVAR Bus Rector along with associated bay at Ajmer (New) Substation; (2) 765/400 kV, 3X500 MVA ICT-II along with associated bays at Ajmer (New) Substation ;Asset-III: 2 X 400 kV D/C(Quad)Tirunelveli Pooling Stataion -Tuticorin Pooling station line  along with new 400/230KV (GIS) Tirunelveli Pooling substation with 2X 125MVAR 400KV Bus reactors & associated bays at 400/230KV Tuticorin Pooling station  ; Asset-IV: 2X500MVA 400/230KV transformers along with associated bays & equipments at new 400/230KV (GIS) Tirunelveli Pooling substation, under Transmission System Associated with "Green Energy Corridors: Inter State Transmission Scheme (ISTS)- Part A� in Northern Region & Southern Region.
Preliminary Scrutiny
5
171/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset: Replacement of 01 No. of 1x315 MVA, 400/220 kV ICT with 1x500 MVA, 400/220 kV ICT (2nd) at 400 kV Maithon S/S under Transmission System for �Eastern Region System Strengthening Scheme-IX� in Eastern Region.
Preliminary Scrutiny
6
170/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Filing of petition for determination of transmission tariff for NLC- KaraiKal 230 kV  D/c line (through LILO of the 230kV Neyveli- Bahour S/c line at Karaikal) under NLC- Karaikal 230kV D/c line in Southern Region
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
7
169/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Truing up of fees and charges for assets under Fibre Optic Communication System in Lieu of existing Unified Load Despatch & Communication (ULDC) Microwave Links in Southern Region
Hearing
8
168/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for assets under Fiber Optic Communication system for central sector Sub-stations & Generating Stations� in Southern Region.
Hearing
9
167/MP/2018
SEMBCORP GAYATRI POWER LIMITED (SGPL)
Petition under Section 79(1)(C) of the Electricity Act, 2003 seeking permission of the Hon'ble Central Electricity Regulatory Commission to transfer and / or assign the rights and obligations of Sembcorp Gayatri Power Limited under the Transmission Service Agreement dated 11.06.2014 to Sembcorp Energy India Limited, as stipulated under the scheme of amalgamation.
Hearing
10
166/MP/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under section 79(1)(f) read with section 79 (1) (c) of the Electricity Act, 2003
Hearing
11
165/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 02.08.2016, executed between the Parampujya Solar Energy Pvt. Ltd. (PSEPL) and Solar Energy Corporation of India Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
12
164/MP/2018
Parampujya Solar Energy Private Limited (PSEPL)
Petition under Section 79 the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 27.07.2016, executed between Parampujya Solar Energy Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
13
163/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations‟1999 and CERC (Terms and Conditions of Tariff) Regulations ‟2014 for determination of Transmission Tariff from actual DOCO to 31/03/2019 For Asset: Modification of 132 kV bus arrangement including switchgear to Double main (DM) scheme with GIS at 220/132 kV Birpara Substation under Eastern Region Strengthening Scheme XIV in Eastern Region.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
14
162/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset: 02 Nos 400kV line bays at Ranchi 400kV Sub-station for Raghunathpur TPS � Ranchi 400kV D/C transmission line under Common Scheme for 765 kV Pooling Stations and Network for NR, Import by NR from ER and from NER/SR/WR via ER and Common scheme for network for WR and Import by WR from ER and from NER/SR/WR via ER in Eastern Region.
Preliminary Scrutiny
15
20/RP/2018 in 13/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94 OF THE ELECTRICITY ACT, 2003 READ WITH REGULATIONS 103, 111 AND 114 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 READ WITH ORDER 47, RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 FOR REVIEW OF ORDER DATED 22.2.2018 PASSED BY THIS HON'BLE COMMISSION IN PETITION NO.13/TT/2017.
Preliminary Scrutiny
16
19/RP/2018 in 62/MP/2017
POWERGRID NM Transmission Limited (PNMTL)
Review of this Hon�ble Commission�s Order dated 26.03.2018 in Petition No. 62/MP/2017 filed by POWERGRID NM Transmission Limited (erstwhile Nagapattinam-Madhugiri Transmission Company Limited).
Hearing
17
18/RP/2018 in 168/MP/2017
WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (WBSETCL)
PETITION FOR REVIEW UNDER SECTION 94 (1) (f) OF THE ELECTRICITY ACT, 2003 R/W ORDER 47 RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1908 AND REGULATION 103 (1) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999, SEEKING REVIEW OF ORDER DATED 29.01.2018 PASSED IN PETITION NO. 168/MP/2017
Hearing
18
161/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1:  1 no. 400 kV Line bay (at POWERGRID, Sikar end) along with 50 MVAR Non- Switchable line reactor for Ckt-I of 400 kV D/C Bikaner (RVPNL)- Sikar (PG) line and  Asset 2: 1 no. 400 kV Line bay (at POWERGRID, Sikar end) along with 50 MVAR Non- Switchable line reactor for Ckt-II of 400 kV D/C Bikaner (RVPNL)- Sikar (PG) line under ? Line bays associated with various Regional Strengthening Schemes in NR? Scheme.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
19
160/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: Replacement of 1X100MVA, 220/132kV ICT-II by 1X200MVA, 220/132kV ICT-II at Raebareli S/s (DOCO: 19.02.2018), Asset-II: Replacement of 1X100MVA, 220/132kV ICT-III by 1X200MVA, 220/132kV ICT-III at Raebareli S/s (DOCO: 01.12.2017) under �Augmentation of Transformation Capacity at Raebareli & Sitarganj 220/132kV Substations�
Hearing
20
159/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 125 MVAR Bus Reactor at 400/220 kV Manesar Substation Extension under ?Bus Reactor Scheme in Northern Region, Phase-II?.
Hearing
21
158/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from Anticipated/ Actual DOCO to 31.03.2019 For Asset 1: 400/220kV, 3 X 105 MVA ICT alongwith associated bays at Hamirpur Substation, Asset  2:  220kV, 2Nos Line Bays at Hamirpur Substation. Asset   3:  220kV, 2Nos Line bays at Jallandhar Substation, Asset 4: 1 X 500 MVA, 400/220 kV ICT-IV  at GIS Gurgaon Substation Under �Augmentation of Transformers in Northern Region�Part B� in Northern Region
Hearing
22
157/MP/2018
Prayatna Developers Private Limited (PDPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 18.05.2016 executed between Prayatna Developers Pvt. Ltd. and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
23
156/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
Petition invoking Section 79(1)(b) and (f) of the Electricity Act, 2003 seeking compensation/ relief for increased expenses due to certain events of Change in Law as per the applicable provisions of the PPAs dated 18.01.2014 and 20.01.2014.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
24
155/MP/2018
BSES YAMUNA POWER Ltd. (BYPL)
Petition under Section 79 (1) (a) & (f) and other applicable provisions of the Electricity Act, 2003 read with Regulation 110 & 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner and Respondent NTPC Ltd. regarding excess recovery of Annual Fixed Costs for various generating stations of the Respondent during FY 2014-19
Hearing
25
154/MP/2018
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Miscellaneous Petition u/s 79 to adjudicate dispute between Petitioner and Respondent in accordance to BPT agreement dated 21.11.2011
Hearing
26
153/MP/2018
MAHARASHTRA STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (MSETCL)
Miscellaneous petition u/s 79 to adjudicate dispute between the petitioner and the respondent as per bulk agreement dated 06.09.2011
Hearing
27
152/MP/2018
BSES Rajdhani Power Limited (BRPL)
Petition under Section 79 (1) (a) & (f) and other applicable provisions of the Electricity Act, 2003 read with Regulation 110 & 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner and Respondent NTPC Ltd. regarding excess recovery of Annual Fixed Costs for various generating stations of the Respondent during FY 2014-19
Hearing
28
151/MP/2018
Shree Cement Limited (SCL)
Down gradation of Trading License from Category-I to Category-II
Preliminary Scrutiny
29
150/TT/2018
DAMODAR VALLEY CORPORATION (DVC)
Petition for determination of tariff for Transmission & distribution System Activities of DVC Network for the period from 01.04.2014 to 31.03.2019
Hearing
30
149/GT/2018
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter �V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of tariff of PARE Hydro Electric Power Plant (PHEP) (2 X 55 = 110 MW) for the period from COD to 31.03.2019;
Preliminary Scrutiny
31
148/TT/2018
TAMIL NADU TRANSMISSION CORPORATION LIMITED (TANTRANSCO)
Transmission Tariff for ISTS Lines of TANTRANSCO
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
32
147/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Aurangabad(POWERGRID) -Padghe (POWERGRID) 765kV D/C line & Padghe (POWERGRID)-Padghe/kudus (MSETCL) 400kV D/C (QUAD) line along with associated bays and Establishment of 765/400 kV 2x1500MVA Padghe GIS SS under System Strengthening in North/West Part of Western Region for IPP Projects in Chhattisgarh (IPP-E).
Preliminary Scrutiny
33
146/MP/2018
NTPC Limited
Seeking Hon?ble Commission?s permission to allow interchange of infirm power with grid for Unit-III of Kudgi STPP Stage-I (3X800 MW), beyond 31.05.2018.
Order reserved
34
145/TT/2018
Essar Power Transmission Company Limited (EPTCL)
Approval under Regulation of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of transmission tariff from the anticipated DOCO to 31.03.2019 for 400 kV D/C Mahan-Sipat and 2x50 MV AR line reactors at Mahan Pooling Substatyion and 1x80 MVAR, 420 kV switchable bus reactor at Mahan TPS along with its associated 400 kV bay
Pending as per directions of the Commission
35
144/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2014-15 in respect of  Rangit Power Station.
Hearing
36
143/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Sewa-II Power Station.
Hearing
37
142/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Parbati-III Power Station.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
38
141/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2016-17 in respect of  Chamera-III Power Station.
Hearing
39
140/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2015-16 in respect of  Chamera-III Power Station.
Hearing
40
139/MP/2018
NHPC LTD
Application under Regulation-31(6) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for recoupment of under-recovered energy charges due to shortfall in energy generation for reasons beyond the control of generating station during the FY 2015-16 in respect of  Dhauliganga Power Station.
Hearing
41
138/MP/2018
DCM SHRIRAM LIMITED (DCMSHRIRAM)
PETITION UNDER SECTION 79 OF THE ELECTRICITY ACT 2003 READ WITH REGUALTION 14 & 15 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010 CHALLENGING THE ILLEGAL AND ARBITRARY REJECTION OF GRANT OF REC APPLICATION OF THE PETITIONER BY THE RESPONDENT.
Hearing
42
137/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31/03/2019 for Asset-I: 1X160 MVA ICT-I alongwith associated bays at Daltonganj Sub-station, 1X160 MVA ICT-II alongwith associated bays at Daltonganj Sub-station and 2X132kV Line bays at Daltonganj Sub-station Asset-II: 02 Nos of 132 kV line bays at Daltonganj Sub-station under ERSS XVII Part A in Eastern Region.
Tariff order u/r 7(7) of 2014 Tariff Regulation
43
136/MP/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under Section 17 of the Electricity Act, 2003 for taking over the assets namely the Indian portion of 132kV S/C Deothang � Rangia Transmission Line and associated bays at Rangia S/S from Government of India.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
44
17/RP/2018 in 89/MP/2016
BSES YAMUNA POWER Ltd. (BYPL)
Review of the Order dated 02.11.2017 passed by this Hon?ble Commission in Petition No. 89/MP/2016 titled as ?BSES Rajdhani Power Limited & Anr. v. Pragati Power Corporation Limited & Anr.?.
Hearing
45
135/MP/2018
KUDGI TRANSMISSION LIMITED (KTL)
Petition seeking payment of transmission tariff between the date of commissioning and date of charging of Element 2 and Element 3 of transmission assets of Kudgi Transmission Limited
Hearing
46
134/MP/2018
Jindal Poly Films Limited (JPFL)
Petition under Third and Fourth Proviso to Regulation 7 (b) of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading license and other related matters) Regulations, 2009 for downgradation of the inter-state trading license from Category �I� to Category �III�
Preliminary Scrutiny
47
133/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Implementation of Regulation 30 (6) of the Central Electricity Regulatory Commission (Terms & Conditions of Tariff) Regulations, 2014.
Preliminary Scrutiny
48
132/MP/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under section 19(1)(c) of the Electricity Act, 2003 for declaration of LILO of 400 kV S/c Vindhyachal-Korba Transmission line of the Petitioner at Mahan.
Hearing
49
131/MP/2018
Sasan Power Limited (SPL)
Petition under Section 79 of the Electricity Act, 2003 read with the statutory framework governing procurement of power through competitive bidding and Power Purchase Agreement dated 07.08.2007 for (i) revision in tariff in exercise of the general regulatory powers; and (ii) compensation on account of increased cost incurred by Sasan Power Limited consequent to Procurer Event of Default.
Hearing
50
130/MP/2018
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Regulation 3(13) of CERC (Terms and Conditions of Tariff) Regulation 2014 , Regulation 111 and 115 of  the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Regulation 3(13) of the Tariff Regulations?2014 for eExtention of cut off date  of Vindhyachal Super Thermal Power Station, Stage-V (1X500MW) from  31.03.2018 to  31.03.2019.
Hearing
51
129/MP/2018
SHALIMAR VISUALS PRIVATE LIMITED (SVPL)
PETITION UNDER SECTIONS 66, 79 AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 READ WITH THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
52
128/MP/2018
North East Transmission Company Ltd. (NETC)
PETITION UNDER SECTION 79 (1) (d) READ WITH SECTIONS 62 AND 64 OF THE ELECTRICITY ACT, 2003 AND REGULATIONS 29 (A) AND 54 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014 AND REGULATION 111 OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 FOR REVISION AND ADJUSTMENT OF THE TRANSMISSION CHARGES DETERMINED BY THE HON?BLE COMMISSION VIDE ORDER DATED 16.8.2016 IN PETITION NO. 213/TT/2015
Preliminary Scrutiny
53
16/RP/2018 in 152/GT/2015
Maithon Power Limited (MPL)
Review Petition under Regulation 103 (1) of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 read with Section 94 (1)(f) of the Electricity Act, 2003 seeking review of the Order dated 26th December 2017 (?Impugned Order?) passed by this Hon?ble Commission in Petition No. 152/GT/2015 filed by MPL.
Additional information as per Interim Order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
54
127/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset -I: Combined Asset of 400kV D/C Orai-Orai (UPPTCL) line and associated bays at both ends ; 1000MVA, 765/400kV ICT-I along with associated bays at Orai(GIS) Sub-station ; 330MVAR, 765kV Bus Reactor-I along with bay at Orai Sub-station; Asset -II: 330MVAR, 765kV Bus Reactor-II along with bay at Orai Sub-station ;Asset -III: 1000MVA, 765/400kV ICT-II along with associated bays at Orai(GIS) Sub-station; Asset -IV: 765kV D/C Orai-Aligarh Line with associated bays including 240MVAR Line Reactor in both Ckt at both end; Asset -V: Combined Asset of LILO of 765kV S/C Kanpur-Jhatikara Line at Aligarh with associated bays; 330MVAR, 765kV Bus Reactor-I along with bay at Aligarh Sub-station; 330MVAR Switchable L/R in 765kV S/C Kanpur-Aligarh Line at Aligarh; Asset -VI: Combined Asset of 330MVAR, 765kV Bus Reactor-II along with bay at Aligarh Sub-station; LILO of 765kV S/C Agra-Meerut Line at Aligarh with associated bays; Asset -VII: Bay extension at Jhatikara end   to convert line reactor of 765 kV S/C Kanpur-Jhatikara TL into switchable line reactor ; Asset -VIII: Conversion of existing line reactor at Gwalior end of Satna-Gwalior Ckt-1 TL (to be LILO at Orai) in to switchable line reactor  ; Asset -IX: 765 KV D/c Jabalpur Pooling station - Orai TL along with 2*330 MVAR Line Reactor along with Bay Extension at 765/400 kV Jabalpur Pooling Station & 02 nos 765 Jabalpur Line bays along with 2*330 MVAR line reactor at Orai S/s;Asset -X: LILO of one circuit of 765 KV Satna-Gwalior TL along with 765 kV Satna Line Bay at Orai Sub Station & 240 MVAR Line Reactor at Orai S/s and 765 kV Gwalior bay at Orai S/s under �Inter-Regional System Strengthening Scheme in WR & NR (Part-B)� in Northern Region & Western Region.
Preliminary Scrutiny
55
126/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

for 3x110 MVAR Line reactor for 765kV D/C Raipur PS -  Wardha Line 1 Ckt#2 to be charged as Bus reactor at Wardha SS under Integration of Pooling stations in Chhattisgarh with central part of WR for IPP generation projects in Chhattisgarh (IPP C).
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
56
125/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Determination of Tariff for  Asset ? I 400kV DC Allahabad ? Kanpur Line along with associated bays at both ends including 2X50 MVAR Line Reactor at Kanpur end
Preliminary Scrutiny
57
124/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 220kV Kishanganga-Amargarh D/C line on M/C tower under ?Transmission system associated with Kishenganga HEP?
Preliminary Scrutiny
58
123/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
 
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
For the assets of �Transmission System associated with Sasan Ultra Mega Power Project(UMPP)�
Preliminary Scrutiny
59
122/MP/2018
Lanco Anpara Power Limited LAPL
Allow LAPL to declare 100% of it net capacity
Hearing
60
121/MP/2018
MY HOME POWER PRIVATE LIMITED (MHPPL)
Down Grading of inter state trading licence from Category II to CategoryIII
Technical Scrutiny Petitioner
61
120/AT/2018
WR-NR Power Transmission Limited (WRNRPTL)
Application under Section 63 of the Electricity Act, 2003 for Adoption of Transmission Charges with respect to the Transmission System being established by the WR-NR Power Transmission Limited  (a 100% wholly owned subsidiary of Power Grid Corporation of India Limited)
Preliminary Scrutiny
62
119/TL/2018
WR-NR Power Transmission Limited (WRNRPTL)
Application under Section 14 of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations, 2009 with respect to Transmission License to WR-NR Power Transmission Limited
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
63
118/MP/2018
TRN ENERGY PRIVATE LIMITED
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation on account of events pertaining to change in law as per the terms of Power Purchase Agreement dated 25.07.2013 (PTC-PPA) executed between the Petitioner and the Respondent No. 6 and as per the terms of the back to back Power Purchase Agreement executed by PTC with Paschimanchal Vidyut Vitran Nigam Ltd (�PaVVNL�), Purvanchal Vidyut Vitran Nigam Ltd (�PuVVNL�), Madhyanchal Vidyut Vitran Nigam Ltd (�MVVNL�), Dakshinanchal Vidyut Vitran Nigam Ltd (�DVVNL�) [hereinafter referred to as the �Procurer(s) PPA�] dated 25.07.2013.
Preparation of ROP
64
5/SM/2018
Suo Motu
Empanelment of Compliance Auditor for REC Mechanism
Preliminary Scrutiny
65
117/GT/2018
THDC India Limited (THDCIL)
Approval of Generation Tariff of Koteshwar Hydroelectric Project (KHEP) (4X100 MW) for the period from 01.04.2014 to 31.03.2019
Additional information for final order to be filed by Petitioner,Respondent
66
116/MP/2018
Maruti Clean Coal and Power Limited (MCCPL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation on account of events pertaining to change in law events.
Hearing
67
115/MP/2018
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Section 79 (1) (a) & (f) and other applicable provisions of the Electricity Act, 2003 read with Regulation 110 & 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking adjudication of dispute between the Petitioner and Respondent NTPC Ltd. regarding excess recovery of Annual Fixed Costs for various generating stations of the Respondent during FY 2014-19
Hearing
68
114/MP/2018
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Sections 79(1)(b), 79(1)(c) and 79(1)(f) of the Electricity Act, 2003, read with the relevant provisions of the IEGC, 2010 for the implementation of the order of this Hon?ble Commission in Proceeding No. L-1/219/2017/CERC dated 05.05.2017 and for seeking issuance of consequential directions to the Respondents for complying with the detailed operating procedure qua reserve shut down of the Unit(s) of the 2 x 660 MW Mahatma Gandhi Thermal Power Plant at Matenhali, Dist. Jhajjhar, Haryana.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
69
113/MP/2018
NER II Transmission Limited nerii
Petition for approval under section 17(3) & 17(4) of Electricity Act 2003, for creation of security interest over all assets including all the movable and immovable assets of the Petitioner in favour of Security Trustee/ Lenders and for any Lenders who may participate in the Facility at a future date including any subsequent transferees, assigns, novatees thereof and any refinancing lenders to the Project, acting on behalf of and for the benefit of the Lenders pursuant to draft Indenture of Mortgage, declaration and memorandum of entry and other security creating documents/Financing Documents and for future refinancing transactions also, by way of mortgage/hypothecation/assignment of Mortgaged Properties and Project Assets, for the following transmission lines ? (i) Biswanath Chariyalli (POWERGRID)- Itanagar 132 kV D/c line (ii) 2 nos. 132kV line bays at Itanagar for termination of Biswanath Chariyalli (POWERGRID)- Itanagar 132kV D/c  line (iii) LILO of one circuit of Biswanath Chariyalli (POWERGRID)- Itanagar 132kV D/c (Zebra Conductor) line at Gohpur (AEGCL) (iv) Silchar (POWERGRID)- Misa (POWERFRID) 400kV D/c (Quad) line (v) 400/132 kV, 2x315 MVA S/s at Surajmninagar (vi) 400/132 kV, 2x315 MVA S/s at P.K. Bari (vii) Surajmaninagar- P.K. Bari 400 kV D/c line  (viii) 2 no. 400 kV line bays at Palatana GBPP switchyard for termination of Palatana- Surajmaninagar 400kV D/C Line (ix) AGTPP (NEEPCO)- P.K. Bari (TSECL) 132kV D/c line with high capacity HTLS Conductor (equivalent to single moose ampacity at 85?C) (x)  2 no.s 132 kV line bays at AFTPP generation switchyard for termination of AGTPP (NEEPCO)- P.K. Bari (TSECL) 132 kV D/c line (xi) 2 no. 132 kV line bays at P.K. Bari (TSECL) S/s for termination of AGTPP (NEECO)- P.K. Bari (TSECL)) 132 kV D/c Line
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
70
112/MP/2018
bhopal dhule transmission company limited (BDTCL)
Petition for approval under section 17(3) & 17(4) of Electricity Act 2003, for creation of security interest over all assets including all the movable and immovable assets of the Petitioner No. 1 in favour of Petitioner No. 2 i.e. Debenture Trustee acting for the benefit of the Debenture Holders and for any subsequent transferees, assigns, novatees thereof pursuant to Indenture of Mortgage, and other security creating documents/financial agreements and for future refinancing transactions also, by way of mortgage/ hypothecation/ assignment of mortgaged properties and project assets, for the following transmission lines - Jabalpur-Bhopal 765 kV S/C Transmission line from Bhopal-Indore 765 kV S/C Transmission line; Bhopal-Bhopal 400 kV D/C Transmission Line; Aurangabad-Dhule 765kV S/C Transmission Line; Dhule-Vadodara 765 kV S/C Transmission Line and Dhule-Dhule 400 kV D/C Line and Substations at Dhule being implemented by Bhopal-Dhule Transmission Company Limited.
Hearing
71
111/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: ?300 MVAR STATCOM at 400kV Aurangabad substation, Asset 2: ?200 MVAR STATCOM at 400kV Gwalior Substation, Asset 3: ?300 MVAR STATCOM at 400kV Satna substation and Asset 4: ?300 MVAR STATCOM at 400kV Solapur substation under ?Installation of  STATCOMs in Western Region?.
Preliminary Scrutiny
72
110/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset ASSET-1: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Arasur Substation,  ASSET-2: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Karaikudi Substation, ASSET-3: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Tirunelveli Substation, ASSET-4: 1X500 MVA 400/230kV ICT along with associated bays and equipment at Pondicherry Substation, ASSET -5: 1X500 MVA 400/220kV ICT along with bays and equipment at Kozhikode Substation under �Augmentation of transformation capacity in Southern Region�.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
73
109/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of True up 2009-14 and tariff2014-19 of Two nos. of 63 MVAR 400 kV Line Reactor at 400kV Balia (PG) Sub-Station (Extension) (actual DOCO : 1.2.2014), under Northern region system strengthening scheme-XXIV in Northern region
Preliminary Scrutiny
74
108/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
For Transmission System Associated with NRSS-XIII in Northern Region consisting of Asset-I:400 kV D/C (Quad) Gurgaon-Manesar Transmission Line along with associated bays (DOCO 01.09.2012),Asset-II : 400/220 kV 500 MVA ICT-I at Manesar S/S along with associated bays (DOCO 01.06.2012),Asset-III: 400/220 kV 500 MVA ICT-II at Manesar S/S along with associated bays (DOCO 01.08.2012) and Asset-IV:125 MVAR Bus Reactor at Manesar (DOCO 01.10.2012).
Preliminary Scrutiny
75
107/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for communication system for DVC under Expansion/ Up gradation of SCADA/ EMS System of SLDCs of Eastern Region (BSPTCL & DVC).
Preliminary Scrutiny
76
106/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for Asset: 400kV D/C (Quad) Nabinagar-II � Gaya transmission line with 02 nos associated bays at Gaya Sub-station associated with Transmission System for Nabinagar-II TPS under Eastern Region.
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
77
105/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
IN THE MATTER OF: Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated/actual DOCOs to 31.03.2019 for Asset I: Combined asset of (a) 400 KV D/C Sasaram - Daltonganj Transmission Line alongwith 2 x 50 MVAR Line Reactors   at  Daltonganj  Sub-station; (b) 400 /220 KV, 315 MVA ICT -I  alongwith bays at Daltonganj Sub-station; (c) 400 KV 80 MVAR BR at Daltonganj Sub-station; & (d) 400 /220 KV, 315 MVA ICT -II  alongwith bays at Daltonganj Sub-station; Asset II: 04 Nos 220 KV Bays at Daltonganj Sub-station; Asset III: Provision of Circuit Breakers for making line reactors at Biharshariff Sub-station switchable; Asset IV: 01 no. 80 mVAR Bus Reactor At Duburi Sub station; Asset V: LILO of 2nd Ckt. Of 400kV D/C Jamshedpur-Rourkela TL at Chaibasa S/s (non-bussed at Chaibasa); and Asset VI: 01 No. 500MVA, 3 phase 400/220kV, Transformer (2nd) and associated bays at Pandiabilli GIS under Eastern Region Strengthening Scheme-III (ERSS-III) in Eastern Region.
Preliminary Scrutiny
78
104/MP/2018
HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED (HPSEBL)
PETITION UNDER SECTIONS 79(1)(c), 79(1)(f) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 SEEKING DIRECTIONS AGAINST THE DIRECT BILATERAL BILLING OF TRANSMISSION CHARGES BY THE RESPONDENT NO. 1, NRSS XXXI (A) TRANSMISSION LIMITED ON THE PETITIONER FOR THE TRANSMISSION SYSTEM ESTABLISHED IN THE STATE OF HIMACHAL PRADESH
Hearing
79
103/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for 2x240 MVAr Switchable Line Reactor with 950 ohms NGR at Aurangabad S/S along with associated bays - DOCO � 25.08.2017 under  �Inter-Regional System Strengthening Scheme for WR and NR (Part-A)� for tariff block 2014-19 in Western Region.
Tariff order u/r 7(7) of 2014 Tariff Regulation
80
102/TT/2018
Essar Power Transmission Company Limited (EPTCL)
Application for determination of transmission tariff (annual fixed cost) for the 2   400 kV Bays at Jhanor Gandhar GPS of NTPC Ltd which form part of the inter-state transmission system of EPTCL
Preparation of ROP
page separator
S. No.
Petition No.
Petitioner
Subject
Status
81
101/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of CERC (Terms and Conditions of Tariff) Regulations, 2009 and CERC (Terms and Conditions of Tariff) Regulations� 2014 for determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

  For the assets of �Transmission System associated with Krishnapatnam UMPP - PART B

a. covered in CERC order dated 24.11.2015 in petition no. 299/TT/2013
b. covered in CERC order dated 29.02.2016 in petition no. 96/TT/2014
Hearing
82
15/RP/2018 in 98/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review petition under Section 94 (1) (f) of the Electrcity Act, 2003
Additional information as per Interim Order to be filed by Petitioner,Respondent
83
4/SM/2018
Suo Motu
Calculation of Average Power Purchase Cost (APPC) at the national level
Preliminary Scrutiny
84
100/MP/2018
Megha Engineering & Infrastructures Ltd (MEIL)
Petition filed under Section 79(1)(f) read with Section 79(1)(k) of the Electricity Act, 2003 along with Regulation 68 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking indulgence of the Hon?ble Central Electricity Regulatory Commission to direct NTPC Vidyut Vyapar Nigam Limited to comply with the Order dated 11.10.2017 in Petition No. 16/MP/2014 by computing the delay suffered by the Generation Project due to force majeure eventualities and revise the Schedule Commercial Operation Date for the Generation Project.
Hearing
85
99/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations?  2014 for  determination of  (i) Truing up Transmission tariff for 2009-14 tariff  block and (ii) Transmission tariff for 2014-19  tariff block For (a) Kalpakkam PFBR-Sirucheri 230 kV D/C Line (b) Kalpakkam PFBR-Arani 230 kV D/C Line under Transmission System associated with Kalpakkam PFBR (500 MW) in Southern Region.
Hearing
86
98/MP/2018
ONGC Tripura Power Company (OTPC)
Request for Extension of Cut-off Date for Project due to delay in civil works of plant township
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
87
96/MP/2018
MB Power (Madhya Pradesh) Limited (MBPMPL)
Petition under Section 79 (1) (c), Section 79 (1) (f) and Section 79 (1) (k) of the Electricity Act, 2003 read with the Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium term Open Access in inter-state transmission and related matters) Regulations, 2009 along with Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 seeking directions against Power Grid Corporation of India Limited for (i) payment of amounts due to the Petitioner in compliance of the Order dated 15.12.2017 of this Hon�ble Commission in Petition No. 141/TT/2015; and (ii) return of Bank Guarantee of INR 60 Crores furnished as per the extant regulations r/w the Transmission Agreement dated 14.06.2010 and Long Term Access Agreement dated 17.06.2011.
Hearing
88
97/AT/2018
Goa-Tamnar Transmission Project Limited (GTTPL)
Application under Section 63 of the Electricity Act, 2003 and Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of Transmission License and other related matters) Regulations, 2009 for Adoption of Transmission charges with respect to Transmission System being established by Goa Tanmar Transmission Project Limited.
Preparation of ROP
89
95/TL/2018
Goa-Tamnar Transmission Project Limited (GTTPL)
Application under Section 14 read with Section 15(1) of the Electricity Act, 2003 and Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of Transmission License and other related matters) Regulations, 2009 for grant of Transmission License to Goa Tanmar Transmission Project Limited.
Preparation of ROP
90
94/TL/2018
Fatehgarh-Bhadla Transmission Limited (FBTL)
Application under Section-14, 15, 79(1)(e) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations, 2009 with respect to Grant of Transmission License to Fatehgarh-Bhadla Transmission Limited
Interim order under preparation
91
93/AT/2018
Fatehgarh-Bhadla Transmission Limited (FBTL)
Application under Section-63 of the Electricity Act, 2003 for Adoption of Transmission Charges with respect to the Transmission System being established by Fatehgarh - Bhadla Transmission Limited
Preparation of ROP
page separator
S. No.
Petition No.
Petitioner
Subject
Status
92
92/MP/2018
Shiga Energy Private Limited (SEPL)
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter-alia, seeking a direction to Respondent No. 1 to pay a sum of Rs. 112.39 crores, being the financial loss suffered by the Petitioner, on account of delay in commencement of the Long Term Access granted to the Petitioner, due to delay in implementation of the Transmission system falling in the scope of Respondent No. 1?s obligations, along with interest on the same till the date of payment of the amount by Respondent No. 1 to the Petitioner.
Hearing
93
91/MP/2018
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79(1)(b) read with Section 79(1)(f) and other applicable provisions of the Electricity Act, 2003 seeking adjudication of disputes and differences under the Power Purchase Agreement dated 31.07.2012 as amended on 19.12.2014 and 23.01.2018 in regard to non-payment of tariff and unilateral deduction of the monthly energy bills of the Petitioner by the Respondents
Hearing
94
90/MP/2018
RAPP Transmission Company Limited (RTCL)
Petition under Section 142 and Section 146 of the Electricity Act, 2003 against Nuclear Power Corporation of India Limited?s willful, deliberate, contumacious and continuous non-compliance of this Hon?ble Commission?s Order in Petition No. 43/MP/2016 dated 21.09.2016
Hearing
95
89/MP/2018
ARAVALI POWER COMPANY PRIVATE LIMITED (APCPL)
Petition for revision of the Normative Annual Plant Availability Factor
Hearing
96
88/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding ("Competitive Bidding Guidelines") and (a) PPA dated 17.03.2010 between Maharashtra State Electricity Distribution Company Ltd. and EMCO Energy Limited
Hearing
97
87/MP/2018
M.R. Industries (MRIndustries)
ACCESS IN INTER-STATE TRANSMISSION) REGULATIONS, 2008, FURTHER READ WITH REGULATION 4 OF THE RERC (INTRA-STATE ABT) REGULATIONS, 2006AND REGULATION 4.2 OF THE STATE GRID CODE SEEKING DIRECTIONS FOR PREPARATION OF UI ACCOUNT FOR UNDER-DRAWAL AGAINST COLLECTIVE TRANSACTIONS WITHIN SPECIFIED TIME AND FOR PAYMENT OF UI CHARGES
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
98
14/RP/2018 in 114/MP/2017
Gati Infrastructure Pvt. Ltd.
A Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) Regulations, 1999 seeking review/ modification of the order dated 22.06.2017 passed by this Hon�ble Commission in Petition No. 114/MP/2017 in the matter of transmission capacity allocation to the generating projects in Sikkim qua Teesta-V- 400 kV line i.e. Rangpo - Siliguri 400kV D/c line Inter State Transmission System of Powergrid Corporation of India Limited pending the construction and completion of the Teesta III -  Kishanganj 400kV D/C quad-moose line by Teesta Valley Power Transmission Limited
Reply / additional information as per ROP to filed by Petitioner,Respondent
99
83/TD/2018
Jammu And  Kashmir  State  Power  Development  Corporation  Limited (JKSPDCLtd)
Application for grant of Inter State Trading License
Preliminary Scrutiny
100
82/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Asset-I:- LILO of 220 kV Tanakpur-Bareilly Transmission Line (Ckt-II) at Sitarganj along with associated bays (DOCO: 01.03.2009), Asset-II:- 220/132, 100 MVA ICT-I at Sitarganj along with associated bays (DOCO: 01.03.2009), Asset-III:- 220/132, 100 MVA ICT-II at Sitarganj along with associated bays (DOCO: 01.08.2009), Asset-IV:- 220/132, 100 MVA ICT-I at Pithoragarh along with associated bays (DOCO: 01.09.2010), Asset-V:- 220/132, 100 MVA ICT-II at Pithoragarh along with associated bays (DOCO: 01.12.2010), Asset-VI:- LILO of one circuit of Dhauliganga- Bareilly Transmission Line at Pithoragarh along with associated bays (DOCO: 01.08.2010) associated with �System Strengthening Scheme in Uttaranchal� in Northern Region.
Additional information for final order to be filed by Petitioner,Respondent
101
81/MP/2018
Western Regional Load Despatch Centre (WRLDC)
Application for approval of performance linked incentive for WRLDC for the financial year 2016-17 with reference to WRLDC Charges
Hearing
102
80/MP/2018
North Eastern Regional load despatch Centre (NERLDC)
Application for approval of Performance Linked Incentive for NERLDC for the financial year 2016-17 with reference to NERLDC Charges for the control period 1.4.2014 to 31.3.2019
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
103
79/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations, 2009 and CERC (Terms and Conditions of Tariff) Regulations� 2014 for determination of

a. Truing up Transmission tariff for 2009-14 tariff  block and 
b. Transmission tariff for 2014-19  tariff block 

for Asset A:  3x110 MVAR Switchable Line Reactor to be charged as Bus Reactor-1 at 765/400 kV Wardha SS,  Asset B: 3x110 MVAR Switchable Line Reactor to be charged as Bus Reactor 2 at 765/400 kV Wardha SS,  Asset C: 3x80 MVAR 765 kV Line reactor for 765 kV D/C Wardha-Aurangabad Line 1 Ckt#1 to be used as Bus Reactor at Aurangabad S/s, Asset D: 3x80 MVAR 765 kV Bus Reactor at Aurangabad S/S and Asset E: 765/400 kV 1500 MVA ICT-2 at Aurangabad S/S  under �Transmission System Strengthening in Western part of WR for IPPs generation projects in Chhattisgargh (IPP D)� in Western Region.
Additional information for final order to be filed by Petitioner,Respondent
104
78/MP/2018
DAMODAR VALLEY CORPORATION (DVC)
Unilateral Surrender of 400 MW Power by MPPMCL from MTPS & CTPS of DVC in violation of provision of PPA
Reply / additional information as per ROP to filed by Petitioner,Respondent
105
77/MP/2018
TRN ENERGY PRIVATE LIMITED
Petition under Section 79 (1) (b) read with Section 79(1) (f) of the Electricity Act, 2003
seeking directions for applicability of the provisions of PTC-PPA signed between
Petitioner & the Respondent No.6 and Procurer�s PPA signed between Respondent
No.6 & Respondent No. 1 to 5, both dated 25.07.2013 for the purposes of calculation of
Penalties due to less than 80% availability for a Contract Year.
Hearing
106
76/MP/2018
BHILANGAHA HYDRO POWER LIMITED (BHPL)
PETITION UNDER REGULATION 14,5 (3) & (4) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010.
Hearing
107
75/MP/2018
OLAM AGRO INDIA PVT. LTD.
Petition seeking directions against National Load Dispatch Centre in the matter of issuance of Renewable Energy Certificates to the Petitioner for the specified period
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
108
74/MP/2018
SJVN Limited
Consideration of declared capacity of Nathpa Jhakri Hydro Power Station (6 x 250 MW) and Rampur Hydro Power Station (6 x 68.67 MW) corresponding to Installed capacity including  overload capacity in accordance with Regulation 6.5(12) of CERC (Indian Electricity Grid Code) Regulations, 2010
Preparation of ROP
109
73/MP/2018
Sneha Kinetic Power Projects Pvt. Ltd (SKPPPL)
Petition under Section 79 (1) (f) and (c) and other applicable provisions of the Electricity Act, 2003 read with Regulation 12 of Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014, against the arbitrary acts and omissions of Teestavalley Power Transmission Limited.
Hearing
110
72/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding ("Competitive Bidding Guidelines") and (a) Article 10 of the PPA dated 09.11.2011 between GMR Kamalanga Energy Ltd. and Bihar State Electricity Board and (b) Article 13 of the PPA dated 12.03.2009 between GMR Energy Ltd. (on behalf of GMR Kamalanga Energy Limited) and PTC India Ltd. with back to back PPA between PTC India Ltd. and Haryana Distribution companies, for compensation due to Change in Law
Hearing
111
71/MP/2018
GMR  WARORA ENERGY LIMITED (GMRWEL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding ("Competitive Bidding Guidelines") and (a) Article 10 of the PPA dated 17.03.2010 between Maharashtra State Electricity Distribution Company Ltd. and EMCO Energy Limited; (b) Article 10 of the PPA dated 21.03.2013 between Electricity Department of Union Territory of Dadra and Nagar Haveli and EMCO Energy Limited and (c) Article 10 of the PPA dated 27.11.2013 between GMR Energy Trading Limited and the Tamil Nadu Generation and Distribution Corporation Limited through EMCO Energy Limited.
Hearing
112
70/MP/2018
Godavari Biorefineries Limited (GBL)
Petition is filed praying for a direction from this Hon'ble Commission to the Respondent to refund the Back Up Supply Charges collected from the Petitioner, during the course of grant of Inter State Open Access to the Petitioner, ny contravening and violating Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008.
Hearing
113
69/MP/2018
Amplus Energy Solutions Private Limited
Miscellaneous Petition
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
114
68/MP/2018
NTPC Tamil Nadu Energy Company Limited (NTECL)
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and with Regulations 36 & 54 of CERC (Terms and Condition of Tariff) Regulation, 2014 for Revision  of NAPAF for Vallur Thermal Power Station (3X500MW) for the period from 01.04.2017 to 31.03.2019.
Hearing
115
67/MP/2018
NTPC Tamil Nadu Energy Company Limited (NTECL)
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and with Regulation 54 of CERC (Terms and Condition of Tariff) Regulation, 2014 for Relaxation of cut off date of Vallur Thermal Power Station (3X500MW)
Hearing
116
3/SM/2018
Suo Motu
Non-compliance of the Central Electricity Regulatory Commission (Payment of Fees) Regulations, 2012.
Interim order issued
117
13/RP/2018 in 187/MP.2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) regulations, 1999 for review of the Order dated 11.10.2017 passed by the Hon?ble Commission in Petition No. 187 / MP / 2015
Hearing
118
2/SM/2018
Suo Motu
Levellised Generic Tariff for RE Technologies for Second Year of Control Period (2018-19) based on Central Electricity Regulatory Commission (Terms and Condition for Tariff determination from Renewable Energy Sources) Regulations, 2017
Preliminary Scrutiny
119
65/TD/2018
NTPC Limited
PETITION FOR TRADING LICENSE
Preparation of ROP
page separator
S. No.
Petition No.
Petitioner
Subject
Status
120
64/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff block and 
(ii) Transmission tariff for 2014-19 tariff block 

For Transmission System Associated with System Strengthening in NR for Sasan and Mundra UMPP in Northern Region consisting of Asset-I:  400 KV Agra-Sikar (D/C QUAD) Line with associated Bays at Agra  (DOCO: 01.01.2014) ;Asset-II :  2 nos. 400 kV line bays for 400 kV D/C Agra-Sikar line including 2 nos. 50 MVAR Line Reactors under Bus Reactor operation mode at 400/220 kV Sikar Sub-station (DOCO: 01.08.2013).
Additional information for final order to be filed by Petitioner,Respondent
121
63/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset: 02 nos of 400 kV bays at Purulia S/S under Eastern Region Strengthening Scheme VII (ERSS VII) in Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
122
62/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 400 kV D/C Kishenpur- New Wanpoh Line alongwith associated bays at both ends under ?Northern Region System Strengthening Scheme XVI? in Northern Region.
Preliminary Scrutiny
123
61/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of    Transmission Tariff from DOCO to 31.03.2019 Asset-I: 2 nos. 400 kV Malerkotla Bays at 400/220 kV GIS Substation at Kurukshetra under ?Provision of 400kV bays for lines under Northern Region System Strengthening Scheme-XXXI(Part-B)?.
Preparation of ROP
page separator
S. No.
Petition No.
Petitioner
Subject
Status
124
60/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 
For Asset :- 400 kV D/C Kishenpur-Samba T/L alongwith bays at both ends, 01 no. 315 MVA,400/220 kV ICT-I alongwith associated bays at Samba and 03 nos 220 kV Line bays (DOCO : 01.04.2013)  under Northern Region Strengthening Scheme -XXII in Northern Region.
Order reserved
125
59/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset-I: LILO of both Circuit of 400 kV D/C Rourkela-Raigrah (02nd Line) alongwith 04 Nos of 400 kV Line bays at Jharsuguda (Sundargarh) Substation; Asset-II: Split Bus arrangement at 400 kV Bus at Jharsuguda  (Sundargarh) Substation and Asset-III: 02 Nos of 400 kV Line bays for termination of OPGC (IB TPS) - Jharsuguda 400 kV D/C line (Under TBCB) at Jharsuguda (Sundargarh) under work associated with common transmission system for Phase-II Generation project in Odisha under Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
126
58/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 400Kv D/C (Quad) Kurukshetra-Jind TL alongwith associated bays under ?Transmission System Strengthening in WR-NR Transmission Corridor for IPPs in Chhattisgarh?.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
127
57/MP/2018
SOUTHERN REGIONAL LOAD DESPATCH CENTRE (SRLDC)
PLI petition for 2016-17 SRLDC
Hearing
128
56/MP/2018
Northern Regional Load Desptach Centre (NRLDC)
Submission under sub-section (4) of section 28 of Electricity Act 2003 read with Regulation 6 & Regulation 29 of Central Electricity Regulatory Commission (Fees & charges of Regional Load Despatch Centre and other related matters) Regulations, 2015 for approval of Performance Linked Incentive for NRLDC for the financial year 2016-17 with reference to NRLDC Charges for the control period 1.4.2014 to 31.3.2019.
Hearing
129
55/MP/2018
EASTERN REGIONAL LOAD DESPATCH CENTRE (ERLDC)
Application for approval of Performance Linked Incentive for ERLDC for the financial year 2016-17 with reference to ERLDC Charges for the control period 1.4.2014 to 31.3.2019.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
130
54/MP/2018
Neyveli Lignite Corporation Ltd (NLC)
NLCIL- BTPS (Barsingsar Thermal Power station)� Non Implementation of ABT from COD - Consequential short admittance of bills by Rajasthan Discoms despite NLCIL efforts for resolution�Miscellaneous Petition for adjudication   -  submitted - Reg.
Hearing
131
12/RP/2018 in 203/MP/2015
GMR Kamalanga Energy Limited (GKEL)
Review of Order Dated 203/MP/2015
Hearing
132
53/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 06 Nos of Link under central sector (562.873) Asset-II: 07 Nos of OPGW links (664.53 Km) and Asset-III: 07 Nos links under Central Sector (1076.57 km) under central sector under the project Fibre Optic communication system in ER under Expansion of wide-band communication network in Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
133
52/MP/2018
Azure Power Venus Private limited (Azurevenus)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 21.10.2016 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central and State levels, resulting in additional recurring and non-recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Hearing
134
50/MP/2018
Prayatna Developers Private Limited (PDPL)
Petition under Section 79 of the Electricity Act, 2003 read with Article 12 of the Power Purchase Agreements dated 16.09.2016 executed between the Petitioner and NTPC Ltd., for seeking approval of Change in Law events due to enactment of the GST Laws.
Hearing
135
49/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I: 400kV Transmission Line for Swapping of Kahalgaon # 1 bay with Sasaram # 1 bay at Biharsharif Sub-station; Asset II: 400KV Transmission Line for Swapping of Purnea(1&2) Bays with Sasaram bays(3&4) at Biharsharif Sub-station and Asset III: Split Bus arrangement with tie line Breaker for 400KV Biharsharif Sub-station under Split Bus arrangement for various substations in Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
136
11/RP/2018 in 88/TT/2017
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED (MPPTCL)
Petition for review the Order dated 19.12.2017 passed by the Hon�ble Commission in Petition No 88/TT/2017
Hearing
137
10/RP/2018 in 039/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for Review of Order dated 12.12.2017 passed in Petition No. 39/TT/2015 under Section 94 of the Electricity Act, 2003
Hearing
138
48/TD/2018
Neyveli Lignite Corporation Ltd (NLC)
Application under sub-section (1) of Section 15 of Electricity Act 2003 seeking grant of an interstate trading licence.under section 14 (c) of Electricity Act 2003  read with CERC (Procedure, Terms and Conditions for grant of trading licence and other related matters) Regulations, 2009 and its amendments.
Additional information for final order to be filed by Petitioner,Respondent
139
47/MP/2018
Azure Power Thirty Six Private  Limited (Azure36)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreement executed by the Petitioner and Solar Energy Corporation of India Limited dated 26.09.2016 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central and State levels, resulting in additional recurring and non-recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreement.
Hearing
140
46/MP/2018
NTPC Limited
Petition for revision of  the Normative Annual Plant Availability Factor in respect of NTPC?s Power Stations on account of shortage of coal availability.
Reply / additional information as per ROP to filed by Petitioner,Respondent
141
45/MP/2018
Power System Operation Corporation Ltd (POSOCO)
Application for approval of Performance Linked Incentive for NLDC for the financial year 2016-17 with reference to NLDC Charges for the control period 1.4.2014 to 31.3.2019.
Hearing
142
9/RP/2018 in MP/069/2014
Aryan M.P. Power Generation Private Limited AMPPGPL
A Petition under Section 94(1)(f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) Regulations, 1999 seeking review of the Order dated 31.10.2017 passed by this Hon�ble Commission in Petition No. 69/MP/2014 in the matter of relinquishment of the Long Term Open Access under the Bulk Power Transmission Agreement dated 29.07.2009, under Regulation 18 read with 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in Inter-State Transmission and related matters) Regulations, 2009
Hearing
143
44/TD/2018
Refex Energy Limited (REL)
Application for grant of trading license under section 14 of the Electricity Act, 2003
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
144
43/GT/2018
NHPC LTD
Petition under Regulation 79(1) & 86 of CERC (Conduct of Business) Regulations, 1999, Section 62(1) (a) of the Electricity Act, 2003 and Regulation- 6 (1) (ii), 7(1) & 14(1) of CERC (Terms and Conditions of Tariff) Regulations, 2014 for approval of generation tariff of Kishanganga HE Project (330 MW) for the period 31.01.2018 (Anticipated COD of Unit#1&2) to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
145
40/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: 2 Nos 400kV line Bays at Parli(POWERGRID) Switching Station  (for Parli new(TBCB)-Parli(POWERGRID) 400kV D/C(Quad) line under TBCB) and Asset-2: 2 Nos 765kV line Bays at Solapur(POWERGRID)  Station  (for Parli new(TBCB)-Solapur(POWERGRID) 765kV D/C line under TBCB route) under �POWERGRID works associated with Western Region Strengthening Scheme XV� for tariff block 2014-19 period.
Hearing
146
8/RP/2018 in 55/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the order dated 30.11.2017
passed by this Hon'ble Commission in Petition No. 55/TT/2017.
Order reserved
147
38/MP/2018
NTPC Limited
Extention of cut off date  of Mauda Super Thermal Power Station, Stage-I (2X500MW) from  31.03.2017 to  31.03.2019.
Hearing
148
37/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from Anticipated DOCO to 31.03.2019 for Asset 1 : 1 x 500MVA, 400/220kV ICT along with associated transformer bays & 220kV line bays at Itarsi substation under Western Region System Strengthening Scheme-XIV
Hearing
149
36/MP/2018
RANA SUGARS LIMITED RSL
Issuance of Pending RECs and Re-accreditation of project under the REC mechansim
Hearing
150
7/RP/2018 in 60/TT/2017
NRSS XXXI (B) Transmission Limited NRSSXXXIB
Review Petition under Section 94 (1) (f) of the Electricity Act, 2003 r/w Order 47 Rule 1 of the Code of Civil Procedure, 1908 and Regulation 103 (1) of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for seeking review of CERC order dated 30.11.2017 passed in Petition No. 60/TT/2017
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
151
6/RP/2018 in 208/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Review Petition under section 94(1)(f) of the Electricity Act, 2003 for review and modification of the final order dated 22.11.2017 passed by this Hon'ble Commission in Petition No. 208/TT/2016.
Order reserved
152
35/MP/2018
GMR Kamalanga Energy Limited (GKEL)
Petition under Section 79 (1) (f) read with CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 seeking refund of the POC charges for 260 MW in Eastern Region granted under the Bulk Power Transmission Agreement dated 01.07.2016.
Hearing
153
34/MP/2018
Azure Power Jupiter Private Limited (AzureJupiter)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Limited dated 29.04.2016 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central and State levels, resulting in additional recurring and non-recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Hearing
154
33/MP/2018
ACME Jaipur Solar Power Private Limited (AJSPPL)
A Petition under Section 79(1)(b) of the Electricity Act, 2003 seeking relief on account of �Change in Law� and consequent revision in capital cost due to introduction of the Central Goods and Services Tax Act, 2017 promulgated by the Department of Revenue, Ministry of Finance notified by way of notification dated 28.06.2017.
Hearing
155
32/MP/2018
Neyveli Lignite Corporation Ltd (NLC)
NLCIL- Mines�increase in O&M Expenses on account of Wage revision and other pay hikes to Employees (Non- Executives & workmen) of NLCIL�s Mines wef 01.01.2012 - recovery from the beneficiaries of NLCIL Power Stations for the year  2012-14- Miscellaneous petition submitted
Preparation of ROP
156
31/MP/2018
Neyveli Lignite Corporation Ltd (NLC)
NLCIL-Thermal �increase in O&M Expenses on account of Wage revision and other pay hikes to Employees (Non- Executives & workmen) of NLCIL�s Power Stations wef 01.01.2012 - recovery from the beneficiaries of NLCIL Power Stations for the year  2012-14- Miscellaneous Petition- Submitted -Reg.
Preparation of ROP
page separator
S. No.
Petition No.
Petitioner
Subject
Status
157
30/MP/2018
Adani Green Energy (MP) Limited (AGEMPL)
Petition under Section 79 (1) (c) and (f) and other applicable provision of the Electricity Act, 2003 read with Regulation 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in the inter-State transmission and related matters) Regulations, 2009 against the letter dated 22.11.2017 of the Respondent, wrongly denying the use of connectivity granted to M/s AGEL (Petitioner�s parent company) at Khavda, by the Petitioner�s proposed wind project at Dayapar in Kutch District of Gujarat.
Reply / additional information as per ROP to filed by Petitioner,Respondent
158
29/MP/2018
INOX WIND INFRASTRUCTURE SERVICES LIMITED (IWISL)
Seeking Facilitation and long term open access to the SPV incorporated by the Petitioner to implement the wind power projects awarded to it under the scheme of Government of India (Ministry of New and Renewable Energy) dated 28.10.2016 for setting up of 1000 MW ISTS Connected Wind Power Projects.
Hearing
159
28/MP/2018
East North Interconnection Company Limited (ENICL)
Petition under Sections 61, 63 and 79 of the Electricity Act, 2003 read with the statutory framework and Article 12 of the Transmission Service Agreement dated 10.08.2009 executed between East North Interconnection Company Limited and its Long-Term Transmission Customers for claiming compensation due to Changes in Law.
Hearing
160
27/MP/2018
Krishna Windfarms Developers Private Limited (KWFDPL)
Petition under Section 79 (1) (f) read with Section 79 (1) (b) of the Electricity Act, 2003 in relation to the disputes arising out of the Power Purchase Agreement dated 03.08.2016 between Petitioner herein i.e. Krishna Windfarms Developers Private Limited and Solar Energy Corporation of India Limited.
Hearing
161
25/TT/2018
ODISHA POWER TRANSMISSION CORPORATION LIMITED (OPTCL)
Petition for approval of Tariff for inclusion of Transmission Assets in Computation of Point of Connection (PoC) Charges and Losses as per Hon�ble Commission�s order dated 12.05.2017 in Petition No. 07/SM/2017 for inclusion in PoC charges in accordance with Central Electricity Regulatory Commission (Sharing of Inter-state Transmission Charges and Losses) Regulations, 2010 and amendments made thereto.
Order reserved
162
24/TT/2018
Karnataka Power Transmission Corporation Limited KPTCL
Approval under Regulation 86 of CERC (Conduct of business) Regulation, 1999 for determination of Tariff for Transmission Lines connecting between Karnataka and other neighboring states
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
163
23/MP/2018
nrssxxix transmission company limited (NRSSXXIX)
Petition under Section 79(1)(c), Section 18 and Section 17(3) of the Electricity Act, 2003 and invoking all other enabling powers of the Hon?ble Central Electricity Regulatory Commission permitting the amendment of the Transmission License dated 14.11.2014 granted to the NRSS XXIX Transmission Limited for establishing Transmission System for Northern Region System Strengthening Scheme NRSS-XXIX on Build, Own, Operate and Maintain basis and accordingly allowing carving out of Jalandhar ? Samba transmission line from the purview of the aforesaid Transmission License and to vest the same into the favour of a separate entity i.e. NRSS XXIX (JS) Transmission Limited.
Hearing
164
22/MP/2018
Mirra and Mirra Industries (MMI)
PETITION UNDER SECTIONS 66, 79 AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 READ WITH THE CENTRAL ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR RECOGNITION AND ISSUANCE OF RENEWABLE ENERGY CERTIFICATE FOR RENEWABLE ENERGY GENERATION) REGULATIONS, 2010
Hearing
165
5/RP/2018 in 70/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the order dated 21.11.2017
passed by this Hon'ble Commission in Petition No. 70/TT/2017.
Additional information as per Interim Order to be filed by Petitioner,Respondent
166
19/MP/2018
TALETTUTAYI SOLAR PROJECTS FOUR PVT. LTD TT4
MEMORANDUM OF ORIGINAL PETITION FILED UNDER SECTION 79 (1) (f) OF THE ELECTRICITY ACT, 2003 (�THE ACT�) AND THE OTHER APPLICABLE PROVISIONS OF THE ACT IN RELATION TO THE DISPUTES HAVING ARISEN UNDER THE POWER PURCHASE AGREEMENT DATED APRIL 11, 2016 BETWEEN THE PARTIES
Hearing
167
4/RP/2018 in MP/419/2014
RAICHUR SHOLAPUR TRANSMISSION COMPANY PRIVATE LIMITED (RSTCPL)
REVISION PETITION ON BEHALF OF RAICHUR SHOLAPUR TRANSMISSION COMPANY LIMITED FOR REVIEW OF THE ORDER DATED 27.06.2016 PASSED BY THE CENTRAL ELECTRICITY REGULATORY COMMISSION IN PETITION NO.419/MP/2014 UNDER REGULATION 103(1) OF THE CENTRAL ELECTRICITY REGULATORY COMMISSION (CONDUCT OF BUSINESS) REGULATIONS, 1999 PURSUANT TO THE ORDER DATED 01.12.2017 PASSED BY THE HON�BLE APPELLATE TRIBUNAL FOR ELECTRICITY IN APPEAL NO.193/ 2016.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
168
3/RP/2018 in 32/MP/2017
Himachal Sorang Power Private Limited (HSPPL)
Review Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of CERC (Conduct of Business) Regulations, 1999 for Reviewof Impugned Order dated 26.09.2017 passed by the Hon?ble Commission in Petition No. 32/MP/2017
Hearing
169
2/RP/2018 in 87/TT/2017
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED (MPPTCL)
Transmission tariff for the transmission lines belonging to the Petitioner (MPPTCL) conveying electricity as deemed ISTS lines, in continuation to the Hon?ble Central Electricity Regulatory Commission?s order dated 15.10.2015 under Petition No. 217/TT/2013 for inclusion of 2 nos. 400 kV lines in computation of point of connection transmission charges in accordance with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 and (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010 namely, 400 kV Seoni (MP)-Sarni (MP) line and 400 kV Seoni (MP)-Bhilai (Chattisgarh) line
Hearing
170
18/MP/2018
Adani Green Energy Limited (AGEL)
Petition under Section 79 (1) (c) and (f) and other applicable provision of the Electricity Act, 2003 read with Regulation 32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in the inter-State transmission and related matters) Regulations, 2009 against the action of the respondent in threatening to cancel the open access and encashment of bank guarantee.
Hearing
171
17/MP/2018
NTPC Vidyut Vyapar Nigam Limited (NVVN)
PETITION UNDER SECTION 79 (1) (f) READ WITH SECTION 79 (1) (a) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES BETWEEN THE PETITIONER AND THE RESPONDENTS 1 TO 3
Hearing
172
16/MP/2018
Tadas Wind Energy Private Limited (TWEPL)
Petition under Regulation 5 Read with Regulations 14 & 15 of the Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 seeking directions for Re- registration of the Petitioner under the Renewable Energy Certificate Mechanism
Reply / additional information as per ROP to filed by Petitioner,Respondent
173
1/SM/2018
Suo Motu
Addional tax burden on transmision licensees on introduction of goods and service tax compensation cess.
Additional information as per Interim Order to be filed by Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
174
15/GT/2018
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter �V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of tariff of Tuirial Hydro Electric Power Plant (TrHEP) ( 2 X 30 = 60 MW) for the period from COD to 31.03.2019
Order reserved
175
14/MP/2018
Western Transco Power Limited (WTPL)
Petition under Section 17, read with Section 79(1)(c) of the Electricity Act, 2003 for creation of security interest by Western Transco Power Limited (�Petitioner�/�Borrower�) in favour of SBICAP Trustee Company Limited, acting on behalf of IDFC Bank Limited IDFC Infrastructure Finance Limited, and seeking approval of substitution of lenders, namely, L&T Infra Debt Fund Limited, Indusind Bank Limited & India Infrastructure Finance Company Limited, with IDFC Bank Limited and IDFC Infrastructure Finance Limited
Order reserved
176
13/MP/2018
Azure Power Thirty Seven Private Limited (APTSPL)
Petition under Section 79 of the Electricity Act, 2003 and Article 12 read with Article 16.3.1 of the Power Purchase Agreements executed by the Petitioner and NTPC Limited dated 10.08.2016 seeking relief on account of a 'Change in Law' viz. the introduction of Goods and Services Tax laws at the Central and State levels, resulting in additional recurring and non-recurring expenditure in the form of an additional tax burden to be borne by the Petitioner after the Effective Date of the Power Purchase Agreements.
Hearing
177
12/MP/2018
RAICHUR SHOLAPUR TRANSMISSION COMPANY PRIVATE LIMITED (RSTCPL)
Application under Section 17(3) and Section 17 (4) of the Electricity Act, 2003.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
178
11/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1-SCADA/EMS systems for Main and backup SLDC of Chhattisgarh (CSPTCL), Asset-2-SCADA/EMS systems for Main and backup SLDC of Goa Electricity Department (GED), Asset-3-SCADA/ EMS system upgradation of Main and backup SLDCs and Sub-LDCs of Gujarat (GETCO), Asset-4-SCADA/EMS system upgradation of Main and backup SLDCs and Sub-LDCs of Madhya Pradesh (MPPTCL), Asset-5- SCADA/EMS system upgradation of Main and backup SLDCs of Daman and Diu (DDED) and Asset-6- SCADA/EMS system upgradation of Main and backup SLDCs and Sub-LDCs of Dadar and Nagar Haveli (DNHED) under �Expansion/ Upgradation of SCADA/EMS system at SLDC of Western Region� for the period 2014-19 block.
Additional information for final order to be filed by Petitioner
179
1/RP/2018 in 128/MP/2016
M.P. Power Management Co. Ltd. (MPPMCL)
Review Application for rectification of the order dated 12.10.2017 in petition no. 128/MP/2016
Hearing
180
9/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

 For the assets of �Transmission System of Vindhyachal -IV & RIHAND - III {1000MW} Generation Project 

a. covered in CERC order dated 04.09.2014 in petition no. 86/TT/2012
b. covered in CERC order dated 18.03.2016 in petition no. 113/TT/2013
c. covered in CERC order dated 17.07.2015 in Petition no. 295/TT/2013
d. covered in CERC order dated 31.12.2015 in Petition no. 192/TT/2014
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
181
8/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-1: Main SCADA EMS System of SLDC of Manipur (DOCO-09.11.2016), Asset-2: Main SCADA EMS System of SLDC of Mizoram (DOCO-10.04.2017), Asset-3: Main SCADA EMS System of SLDC of Arunachal Pradesh (Anticipated DOCO-15.11.2017) and Asset-4: Main SCADA EMS System of SLDC of Nagaland (Anticipated DOCO-30.11.2017) under project ? ?Expansion/ Upgradation of SCADA/ EMS System of SLDCs of North Eastern Region? for the period 2014-19 block.
Hearing
182
7/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for Asset 1: LILO of Vindhyachal-Jabalpur 400 kV 2nd D/C line (Ckt3&4) along with associated bays and equipments at 400/220kV  Rewa Pooling Station under Transmission System for Ultra Mega Solar Park (750MW) in Rewa District, Madhya Pradesh in Western Region.
Reply / additional information as per ROP to filed by Petitioner,Respondent
183
6/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Determination of Tariff for Asset : 400/220 kV New Wanpoh Substation: (+) 300 MVAR / (-) 200 MVAR SVC Under ?Static VAR    Compensators (SVCs) in Northern Region?.
Additional information for final order to be filed by Petitioner,Respondent
184
5/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Establishment of Fibre Optic Communication System under Master Communication Plan in Western Region
Hearing
185
4/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval of Tariff for NRSS XXIX
Additional information for final order to be filed by Petitioner
186
3/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations �1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 �Bunching of Tirunelveli � Edamon section of the Tirunelveli � Muvathapuza (Cochin) 400kV quad D/c line initially(and temporarily) at 220kV with existing  Tirunelveli � Edamon 400kV twin D/c line (400KV line charged at 220Kv) under Transmission System associated with Kudamkulam Atomic Power Project�  in Southern Region..
Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
187
2/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset �ASSET- 1A: LILO of 400KV D/C Gooty-Tumkur (Vasantnarsapur) D/C line at Tumkur (Pavagada) pooling station, ASSET- 1B: New 400/220KV pooling station at Tumkur (Pavagada) with 1 X 500MVA 400/220KV ICT and 1x 125MVAR Bus reactor and along with associated bays & equipment's, ASSET- 2: LILO of 400KV D/C Bellary -Tumkur (Vasantnarsapur) D/C (Quad Moose) TL at Tumkur (Pavagada) pooling station along with associated bays & equipment�s,  ASSET - 3: 2 X 500MVA 400/220KV ICTs along with associated bays & equipment�s and ASSET�4: Tumkur (Pavagada) pool-Hiryur 400KV D/C line along with associated bays & equipments at both ends under Transmission System for Ultra mega Solar Power Park at Tumkur (Pavagada), Karnataka-Phase-I�.
Reply / additional information as per ROP to filed by Petitioner,Respondent
188
1/TT/2018
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of Transmission Tariff for Asset-I: (i) 132kVS/C (on D/C Tower) Pasighat�Roing Transmission Line alongwith associated bays at Pasighat and Roing S/s, (ii) 3x5 MVA (132/33kV), 1-ph, ICT-I alongwith associated bays at Roing, (iii) 4x5 MVA (132/33kV), 1-ph, ICT-II alongwith associated bays at Roing, (iv) 4x6.67 MVAR, 1-Ph, 132kV Bus Reactor along with associated bay at Roing, Asset-II: (i) 132kV S/C (on D/C Tower) Roing�Tezu Transmission Line alongwith associated bays at Roing and Tezu S/S, (ii) 4x6.67 MVAR, 1-Ph, 132kV Bus Reactor along with associated bay at Tezu from DOCO to 31.03.2019 under the transmission system associated with �Transmission system associated with Pallatana GBPP and Bongaigaon TPS�
Order reserved Engineering Division,Petitioner
189
269/MP/2017
Korba West Power Company Limited (KWPCL)
Petition under Section 79 (1) (c) and Section 79 (1) (f) of the Electricity Act, 2003 read with Clause 9 of the BPTA, Clause 11 of the TSA and Regulation 32 of CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 for deferment of operationalization of LTA on account of Force majeure events.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
190
267/MP/2017
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION (TANGEDCO)
The practical difficulties and financial implications due to the implementation of the Detailed Operating Procedure dated 05.05.2017.
Reply / additional information as per ROP to filed by Petitioner,Respondent
191
47/RP/2017 in 26/TT/2017
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
PETITION UNDER SECTION 94 (1) (f) OF THE ELECTRICITY ACT, 2003 READ WITH ORDER 47 RULE 1 OF THE CODE OF CIVIL PROCEDURE, 1907 FOR REVIEW OF THE ORDER DATED 18.10.2017 PASSED IN PETITION NO. 26/TT/2017
Additional information as per Interim Order to be filed by Petitioner,Respondent
192
264/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014  for  determination of Transmission Tariff  of Asset (A): 400 kV Anta Bay at Kota Sub-Station for 400 kV S/C Anta-Kota Line (Line owned by RVPNL) under �Northern Region System Strengthening Scheme-XXVII�, for tariff block 2014-19 period in Northern Region.
Additional information for final order to be filed by Petitioner,Respondent
193
263/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations?  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Asset I:LILO of Meramundali-Jeypore 400 kV S/C line at Angul Sub-station, Asset II: one no. of 125 MVAR Reactor (1st) and associated bays at Angul Sub-station, Asset III:  , Asset IV: one no. of 125 MVAR Reactor (3rd) and associated bays at Angul Sub-station, Asset VI: LILO-I (Ckt.-III) of Rourkela-Raigarh 400 kV D/C line at Jharsuguda Sub-station, Asset-VII: LILO-II (Ckt.-I) of Rourkela-Raigarh 400 kV D/C line at Jharsuguda Sub-station, Asset-VIII: one no. of 125 MVAR Reactor (1st) and associated bays at Jharsuguda Sub-station, Asset-IX: one no. of 125 MVAR Reactor (2nd) and associated bays at Jharsuguda Sub-station under Transmission System for Phase-I Generation Projects in Orissa-Part-A in Eastern Region
Order reserved
194
262/MP/2017
Jindal Power Limited (JPL)
Petition seeking amendment to the transmission license granted to the Petitioner vide an order dated 09.05.2011, passed in Petition No. 105 of 2010, for including the 2 x 400kV bays and bus sectionalizer bays and part of 400/220 kV sub-station equipment at Raipur Sub-station of PGCIL
Preliminary Scrutiny
page separator
S. No.
Petition No.
Petitioner
Subject
Status
195
261/MP/2017
NTPC Limited
Petition under Section 79 (1) (c) & (f) of the Electricity Act, 2003 read with the provisions of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations), 2010 to set aside the bill dated 06.11.2017 of the Central Transmission Utility (PGCIL) towards LTA Charges for the Kudgi Transmission System.
Reply / additional information as per ROP to filed by Petitioner,Respondent
196
259/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 400/220 kV 1X500 MVA ICT-III at Satna along with associated ICT bays and 2 Nos. 220kV line bays at Satna SS under �Western Region Strengthening Scheme-XVI� for tariff block 2014-19 period.
Hearing
197
255/MP/2017
ADHUNIK POWER AND NATURAL RESOURCES LIMITED (APNRL)
PETITION UNDER SECTIONS 79(1)(b) AND 79(1)(f) OF THE ELECTRICITY ACT, 2003 READ WITH ARTICLE 10 OF THE PPA AND PSA
Order reserved
198
254/MP/2017
BSES Rajdhani Power Limited (BRPL)
Re-setting of the Rate of Late Payment Surcharge under Clause 45 of the Tariff Regulations 2014-19
Hearing
199
253/MP/2017
sks power generation (chhattisgarh) limited (SPGCL)
Petition seeking surrender/ relinquishment of LTA of 513 MW (149 MW in WR and 364 MW in NR) out of the total LTA quantum of 683 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010.
Hearing
200
251/GT/2017
UDUPI POWER CORPORATION LTD (UPCL)
Application under Regulations 20, 25 & 27 of the  of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999; Regulations 2, 6 and 7 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations 2014 and under Section 62 and 79(1)(b) of the Electricity Act, 2003 for determination of tariff for the 2x600 MW thermal power plant set up by  Udupi Power  Corporation Limited in Udupi Taluk, Udupi District, Karnataka for the period, from 01.04.2014 to 31.03.2019.
Hearing
201
250/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation: 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1 : 765 kV Line bays at Jabalpur Pooling Station for 765 kV D/C Gadarwara STPS (NTPC) - Jabalpur pooling Station TL under  " POWERGRID Works associated with Part A of Transmission system for Gadarwara STPS of NTPC" in Western Region.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
202
249/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business)

Regulations‟1999 and CERC (Terms and Conditions of Tariff) Regulations ‟2014 for determination of Transmission Tariff from anticipated DOCOs to 31.03.2019 for Asset-I: Extension of 400/220 kV Sikar Substation with 1X500 MVA, 400/220/33 kV auto transformer along with associated bays along with 2 nos. 220 kV line bays and Asset-II: Extension of 400/220 kV Manpuri Substation with 1X500 MVA, 400/220/33 kV auto Transformer and associated bays along with 2 nos. 220 kV line bays under �Augmentation of transformation capacity at Mainpuri and Sikar� in Northern Region.
Order reserved
203
248/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset-I: 17 Nos of OPGW links (759 km) (DOCO: 01.10.2012), Asset II: 09 nos of OPGW links (490 km) (DOCO: 01.04.2013), Asset III: 10 nos of OPGW links (440 km) (DOCO: 01.11.2013) and Asset IV: 01 nos of WBSETCL sector portion OPGW link (78.26 km) (DOCO: 01.03.2014) under �Fibre Optic communication system in lieu of existing Unified Load Despatch and Communication(ULDC) Microwave links� in Eastern Region
Hearing
204
247/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 1X500MVA, 765/400kV Transformer as spare ICT at Agra Sub-station, Asset-II: 1X500MVA, 765/400kV Transformer as spare ICT at Fatehpur Sub-station, Asset-III: 765/400 KV,500MVA, single phase  Auto Transformer as spare ICT at Jhatikra S/S and Asset-IV: 765/400 KV, 333MVA, single phase  Auto Transformer as spare ICT at Bhiwani S/S  under �Spare Transformer for 765/400KV ICTs in NR�.
Reply / additional information as per ROP to filed by Petitioner,Respondent
205
245/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
approval of Transmission Tariff from DOCO i.e. 01.12.2015 to 31.03.2019 for Gooty-Madhugiri 400kV D/C line and 2x500MVA transformers alongwith downstream bays at Madhugiri Substation upon bifurcation of capital cost and hence transmission tariff as per directive of Hon�ble Commission vide Order dated 18.07.2017 in Petition 54/RP/2016 Under �Transmission system associated with System strengthening -XIII� in Southern Region for tariff block 2014-19 period.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
206
244/TT/2017
HIMACHAL PRADESH POWER TRANSMISSION CORPORATION LTD. (HPPTCL)
Approval under Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations, 2014 for determination of Transmission Tariff forAsset: 33/220kV, 80/100 MVA GIS Substation Phojal along with 220kV D/C LILO   Transmission line.
Hearing
207
46/RP/2017 in TT/227/2014
bhopal dhule transmission company limited (BDTCL)
Petition for review and modification of the Order dated 20.09.2017 passed by this Hon?ble Commission in Petition No. 227/TT/2014 titled Power Grid Corporation of India Limited v. Madhya Pradesh Power Management Company Limited and Ors.
Hearing
208
243/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff  of  Bongaigaon Thermal Power Station (3X250 MW) for the period from Date of Commercial Operation of Unit-1 (i.e. 01.04.2016) to 31.03.2019.
Interim order under preparation
209
242/MP/2017
Aryan M.P. Power Generation Private Limited AMPPGPL
Petition for declaring the letter of invocation of Bank Guarantee dated 23.10.2017 and thereafter the encashment of the Bank Guarantee dated 23.02.2010 of an amount of Rs. 56.1 Crores issued by Axis Bank Ltd. as illegal and for return of the said encashed amount along with damages.
Hearing
210
45/RP/2017 in 272/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the order dated 20.09.2017 passed by this Hon'ble Commission in Petition No. 272/TT/2015.
Additional information for final order to be filed by Petitioner,Respondent
211
241/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Determination of tariff of Muzaffarpur Thermal Power Station        Stage-I Unit-2 (110 MW) for the Period 15.10.2010 to 31.03.2014
Hearing
212
240/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Approval of tariff of MTPS Stage-I (2x110 MW) from 01.04.2014 to 31.03.2019.
Hearing
213
238/MP/2017
Darbhanga Motihari Transmission Company Limited (DMTCL)
Petition u/s 61, 63 and 79 of Electricity Act, 2003 to be read with the other laid down statutory framework
for seeking extension in Project scheduled commercial operation date and increase in transmission
charges due to unforeseen and uncontrollable events post award of ERSS-VI Transmission Scheme implemented by Darbhanga-Motihari Transmission Co. Ltd. under Tariff Based Competitive Bidding guidelines.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
214
237/MP/2017
Suzlon Energy Limited (SEL)
Petition preferred under Section 94 (1)(f) of the Electricity Act, 2003 read with Regulation 111 and 116 of Central Electricity Regulatory Commission (Conduct of Business Regulations),1999 for seeking extension of time prescribed for implementation of the Hon�ble Central Electricity Regulatory Commission�s Order dated 5 January, 2016 in Petition No. 420/MP/2014 in the matter of �Endangering grid security due to non-implementation of contingency demand disconnection scheme for sudden loss of wind generation, non-availability of LVRT protection, non-scheduling of wind generation as per CERC (Indian Electricity Grid Code) Regulations, 2010 (IEGC) 6.5.23 (i), lack of necessary demand estimation as per IEGC Regulation 5.3 and not providing real time SCADA data to LDC.�, and for seeking relief to specific provisions of the aforementioned Order.
Hearing
215
236/MP/2017
DAMODAR VALLEY CORPORATION (DVC)
Petition against the decision of MPPMCL for Unilateral surrender of 100 MW from DSTPS in violation of provision of PPA between DVC & MPPMCL
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
216
235/MP/2017
Darbhanga Motihari Transmission Company Limited (DMTCL)
Application for seeking approval under Sections 17 (3) and (4) of the Electricity Act, 2003 for creation of security interest by Darbhanga - Motihari Transmission Company Limited (the "Petitioner-I" / "Borrower") in favour of IDBI Trusteeship Services Limited (the "Petitioner-II" / "Security Trustee"), as Security Trustee, acting on behalf of IDFC Bank Limited (hereinafter referred to as the "Lender", which expression, shall, unless it be repugnant to the subject or context thereof, be deemed to mean and include its successors, assigns or substitutes, from time to time), over all rights, title and interest of the Petitioner-I, both present & future, over and in respect of (i) all the movable and immovable assets of the  Petitioner-I including all movable and immovable assets of the utility to be established by the  Petitioner-I that constitute the Project (defined hereinafter); (ii) the Transmission Service Agreement executed by the  Petitioner-I in the month of August, 2013 (the "TSA"); (iii) the transmission license dated May 30, 2014 for the development of transmission system under "Eastern Region System Strengthening Scheme - VI" (the "Project"); and (iv) all the Project documents as well as the cash flows, receivables, bank accounts, clearance(s), notifications, Government approvals, orders, both present and future and including but not limited to any amendments, supplements to the existing project documents etc., under the Project, pursuant to the refinancing of the original project lenders of the Petitioner-I through the loans availed from the Lender.
Hearing
217
234/MP/2017
M.P. Power Management Co. Ltd. (MPPMCL)
Petition under Section 79 of the Electricity Act, 2003 for direction to Rajasthan Rajya Vidyut Prasaran Nigam Ltd to make payment of outstanding amount to the petitioner on account of overdrawal of power from Chambal - Satpura Complex/Chambal project & payment of O&M/capital expenditure of the Chambal - Satpura Complex/Chambal project and scheduling of respective shares of both the States in Chambal project (Hydel Power Plants)
Preparation of ROP
218
233/MP/2017
ACME Yamunanagar Solar Power Private Limited (AYSPPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of Power Purchase Agreements (PPAs) dated 09.08.2016.
Hearing
219
232/MP/2017
ACME Mahbubnagar Solar Energy Private Limited (AMSEPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of Power Purchase Agreements (PPAs) dated 08.08.2016.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
220
231/MP/2017
ACME Rewari Solar Power Private Limited (ARSPPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 24.06.2016.
Hearing
221
230/MP/2017
ACME Kurukshetra Solar Energy Private Limited (AKSEPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 24.06.2016.
Hearing
222
229/MP/2017
NTPC Vidyut Vyapar Nigam Limited (NVVN)
Adjudication of disputes between NTPC Vidyut Vyapar Nigam Limited and Power Company of Karnataka Limited related to the procurement of power pursuant to a Tariff Based Competitive Bid Process undertaken by the Power Company of Karnataka Limited
Additional information for final order to be filed by Petitioner,Respondent
223
228/MP/2017
Bhushan Power & Steel Ltd. (BPSL)
Petition under Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 32 of the CERC (Grant of Connectivity, Long Term Open Access in intra State Transmission and related matters) Regulations, 2009 alongwith affidavit.
Hearing
224
227/MP/2017
LANCO AMARKANTAK POWER LTD. LAMPL
Petition under Section 79(1) (c) read with Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999
Hearing
225
225/MP/2017
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Petition under section 94 (1) (f) of the Electricity Act, 2003 read with related provisions of Regulation 103 (1) of the Central Electricity Regulatory Commission (Conduct of Business) (Amendment) Regulations, 2013 seeking compensation for loss of Capacity Charge on account of inadequate availability of fuel gas under provisions of Regulation 54 (Power to Relax) of the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulations, 2014  in respect of the Assam Gas Based Power Plant (AGBP).
Reply / additional information as per ROP to filed by Petitioner,Respondent
226
224/MP/2017
North East Transmission Company Ltd. (NETC)
PETITION UNDER SECTIONS 79(1)(d) OF THE ELECTRICITY ACT, 2003 READ WITH REGULATIONS 54 AND 55 OF THE CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014.
Hearing
227
223/MP/2017
ENN ENN CORP LTD (ENNENN)
Petition under Section 79(1) of the Electricity Act, 2003 and Section 14 & 15 of Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010, challenging the illegal and arbitrary rejection of grant of REC application of the Petitioner by Respondent
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
228
222/MP/2017
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79(1)(b), 79(1)(f) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES WITH THE RESPONDENT WITH REGARD TO THE TARIFF PAYABLE UNDER THE POWER PURCHASE AGREEMENT DATED 27/11/2013
Hearing
229
221/TT/2017
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval of tariff in respect of PTCUL owned transmission lines/system connecting with other states and intervening transmission lines incidental to inter-State transmission of electricity as per the Central Electricity Regulatory Commission�s order dated 14.3.2012 in Petition No.15/Suo-Motu/2012, for inclusion in POC charges as provided in the Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) Regulations, 2010 in accordance with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for tariff block 2014-19 period and Regulation 86 of CERC (Conduct of Business) Regulations, 1999.
Order reserved
230
220/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset �a) Both circuits of one LILO D/C portion of Simhadri-Vijayawada 400kV Line at Vemagiri-I (AP) shall be LILOed at Vemagiri-II (PG) (D/C Portion and multi-circuit Portion) alongwith associated bays at Vemagiri-II (PG)  b) Both circuits of Second LILO D/C portion of Simhadri-Vijayawada 400kV Line at Vemagiri-I (AP) shall be looped in at Vemagiri-II (PG). There shall be NO LOOP OUT. The open section of 400kV D/C line from Vemagiri-I (AP) shall be used for termination of KV Kota Line alongwith associated bays at Vemagiri-II (PG). c) Shifting of 2 Nos. of 63 MVAr reactors from Gazuwaka to Vemagiri-II (PG) for utilization on Simhadri-II-Vemagiri-II(PG) 400kV D/C Line under �Removal of Constraints in 400kV Bays Extensions at 400kV Vemagiri S/S� in Southern Region.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
231
43/RP/2017 in 067/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) Regulations, 1999 for review of the Order dated 31/08/2017 passed by the Hon�ble Commission in Petition No. 67/TT/2015 in the matter of determination of transmission tariff for i) Asset � I (HVDC Portion), ii) Combined Asset � II (AC Portion) from anticipated DOCO 31.03.2015 to 31.03.2019 under the Transmission system associated with NORTH EAST - NORTHERN/WESTERN INTERCONNECTOR -I in North Eastern, Northern & Western Regions.
Hearing
232
42/RP/2017 in 218/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for Review and Modification of the Order dated 18.09.2017 passed by this Hon�ble Commission in Petition No. 218/TT/2016 titled Power Grid Corporation of India Limited v. Madhya Pradesh Power Management Company Limited and Ors.
Order reserved
233
41/RP/2017 in 213/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the Order dated 07.09.2017 passed by this Hon�ble Commission in Petition No. 213/TT/2016 titled Power Grid Corporation of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Limited and Ors.
Order reserved
234
219/TD/2017
Ms. Saini Power Transactor Represented by Saroj Bala Saini
Application for grant of trading Licence Category - IV
Hearing
235
218/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval of Truing tariff for  Accelarated Depreciation of SCADA/EMS system of ULDC
Order reserved
236
217/TT/2017
Jaypee Powergrid Limited (JPL)
APPROVAL UNDER REGULATION 86 OF CERC (CONDUCT OF BUSINESS) REGULATIONS, 1999 AND REGULATION 6 OF CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2009 AND CERC (TERMS AND CONDITIONS OF TARIFF) REGULATIONS, 2014 FOR DETERMINATION OF:

I) TRUING UP TRANSMISSION TARIFF FOR 2009-14 TARIFF BLOCK AND
II) TRANSMISSION TARIFF FOR 2014-19 TARIFF BLOCK FOR 

ASSET ? I 
LILO OF 400 KV DC BASPA-NAPTHA-JHAKRI TRANSMISSION LINE

ASSET ? II 
KARCHAM WANGTOO ABDULLAPUR 400 KV DC QUAD TRANSMISSION LINE
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
237
216/RC/2017
Indian Energy Exchange Ltd. (IEX)
PETITION FOR SEEKING APPROVAL TO AMENDMENTS OF BYE LAWS, RULES & BUSINESS RULES WITH RESPECT TO THE CENTRAL ELECTRICITY REGULATORY COMMISSSION (TERMS AND CONDITIONS FOR EXCHANGE OF ENERGY SAVINGS CERTIFICATES) REGULATIONS, 2016 REGARDING ESCerts CONTRACTS TRANSACTION ON INDIAN ENERGY EXCHANGE LIMITED
Preliminary Scrutiny
238
40/RP/2017 in 235/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition for review and modification of the Order dated 19.09.2017 passed by this Hon?ble Commission in Petition No. 235/TT/2016 titled Power Grid Corporation of India Limited v. Karnataka Power Transmission Corporation Limited and Ors
Hearing
239
215/TT/2017
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
Determination of Tariff for the year 2017-18 in respect of RVPN owned transmission lines/system.
Order reserved
240
214/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Misc. Petition for Approval under sub-section(4) of Section 28 & 79(1)(d) of Electricity Act 2003 and regulation-86 of CERC (Conduct of Business) Regulations?1999 for  determination of 

i) Trued up Fees and Charges for 2009-14 block
ii)  Fees and Charges for the period 2014-19 block. 

For Fibre Optic communication system in lieu of existing Unified Load Despatch and Communication(ULDC) Microwave links in North Eastern Region
Hearing
241
213/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Misc. Petition for Approval under sub-section(4) of Section 28 & 79(1)(d) of Electricity Act 2003 and regulation-86 of CERC (Conduct of Business) Regulations�1999 for  determination of 

i) Trued up Fees and Charges for 2009-14 block
ii) Fees and Charges for the period 2014-19 block. 

For Asset-I: 02 Nos OPGW links under Central Sector (127 km) (DOCO: 01.11.2013) and Asset II: 03 Nos OPGW links under Central Sector (170.234 km) (DOCO: 01.03.2014), under �Fibre Optic communication system under Expansion of Wideband Communication Network� in Eastern Region.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
242
212/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Revised/Fresh Petition for approval under sub-section(4) of Section 28 of Electricity Act 2003 for revision of Fees and Charges for the period 2014-19 block considering accelerated depreciation of SCADA/EMS systems of SLDCs for Unified Load Despatch & Communication  Scheme (POWERGRID portion i.e. Communication system portion and SLDC system retained by the petitioner after formation of POSOCO) in Western Region.
Order reserved
243
211/MP/2017
Solar Power Developers Association (SPDA)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreements (PPA) dated 14.10.2016.
Order reserved
244
39/RP/2017 in 146/GT/2015
Neyveli Lignite Corporation Ltd (NLC)
NLCIL- TSII Expn (2 X 250 MW)  - Petition seeking review of Tariff under CERC(Terms and Conditions of Tariff) Regulations 2014 � Reg
Hearing
245
210/MP/2017
KUDGI TRANSMISSION LIMITED (KTL)
Petition for revision of Tariff for events occurring after the Bid Due Date
Hearing
246
209/MP/2017
A D Hydro Power Limited (ADHPL)
Petition for Approval of Transmission Charges, Transmission Losses and other Conditions for use of the 176.5 km long 220KV Double Circuit Dedicated Transmission Line of Allain Duhangan Hydro Project- In Remand of proceedings arising out of Petition No. 259/MP/2010 by Hon'ble Supreme Court of India.
Hearing
247
208/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations �1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for �(i) Hyderabad (Maheshwaram)-Nizamabad 765kV D/C Line and (ii) 2 nos 765kV bays along with 1 no. 240 MVAR switchable line reactor each at Hyderabad (Maheshwaram) & Nizamabad substation each for both circuits of Hyderabad-Nizamabad 765kV D/C Line� with Anticipated DOCO as 01.08.2017 under �Wardha � Hyderabad 765 kV Link�  in Southern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
248
207/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Assets under �Transmission System associated with Mundra Ultra Mega Power Project� for tariff block 2014-19 in Western Region.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
249
38/RP/2017 in 135/GT/2015
NLC Tamilnadu Power Ltd (NTPL)
Petition for review of the Order dated 11.7.2017 passed by the Hon?ble Commission in Petition No. 135/GT/2015 in the matter regarding approval of tariff of Coal based NLC Tamil Nadu Power Ltd (TPS 2 x 500 MW) for the period from the date of the declaration of commercial operation of Unit I &II till 31.3.2019.
Hearing
250
206/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: Rapp� Kota 400 kV D/C line (part of Rapp-Jaipur(South) 400kV D/C line with one ckt LILOed at Kota) along with associated bay at Kota (Ant. DOCO: 31.08.17)  under Transmission system associated with Rapp 7 & 8, Part-A
Order reserved
251
205/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: Pole-II of the ?800 kV, 3000 MW Champa & Kurukshetra HVDC Terminals along with associated bays under ?WR ? NR HVDC Interconnector for IPP Projects in Chhattisgarh? in Northern Region & Western Region.
Order reserved
252
204/MP/2017
ACME Babadham Solar Power Private Limited (ABSPPL1)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 22.08.2016.
Preparation of ROP
253
203/MP/2017
ACME Vijayapura Solar Energy Private Limited (AVSEPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 22.08.2016.
Preparation of ROP
254
202/MP/2017
ACME Koppal Solar Energy Private Limited (AKSEPL1)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 22.08.2016.
Preparation of ROP
255
201/MP/2017
ACME Kaithal Solar Power Private Limited (AKSPPL1)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 22.08.2016.
Preparation of ROP
256
200/MP/2017
Nirani Sugars Ltd. (niranisugars)
PAYMENT OF OUTSTANDING DUES TOWARDS THE POWER SOLD
Reply / additional information as per ROP to filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
257
199/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Kudgi Super Thermal Power Station Stage-I (3 X 800 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e. 25.07.2017) to 31.03.2019.
Interim order under preparation
258
198/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval Under Regulation 86 of CERC (Conduct of Business) Regulations�1999, and CERC (Terms and Conditions of Tariff) Regulations�2014 for Determination of    Transmission Tariff  for Asset-I:�800kV 3000MW HVDC POLE-III and LILO of Bishwanath Chariali � Agra HVDC line for parallel operation of the HVDC station at Alipurduar, Asset-II:�800kV 3000MW HVDC POLE-IV alongwith Earth electrode station and Earth Electrode line at Alipurduar and Agra end, Asset-III:LILO of Bongaigaon � Siliguri 400kV D/c line (quad) (under pvt. Sector) alongwith associated bays at Alipurduar, Asset-IV:LILO of Birpara-Salakati 220kV D/c line alongwith associated bays at new pooling station in Alipurduar, Asset-V:1x315MVA 400/220kV, ICT-I at Alipurduar, Asset-VI:1x315 MVA 400/220kV ICT-II at Alipurduar, Asset-VII:1x125MVAr 400kV Bus Reactor-I at Alipurduar and Asset-VIII:1x125MVAr 400kV Bus Reactor-II at Alipurduar from anticipated DOCO to 31.03.2019 under the transmission system associated with �Transmission system for development of pooling station in Northern part of West Bengal and transfer of power from Bhutan to NR/WR�.
Tariff order u/r 7(7) of 2014 Tariff Regulation
259
197/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Feroze Gandhi Unchahar Thermal Power Station Stage-IV (1 X 500 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e. 31.07.2017) to 31.03.2019.
Interim order under preparation
260
196/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for LILO of both circuits of Mundra UMPP - Limbdi 400 kV D/C line (triple snowbird) at Bachau S/S alongwith extension of 400 kV Bachau S/S - DOCO - 01.10.2017 (ant.) under ?Transmission System Strengthening associated with Mundra UMPP (Part-A)? for tariff block 2014-19 in Western Region.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
261
195/MP/2017
NRSS XXXI (B) Transmission Limited NRSSXXXIB
Petition u/s 61, 63 and 79 of Electricity Act, 2003 to be read with the other laid down statutory framework for seeking extension in Project scheduled commercial operation date and increase in transmission charges due to unforeseen and uncontrollable events post award of NRSS XXXI (B) Transmission Scheme under Tariff Based Competitive Bidding guidelines of Transmission Projects.
Hearing
262
35/RP/2017 in 154/MP/2015
GUJARAT URJA VIKAS NIGAM LIMITED (GUVNL)
Petition for review of the order dated 31.07.2017 passed by this Hon'ble Commission in Petition No. 154/MP/2015
Additional information for final order to be filed by Petitioner,Respondent
263
194/MP/2017
North Karanpura Transco Limited NKTL
Petition under Sections 61, 63, 79(1)(c) and 79(1)(f) of the Electricity Act, 2003 read with Article 16 of TSA and the tariff-based competitive bidding guidelines for transmission service, for claiming relief under TSA dated 14.03.2016 relating to implementation of the transmission Project Elements
Hearing
264
193/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations, 2009 and CERC (Terms and Conditions of Tariff) Regulations� 2014 for determination of

a. Truing up Transmission tariff for 2009-14 tariff  block and 
b. Transmission tariff for 2014-19  tariff block 

 for Asset 1:  Part of 400 kV D/C Vapi-Navi Mumbai TL (from Vapi Gantry till 1st M/C point at Loc. AP-18) alongwith bay at Vapi (DOCO: 01.04.13) (executed in contingency arrangement to make it Vapi-Navsari TL) and Asset 2: 220 kV  D/C Vapi - Khadoli Transmission line along with associated Bays (DOCO: 01.10.10) under WRSS-V Transmission System in WR Region.
Hearing
265
192/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset I: 400kV D/C Aurangabad - Boisar TL  {from Aurangabad S/S to location 313/0 on D/C Towers & from location 332/0 to Boisar S/S on Multi circuit towers} &  Asset II: Part of 400kV D/C Navsari � Boisar TL  from location 332/0 to Boisar S/S on Multi circuit towers under IPPs generation projects in Chhattisgargh (IPP D) in Western Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
266
191/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Mauda II � Betul 400 kV D/C (Quad) T/L alongwith associated bays at Betul GIS � Asset-1 (Ant. DOCO � 01.04.2017), Betul � Khandwa 400 kV D/C (Quad) T/L alongwith associated bays at Betul GIS and Khandwa S/S � Asset-2 (Ant. DOCO � 01.04.2017), Khandwa � Indore 400 kV D/C T/L alongwith associated bays � Asset-3 (DOCO � 01.01.2017) & Establishment of 400/220 kV, 2*315 MVA GIS at Betul � Asset-4 (Ant. DOCO � 01.04.2017) under �Transmission System associated with Mauda Stage-II (2 x 660 MW) Generation Project� in Western Region for tariff block 2014-19 period.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
267
32/RP/2017 in GT/325/2014
NTPC Limited
Review of the order dated 10.04.2017 in respect of determination of tariff of Jhanor Gandhar GPS (657.39 MW)  for the period from 01.04.2014 to 31.03.2019.
Hearing
268
190/MP/2017
ACME Hisar Solar Power Private Limited (AHSPPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 14.10.2016.
Preparation of ROP
269
189/MP/2017
ACME Karnal Solar Power Private Limited (AKSPPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 14.10.2016
Preparation of ROP
270
188/MP/2017
ACME Bhiwadi Solar Power Private Limited (ABSPPL)
Petition under section 79 of the Electricity Act, 2003 for revision of tariff on account of increase in capital cost relating to the provisions of the Power Purchase Agreement (PPA) dated 14.10.2016.
Preparation of ROP
271
187/MP/2017
Essar Power M.P. Ltd. (EPMPL)
Petition for Relinquishment of 750 MW of LTA out of total LTA of 1200 MW granted under BPTA dated 07.01.2009
Reply / additional information as per ROP to filed by Petitioner,Respondent
272
180/MP/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Section 41 of the Electricity Act, 2003 read alongwith Central Electricity Regulatory Commission (Sharing of Revenue derived from utilization of Transmission Assets for other business) Regulations, 2007 for intimation to engage in other business for optimum utilization of transmission assets.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
273
178/GT/2017
NTPC Limited
Petition Under Section 62 and 79 (1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Solapur Super Thermal Power Station   (2 X 660 MW) for the period from anticipated date of Commercial Operation of the Unit-I (i.e.  31.08.2017)  to 31.03.2019.
Interim order under preparation
274
176/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for �ASSET-I: 01x125MVAr 400kV Bus Reactor-3 along with associated bays and equipment at Vijayawada Substation, 01x500MVA 400/220/33 kV ICT-3 along with associated bays and equipment each at Hyderabad (Ghanapur) and Vijayawada Substation. ASSET-II: 01x125MVAr 400kV Bus Reactor-4 along with associated bays at Vijayawada Substation, ASSET-III: 1x500MVA, 400/220/33kV ICT along with associated bays and equipments at Pugalur Substation, ASSET-IV: Conversion of 50MVAR line reactors at Madakathara end on both circuits of Ellapally (palakkad) � Madakathara (North Trissur) 400KV D/c line into switchable reactors by providing necessary switching arrangement, ASSET-V:1x500MVA,400/220/33kV ICT along with associated bays and equipments at Trichy Substation, ASSET-VI: Replacement of existing 2x315MVA 400/220KV transformers with 2x 500MVA transformers and utilize the replaced 2x315MVA transformers as regional spare at Narendra S/S  under System strengthening-XX�  in Southern Region.
Order reserved
275
175/TT/2017
DELHI TRANSCO LIMITED (DTL)
Approval under Regulation-86 of CERC (Conduct of Business) Regulations, 1999 and Regulation-6 of CERC (Terms and Conditions of Tariff) Regulations, 2014 read with Section-62 & 79 of Electricity Act, 2003 for determination of

(i) Transmission Tariff for 2014 -19 tariff block

For 400 kV Mandaula - Bawana Double Ckt. and 400 kV Ballabhgarh - Bamnauli Double Ckt. Transmission Lines.
Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
276
171/GT/2017
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
In the matter of approval for filing petition in CERC for approval of Generation Tariff for shared Hydro Projects of Rajasthan & Madhya Pradesh installed in Rajasthan namely Rana Pratap Sagar Hydel Power station for the Financial year 2012-13 & 2013-14 in accordance with the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulation 2009.
Hearing
277
170/GT/2017
RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED (RVPN)
In the matter of approval for filing petition in CERC for approval of Generation Tariff for shared Hydro Projects of Rajasthan & Madhya Pradesh installed in Rajasthan namely Jawahar Sagar Hydel Power station for the Financial year 2012-13 & 2013-14 in accordance with the Central Electricity Regulatory Commission (Terms and Condition of Tariff) Regulation 2009.
Hearing
278
169/MP/2017
sks power generation (chhattisgarh) limited (SPGCL)
Petition seeking surrender/ relinquishment of 170 MW (170 MW in WR) out of the total LTA quantum of 683 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010.
ROP Issued
279
165/GT/2017
THDC India Limited (THDCIL)
Approval of Generation Tariff of Koteshwar Hydro Electric Project (KHEP) (4X100 MW) for the period 01.04.2011 to 31.03.2014
Additional information for final order to be filed by Petitioner,Respondent
280
164/MP/2017
IL & FS Tamil Nadu Power Company Limited (IL&FS)
PETITION UNDER SECTIONS 79(1)(C) AND 79(1)(F) OF THE ELECTRICITY ACT, 2003
Hearing
281
29/RP/2017 in 45/GT/2016
NTPC Limited
Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 103 of the CERC (Conduct of Business) Regulations, 1999 for review of the Order dated 22.05.2017 passed by Hon�ble Commission in Petition No 45/GT/2016  in the matter of approval of tariff of Bongaigaon Thermal Power Station of Unit#1 (250 MW) for the period 1.4.2016 to 31.3.2019.
Order reserved
282
162/MP/2017
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (C), (D), (F) AND OTHER APPLICABLE PROVISIONS OF THE ELECTRICITY ACT, 2003 SEEKING DIRECTIONS AGAINST THE RESPONDENT IN RELATION TO THE MEDIUM TERM OPEN ACCESS FOR TRANSFER OF POWER FROM THE WESTERN REGION TO THE NORTHERN REGION
Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
283
161/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of 
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For

Asset : LILO of both circuits of 400 kV D/C Kishenpur Wagoora T/L along with bays at New Wanpoh & 1 No. 315 MVA, 400/220kV ICT-I along with associated bays at New Wanpoh and 03 No. 220 kV Line Bays (DOCO: 01.10.2013), under Northern region system strengthening scheme-XVI in Northern region
Hearing
284
160/MP/2017
Tata Power Trading Company Limited (TPTCL)
Petition under Section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation on account of event pertaining to change in law as per the terms of LOA placed by the Respondent upon the petitioner no. 1 for supply of power from plant of Petitioner No. 2
Hearing
285
159/MP/2017
Tata Power Trading Company Limited (TPTCL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation from Respondent on account of event pertaining to change in law as per the terms of LOI dated 14.01.2016 placed by the Respondent upon the Petitioner No. 1.
Hearing
286
158/MP/2017
Tata Power Trading Company Limited (TPTCL)
Petition under section 79(1)(b) and 79 (1)(f) of the Electricity Act, 2003 for claiming compensation on account of event pertaining to change in law as per the terms of LOA dated 18.01.2016 read with the terms of NIT dated 22.12.2015 executed between the Petitioner No. 1 and the Respondent.
Hearing
287
157/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Transmission Asset �(a) LILO of Hyderabad - Kurnool 400kV S/C line at Maheshwaram Pooling Station along with associated bays and (b) Establishment of 765/400kV GIS Pooling Station at Hyderabad (Maheshwaram) with 2X1500MVA 765/400kV Transformers and 2nos 240 MVAR 765kV alongwith associated bays at Maheshwaram pooling stations under �Sub-Station Works associated with Hyderabad (Maheshwaram) Pooling Station�.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
288
156/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for Asset-I:2 nos of 400kV GIS line bays at Nizamabad (PG) for the termination of Nizamabad-Yeddumailaram (Shankarpalli) 400kV D/C line and Asset-II: 2 Nos. of 400kV GIS line bays at Maheswaram (PG) for termination of Maheswaram(PG)�Mehboob Nagar 400kV D/C Transmission line under "Provision of Line bays for the Scheme � Connectivity lines for Maheshwaram (Hyderabad) 765/400 kV Pooling Station� in Southern Region
Order reserved
289
155/TT/2017
ODISHA POWER TRANSMISSION CORPORATION LIMITED (OPTCL)
Petition for approval of Tariff for inclusion of Transmission Assets in Computation of Point of Connection (PoC) Charges and Losses as per Hon�ble Commission�s order dated 12.05.2017 in Petition No. 07/SM/2017 for inclusion in PoC charges in accordance with Central Electricity Regulatory Commission (Sharing of Inter-state Transmission Charges and Losses) Regulations, 2010 and amendments made thereto.
Order reserved
290
153/MP/2017
DAMODAR VALLEY CORPORATION (DVC)
Petition under section 79(1)(d) of the Electricity Act 2003 and CERC (Open Access in interstate Transmission) Regulation,2008 for approval of Open Access charges for transmission and wheeling of power using Transmission and Distribution network of Damodar Valley Corporation
Hearing
291
149/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations, 1999 and Regulation-6 of CERC (Terms and Conditions of Tariff) Regulations, 2009 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Truing up Transmission tariff for 2009-14 tariff  block and Transmission tariff for 2014-19 tariff block for  Asset : �Loop- out of 220KV Jalandhar -Hamirpur line at Hamirpur (To be used as LILO of 1ST Ckt. of 220KV Hamirpur-Jalandhar T/L)� (DOCO: 01.01.2014) under the �STRENGTHENING SCHEME IN NORTHERN REGION� in Northern region.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
292
148/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCOs to 31.03.2019 for Asset I: LILO of Agra-Bharatpur 220 kV S/c Line at Agra (POWERGRID) S/s alongwith line bays and 1X315 MVA 400/220 kV ICT (Shifted from Ballabhgarh S/s) alongwith ICT bays at Agra (POWERGRID) Substation, Asset II: LILO of 400 kV Amritsar-Hamirpur  Line at Jalandhar (One circuit of Parbati Pooling station-Amritsar Line) along with bays, Asset-III: 01X 315 MVA, 400/220 kV ICT along with associated bays at Kaithal sub-station (Spare ICT from Ballabhgarh), Asset-IV: 02 nos 220 kV bays at Kaithal S/s, Asset-V: 02 nos. of 220 kV Line bays at Bhinmal S/S under Northern Region system Strengthening Scheme XXXIV in Northern Region
Order reserved
293
12/SM/2017
Suo Motu
Operationalisation of LTA of Long Term Transmission Customers (LTTCs) as per Regulation 8(5) of the Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) Regulations, 2010
Additional information for final order to be filed by Petitioner,Respondent
294
144/MP/2017
Neyveli Lignite Corporation Ltd (NLC)
Seeking upward revision of Technical Minimum of NLCIL  Stations
Additional information for final order to be filed by Petitioner,Respondent
295
143/MP/2017
Kerala State Electricity Board Limited (KSEB Ltd.)
Petition under section 79(1)(a), 79(1)(f) and 94(1)(f) of the Electricity Act,2003 read with Regulation 54 and 55  of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 and Regulation 103 of the CERC(Conduct of Business)Regulations, 1999 seeking a  review of the order dated 27.10.2016 passed by the Central Electricity Regulatory Commission in Petition No. 269/GT/2014,   in view of the difficulties faced by KSEBL out of the order of State Commission dated 27-4-2017.
Reply / additional information as per ROP to filed by Petitioner,Respondent
296
27/RP/2017 in GT/255/2014
Neyveli Lignite Corporation Ltd (NLC)
Petition for review of the Order dated 3.5.2017 passed by the Honorable Commission in Petition No. 255/GT/2014 in the matter regarding approval of tariff of Circulating Fluidized Bed Combustion (CFBC) Technology based Barsingsar Thermal Power Plant (2 X 125 MW) of NLC India Ltd for the period 2014-19.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
297
139/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79 of the Electricity Act 2003 read with Regulation 54 and 55 of the CERC (Terms and Conditions of Tariff) Regulations 2014 seeking Appropriate Relief due to Extreme Practical Difficulty faced by the Petitioner in implementing Regulation 30 (6) of the said Regulation and Directions issued by the Hon?ble Commission in its Order dated 25.01.2016 and For Consequential Directions
Hearing
298
136/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation 86 of CERC  Conduct of Business Regulations1999 and CERC Terms and Conditions of Tariff Regulations 2014 for  determination of    Transmission Tariff  from 01.04.2014 to 31.03.2019
Order reserved
299
135/TT/2017
ODISHA POWER TRANSMISSION CORPORATION LIMITED (OPTCL)
Determination of Wheeling Charges in respect of 220kV Rourkela-Tarkera-Budhipadar-Korba(Odisha portion) for transmission of surplus NTPC Power from ER to WR
Order reserved
300
134/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval of Truing up tariff and tariff for assets under Augmentation of Transformation capacity (Part-1) in Northern & Eastern Region
Hearing
301
133/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for �100 MVAR STATCOM at NP Kunta Pooling Station under �Transmission System for Ultra Mega Solar Park in Anantpur District, Andhra Pradesh - Part A (Phase-I)� (Anticipated DOCO: 01.04.2017)
Order reserved
302
129/MP/2017
SIMHAPURI ENERGY LIMITED (SEL)
Petition seeking surrender of 146 MW (135 MW in WR and 11 MW in SR) out of the total LTA quantum of 546 MW granted under the Bulk Power Transmission Agreement dated 24.02.2010 read with Annexure-I as modified vide amendments dated 02.01.2012 and 17.10.2012.
Hearing
303
128/GT/2017
NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED (NEEPCO)
Approval of tariff of Tripura Gas based Power Plant (TGBP), 101 MW for the period from COD of its Gas Turbine Unit to 31.03.2019
Hearing
304
10/SM/2017
Suo Motu
Non-compliance of the provision of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of Transmission Licence and other related matters) Regulations, 2009.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
305
125/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 400 kV D/C (Quad) Lara STPS-I � Champa PS Line along with associated bays at Champa Pooling Station under �Transmission System associated with Lara STPS � I (2x800 MW) Generation Project of NTPC� in Western Region for tariff block 2014-19 period.
Order reserved
306
124/MP/2017
Kanchanjunga Power Company Private Limited KPCPL
Petition under section 79(1)(f) read with section 79(1)(c) & (d), section 38, section 39, section 40 and section 60 of the Electricity Act, 2003 concerning the unjust, arbitrary and illegal terms imposed by Himachal Pradesh Power Transmission Corporation Limited and Allain Duhangan Hydro Power Limited for transmission of power by the Petitioner on inter-state transmission lines operated by them.
Hearing
307
123/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset : LILO of one ckt of 400 kV D/C Teesta III - Kishanganj line (LILO-I) at Rangpo and associated bays at Rangpo Sub-station under Sikkim Generation Projects- Part-B  in Eastern Region
Order reserved
308
122/MP/2017
Essar Power Gujarat Limited (EPGL)
Petition for Relinquishment of 250 MW of Long Term Access Agreement dated 04.12.2011 under Regulation 18 read with Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in inter-state Transmission System and related maters) Regulation, 2009, of the identified transmission system by the Essar Power Gujarat Limited (4x660-Phase-II) Thermal Power Plant at District Jamnagar in the State of Gujarat.
Reply / additional information as per ROP to filed by Petitioner,Respondent
309
119/MP/2017
Rajasthan Sun Technique Energy Private Ltd RSTEPL
The Power Purchase Agreement 8th January 2011 (?PPA?) entered into between NTPC Vidyut Vyapar Nigam Limited and Rajasthan Sun Technique Energy Pvt Ltd./Extension of Scheduled Commissioning Date
Hearing
310
118/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for 400 kV D/C Kakrapar APP-Navsari T/L along with associated bays at Navsari GIS & 400 kV D/C Kakrapar APP-Vapi T/L along with associated bays at Vapi S/S.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
311
117/MP/2017
DB Power Limited (DBPL)
Petition under Section 79(1) (b) read with Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 111 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 inter alia seeking direction to the Respondent to pay the Tariff considering 01.08.2015 to 31.03.2016 as the First Contract Year in terms of Schedule 8 of the Power Purchase Agreement 19.08.2013 executed between the Petitioner and the Respondent
Hearing
312
116/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset-I: 400kV Lucknow- Kanpur(New) D/C transmission line alongwith associated bays at both end (Anticipated DOCO:01.06.2017),  Asset-II: Augmentation of Transformation capacity at 400/220kV Ballabhgarh S/s by installing 500MVA ICT-III(Anticipated DOCO:30.04.2017), Asset-III: : Augmentation of Transformation capacity at 400/220kV Ballabhgarh S/s by installing 500MVA ICT-IV (Anticipated DOCO:31.05.2017),Asset-IV: : Augmentation of Transformation capacity by 500MVA ICT(3rd) at 400/220kV GIS Gurgaon (Anticipated DOCO:30.05.2017), Asset-V: Extension of GIS Parbati Pooling station with 7X105MVA ICT along with associated bays and 2 Nos. 220kV bays(Anticipated DOCO:01.06.2017) under NRSS-XXXII in Northern Region�.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
313
115/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For
Asset-I:- Combined assets of 1500 MVA 765/400/33KV, ICT-I, ICT-II, ICT-III & ICT-IV along with associated bays at Jhatikara 765/400 KV New S/s(DOCO:-01.10.2012), Asset-II:- Comb assets of 1500 MVA 765/400 /33 KV, ICT-I & ICT-II along with associated bays at Meerut S/s(Revised DOCO:-01.06.2013), Asset-III:-Associated bays for LILO of Both ckts of 400 KV D/C Bamnouli-Mundka/Bawana at Jhatikara 765/400 KV New S/s(DOCO:-01.10.2012), Asset-IV:- One no 765 Kv Line bay for 765 KV Agra-Jhatikara Line including 765 KV 240 MVAr Switchable Line Reactor as Bus Reactor Operation mode at 765/400 KV Jhatikara (New) S/s(Revised DOCO:01.05.2013), Asset-V:- Associated Line bays for (765 kV S/C Agra-Jhatikra Transmission Line) at Agra S/S(DOCO:-01.05.2013), Asset-VI:- One no. 765 KV line bay for 765 KV Agra-Meerut Line along with 765 KV 240 MVAR switchable Line Reactor under Bus Reactor operation mode at 765/400/220 KV Meerut S/s(Revised DOCO:-01.06.2013), Asset-VII:- Associated Line bays for 765 kV S/C Agra-Meerut Transmission Line at Agra S/S(DOCO:-01.06.2013), Asset-VIII:- 765 KV 240 MVAR Bus Reactor along with associated bays at 765/400/220 KV Meerut S/s(DOCO:-01.02.2013), Asset-IX:- 765 KV 240 MVAR Bus Reactor along with associated bays at 765/400/220 KV Jhatikara S/s(DOCO:-01.10.2012), Asset-X:- Associated bays at Jhatikara for 765 kV Jhatikara-Bhiwani Line(DOCO:-01.10.2012) under 765 KV system for Central part of Northern Grid Part-II for the 2009-14 tariff period.
Order reserved
314
26/RP/2017 in 085/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
REVIEW PETITION UNDER SECTION 94(1)(f) OF THE ELECTRICITY ACT, 2003 FOR REVIEW  AND MODIFICATION OF THE FINAL ORDER DATED 24.02.2017 PASSED BY THIS HON'BLE COMMISSION IN PETITION NO. 85/TT/2015
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
315
114/MP/2017
DANS Energy Private Limited (DEPL)
PETITION UNDER SECTION 79 (1) (c) READ WITH SECTIONS 28 AND 29 OF THE ELECTRICITY ACT, 2003 AND THE APPLICABLE REGULATIONS NOTIFIED BY THE HON�BLE COMMISSION
Additional information as per Interim Order to be filed by Petitioner,Respondent
316
113/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of

(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For Asset I: 160 MVA Transformer (1st) and associated bays at Malda Sub-station, Asset II: 160MVA Transformer (2nd) and associated bays at Malda Sub-station, Asset III: 01 no. 400 kV bay at Malda Sub-station, Asset IV: 160 MVA Transformer and associated bays at 220/132 kV Birpara Sub-station, Asset V: 160 MVA Transformer and associated bays at 220/132 kV Siliguri Sub-station under ERSS-IV project in Eastern Region
Hearing
317
110/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations'1999 and CERC (Terms and Conditions of Tariff) Regulations'2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for "Extension of Kudankulam APP- Tirunelveli 400kV (Quad) D/C line to Tuticorin pooling station along with associated bays at Tuticorin pooling station under Connectivity for Kudankulam 3&4 (2X1000MW) with interstate transmission system" in Southern Region.
Order reserved
318
109/MP/2017
PATRAN TRANSMISSION COMPANY LIMITED (PTCL)
Petition under Section 142 read with Section 79 (1) (f) and 79 (1) (c) of the Electricity Act, 2003 and Regulation 119 of the Conduct of Business Regulations 1999 in Petition No. 155/MP/2016.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
319
108/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Misc. Petition for Approval under sub-section(4) of Section 28 & 79(1)(d) of Electricity Act 2003 and regulation-86 of CERC (Conduct of Business) Regulations�1999 for  determination of 

i) Trued up Fees and Charges for 2009-14 block
ii) Fees and Charges for the period 2014-19 block. 

For Asset-I: 1099.803 Kms of Fibre optic Communication System in lieu of existing Microwave. (DOCO: 01.04.2012), Asset II: 1628.966 Kms of Fibre optic Communication System in lieu of existing Microwave. (DOCO: 01.01.2013), Asset III: 493.064 Kms of Fibre optic Communication System in lieu of existing Microwave. (DOCO: 01.04.2013), and Asset IV: 530.621 Kms of Fibre optic Communication System in lieu of existing Microwave. (DOCO: 01.10.2013) under � FIBRE OPTIC COMMUNICATION SYSTEM IN LIEU OF EXISTING UNIFIED LOAD DISPATCH & COMMUNICATION (ULDC) MICROWAVE LINKS IN NORTHERN REGION� Scheme.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
320
107/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

For combined assets Asset-1: 400 kV D/C Parbati Pooling Point �Amritsar line alongwith associates bays and Asset-2 : 80 MVAR bus reactor at Parbati Pooling Point along with associated bays under transmission system associated with PARBATI-III-HEP in Northern Region.

And 

Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and  Regulation-6 of   CERC (Terms and Conditions of Tariff) Regulations,  2009 and CERC (Terms and Conditions of Tariff) Regulations�  2014 for  determination of
(i) Final and Truing up Transmission tariff for 2009-14 tariff  block and 
(ii) Transmission tariff for 2014-19  tariff block 

Asset-3 : LILO of 2nd ckt of Parbati-II-Koldam T/L at Pooling station and LILO at Parbati-III (Portion c-d ), Asset-4 : LILO of 2nd ckt of Parbati-II-Koldam T/L at Pooling Station along with associated bays and LILO of Parbati-III (Portion e-f) under transmission system associated with PARBATI-III-HEP in Northern Region.
Order reserved
321
100/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
02 nos 400kV line bays along with 02 nos 80 MVAR Switchable Line Reactors at 400kV Siliguri S/S and 02 nos 400kV line bays (for 400kV D/C Siliguri-Bongaigaon TL) at Bongaigaon S/S  under Transmission schemes for enabling import of NER/ER surplus power by NR in Eastern Region.
Additional information awaited as per order u/r 7(7) of 2014 Tariff Regulation by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
322
98/MP/2017
NTPC Limited
Petition under Section 79 of the Electricity Act, 2003 read with Regulation 14 (3) (ii) and Regulation 8 (3) (ii) of the CERC (Terms and Condition of Tariff) Regulations 2014 for approval of Expenditure on installation of various Emission control systems as detailed in this Petition for compliance of Ministry of Environment and Forests and Climate Change, Government of India notification dated 07.12.2015 mandating compliance with revised environmental norms for thermal power stations.
Additional information for final order to be filed by Petitioner,Respondent
323
19/RP/2017 in 94/TT/2011
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Petition seeking review of order dated 16.11.12, 02.01.2013, 17.02.2016 and 23.02.2016 passed by the Hon'bie Commission in Petition No. 94/TT /2011.
Hearing
324
18/RP/2017 in 92/TT/2011
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Petition Seeking Review of Order dated 16.11.2012 passed by the Hon'ble CERC in 92/TT/2011.
Hearing
325
95/MP/2017
Welspun Energy Private Limited (WelspunEnergy)
Petition under Section 79 of the Electricity Act, 2003 in relation to disputes arising out  of the Power Purchase Agreement dated 26.07.2016 between Petitioner herein, i.e. Welspun Energy Private Limited and Solar Energy Corporation of India Limited
Order reserved
326
94/MP/2017
Bharat Aluminium Company Limited (BALCO)
A petition under Section 79 (1)(f) of the Electricity Act, 2003 read with the relevant provisions of CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010 for seeking quashing of notices dated 16.03.2017, 24.03.2017, 06.04.2017 and e-mail dated 19.04.2017 sent by the Power Grid Corporation of India Ltd and refund of the payments made under protest by the Petitioner against the impugned invoices
ROP Issued
327
93/MP/2017
Kerala State Electricity Board Limited (KSEB Ltd.)
Petition seeking clarification on the claim of 'other charges' in the monthly energy bills and claim of Annual Fixed Cost over and above that approved by Hon'ble CERC.
Additional information for final order to be filed by Petitioner
328
85/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for determination of Transmission Tariff from DOCO to 31.03.2019 for 1x1500 MVA, 765/400 kV ICT at Vindhyachal Pooling Station alongwith associated bays - Asset-1 (Ant. DOCO ? 01.06.2017), under ?Transmission System associated with Vindhyachal-V (500 MW) Project of NTPC (Part-A)? in Western Region for tariff block 2014-19 period
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
329
16/RP/2017 in TT/384/2014
NTPC Limited
Review of the Order dated 16.01.2017 passed by the Hon�ble Commission approving the transmission tariff for a section of the 400 kV (Quad) 2xS/C Parbati-Koldam transmission line Circuit-II (starting from LILO point of Parbati (Banala) Pooling Station to Koldam HEP) in Northern Region for Tariff block 2014-19 period under Regulation 86 of Central Electricity Regulatory Commission (Conduct of business) Regulations, 1999 and Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014.
Hearing
330
15/RP/2017 in 156/TT/2015
NHPC LTD
Petition under Section 94(1) (f) of the Electricity Act, 2003, for Review of tariff order dated 29.12.2016 passed by the Central Commission in Petition No. 156/TT/2015.
Hearing
331
74/GT/2017
KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL)
Petition Under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of MTPS Stage-II (2x195 MW) from anticipated COD of Unit-1 to 31.03.2019
Hearing
332
68/MP/2017
DB Power (Madhya Pradesh) Limited (DBPMPL)
Petition under sections 79(1)(c) read with 79(1)(f) of the Electricity Act, 2003, inter alia seeking setting aside/quashing of invocation & encashment by the Respondent of  the Bank Guarantee furnished by the Petitioner in relation to the grant of LTA to the Petitioner qua its proposed Thermal Power Project in Singrauli District, Madhya Pradesh and consequent direction to the Respondent to reimburse the encashed amount along with interest to the Petitioner.
Hearing
333
66/MP/2017
NTPC Limited
Petition under Part 7 Regulation 4 of the CERC (Indian Electricity Grid Code) Regulations 2010 (as amended) read with Regulation 111 of CERC (Conduct of Business) Regulations, 1999 in regard to provision 6.3 A of the Grid Code.
Hearing
334
59/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under Regulation- 86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Solapur STPP � Solapur (POWERGRID) 400 kV D/C (Quad) 2nd Transmission Line alongwith associated bays at Solapur (POWERGRID) Sub-Station under �Transmission System associated with Solapur STPP (2x660 MW) Part-A� in Western Region for tariff block 2014-19 period.
ROP Issued
335
58/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Assets under SRSS XXIII
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
336
56/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2009  for  determination of Transmission Tariff  of Asset-I:400 kV D/C (Quard) Dehradun- Abdullahpur transmission line along with associated bays at Dehradun and Abdullahpur Substation and Asset-II:400kV D/C(Quard) Dulhasti-Kishenpur �single circuit strung along with associated bays at kishenpur end  under �Northern Region Strengthening Scheme � XXIV�
Reply / additional information as per ROP to filed by Petitioner
337
45/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations �2014 for determination of Transmission Tariff from anticipated DOCO to 31.03.2019 for Transmission Asset �(a) LILO of Gazuwaka - Vijayawada 400kV S/C line at Vemagiri Pooling Station along with associated bays and (b) Establishment of 765/400kV GIS Pooling Station at Vemagiri with 2X1500MVA 765/400kV Transformers, 2nos 240 MVAR 765kV & 1 no. 80 MVAR 400kV Bus Reactors at Vemagiri and 2nos 765kV bays along with 1 no. 240 MVAR switchable line reactor each at Vemagiri & Srikakulam pooling stations each for both circuits of Srikakulam PS - Vemagiri PS 765kV D/C line under �Sub-Station Works Associated with System Strengthening in Southern Region for Import of Power from Eastern Region�. (Anticipated DOCO:31.12.2016)
Order reserved
338
44/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business)
Regulations‟1999 and CERC (Terms and Conditions of Tariff) Regulations ‟2014 for determination of Transmission Tariff from anticipated DOCOs to 31.03.2019 for Assets (09 nos)  under Eastern Region Strengthening Scheme-V in Eastern Region.
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
339
38/TT/2017
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Asset-I: 01 No. of 01x125 MVAR Bus Reactor (1st) and associated bay equipments at 400 KV Durgapur S/S, Asset-II: 01 No. of 1x125 MVAR Bus Reactor (2nd) and associated bay equipments at 400 KV Durgapur S/S   , Asset-III: 01 Nos of 125 MVAr Bus Reactor (1st) at Rengali Substation, Asset-IV: 01 Nos of 125 MVAr Bus Reactor (2nd) at Rengali Substation, Asset-V: Installation of 01x125 MVAR Bus Reactor by replacing existing 1x50 MVAR Bus Reactor at 400 KV Rourkela S/S Asset-VI: Installation of 01x125 MVAR Bus Reactor in Parallel with existing 50(3X16.67) MVAR Bus Reactor at Biharsharif S/S Asset-VII: Installation of 2x125 MVAR Bus Reactor in Parallel with existing 2X50 MVAR Bus Reactor at Jamsedpur S/S Asset-VIII: Procurement of one 500 MVA, Single phase unit of 765/400 kV ICT for Eastern Region to be stationed at Gaya Sub-station (diverted to Ranchi) Asset-IX: Installation of 1X125 MVAR Bus Reactor at 400 kV Gazuwaka S/S Asset-X: Converting 2X80 MVAr Line reactor to 2X80 MVAr switchable line reactor  at Gorakhpur end for 400 kV Barh-II-Gorakhpur transmission line under Eastern Region Strengthening Scheme IX in Eastern Region.
Hearing
340
35/MP/2017
Uttar Pradesh Rajya Vidhut Utpadan Nigam Ltd. (UPRVUNL)
Petition under Regulation (4) of Part 7 of the CERC (Indian Electricity Grid Code) Regulations, 2010 read with Regulation 111 of CERC (Conduct of Business) Regulations, 1999 seeking relaxation of Regulation 5.2 (f) regarding requirement of implementing RGMO / FGMO for vintage units of UPRVUNL
Hearing
341
34/TD/2017
Rajasthan Urja Vikas Nigam Limited (RUVNL)
APPLICATION FOR GRANT OF INTER STATE TRADING LICENSE FOR CATEGORY-1
Suggestion/Comments awaited from other organisations- Pre Listing
342
33/RC/2017
Indian Energy Exchange Ltd. (IEX)
Regulatory Compliance Application in compliance of Regulation 7(2) and 24 of the Central Electricity Regulatory Commission (Power Market) regulations,2010
Hearing
343
29/MP/2017
JINDAL STEEL & POWER LIMITED (JSPL)
A petition under Section 79 (1)(c) read Section 79(1)(k) of the Electricity Act, 2003 and the CERC (Open Access in Inter-State Transmission) Regulations 2008 for seeking appropriate directions upon State Load Dispatch Centre, Odisha for grant of open access in a collective transaction.
Order reserved
344
10/RP/2017 in TT/384/2014
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition under section 94(1)(f) of the Electricity Act, 2003 read with regulation 103 of The Central Electricity Regulatory Commission (Conduct of Business), Regulation 1999
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
345
9/RP/2017 in TT/312/2014
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition for review of order dated 19.12.2016 passed by this Hon'ble Commission in 312/TT/2014 titled as PKTCL Vs HPSEB and Others
Hearing
346
8/RP/2017 in TT/312/2014
NTPC Limited
REVIEW OF THE ORDER DATED 19.12.2016 PASSSED BY CERC I PETITION NO. 312/TT/2014
Hearing
347
4/RP/2017 in 156/TT/2015
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition for review of order dated 29.12.2016 passed by this Hon;ble Commission in 156/TT/2015 titled as "PKTCL Vs RRVPNL & Ors"
Hearing
348
24/MP/2017
BHARTIYA RAIL BIJLEE COMPANY LTD. (BRBCL)
Petition under Section 79(1) of the Electricity Act, 2003 read with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for issuing direction to ERLDC/ERPC to accept Declared Capacity or DC' of Unit#1 of Nabinagar TPP(4X250 MW) of BRBCL from the Successful Declaration of COD of Unit#1
Reply / additional information as per ROP to filed by Petitioner
349
23/GT/2017
BHARTIYA RAIL BIJLEE COMPANY LTD. (BRBCL)
Approval of tariff  of Nabinagar Thermal Power Project (4X250 MW) for the period from anticipated Date of Commercial Operation  of Unit-1  to 31.03.2019.
Reply / additional information as per ROP to filed by Petitioner,Respondent
350
22/GT/2017
Bhakra Beas Management Board (BBMB)
Determination of Tariff of BBMB Generating Stations for the period 2014-19
Order reserved
351
21/MP/2017
Essar Power (Jharkhand) Ltd EPJL
Petition for Relinquishment of 1100 MW of Long Term Access agreed under the Bulk Power Transmission Agreement dated 24.02.2010 under Regulation 18 read with Regulation 32 of Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009, of the subject Transmission Lines by the ESSAR Power Jharkhand Limited (3x600 MW) Thermal Power Plant, Chandwa Tehsil, District Latehar in the State of Jharkhand.
Pending as per directions of the Commission
352
16/TT/2017
Bhakra Beas Management Board (BBMB)
Determination of Tariff of BBMB Transmission systems & SLDC functions for the period 2014-19
Order reserved
353
14/MP/2017
NTPC Limited
Petition under Section 79(1)(a) and Section 79(1)(f) of the Electricity Act, 2003 read with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for relief on account of a Change in Law affecting Stage II of the Badarpur Thermal Power Station.
Additional information for final order to be filed by Petitioner,Respondent
page separator
S. No.
Petition No.
Petitioner
Subject
Status
354
11/MP/2017
GMR CHHATTISGARH ENERGY LIMITED (GCEL)
Petition under Section 79(1)(c) of the Electricity Act, 2003, read with the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and the Detailed Procedure for grant of LTA, seeking deferment of operationalization of Long Term Access of 430 MW in Northern Region as per the BPTA dated 31.03.2010 and Petition under Section 79(1)(c) of the Electricity Act, 2003, read with the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and the Detailed Procedure for grant of LTA, seeking relinquishment of Long Term Access of 386 MW in Western Region out of the total quantum of 816 MW as per the BPTA dated 31.03.2010
Hearing
355
7/GT/2017
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business) Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 6(2) of CERC (Terms and Conditions of Tariff) Regulations, 2009 for revision of generation tariff from 24.03.2014 to 31.03.2014 in respect of Parbati-III Power Station.
Interim order under preparation
356
6/GT/2017
NHPC LTD
Petition under 79(1) & 86 of the CERC (Conduct of Business) Regulations, 1999, Section 62(1)(a) of the Electricity Act, 2003 and Regulation 7 of CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Tariff for period 2014-19 in respect of Parbati--III Power Station.
Interim order under preparation
357
5/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79(1)(f) and 79(1)(b) of the Electricity Act, 2003 in connection with the disputes and differences arising under the Power Purchase Agreement dated 12.05.2008 between the Petitioner and Respondent no. 1.
Hearing
358
4/MP/2017
Maithon Power Limited (MPL)
Petition under Section 79(1)(f) and 79(1)(b) of the Electricity Act, 2003 in connection with the disputes and differences arising under the Power Purchase Agreement dated 18.07.2008 between the Petitioner and Respondent no. 1.
Hearing
359
249/GT/2016
Teesta Urja Limited (TUL)
Determination of Tariff of 1200 MW Teesta III Hydro Electric Project Sikkim
Hearing
360
248/MP/2016
KUDGI TRANSMISSION LIMITED (KTL)
Revision of SCOD due to reasons beyond the control of the TSP
Hearing
361
246/MP/2016
Coastal Energen Private Limited (CEPL)
Relinquishment of 542 MW LTOA.
ROP Issued
362
244/MP/2016
NTPC Limited
Measurement of GCV of Coal received at the plant site of NTPC Power Stations
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
363
66/RP/2016 in 41/IA/2016 in TT/528/2014
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Review Petition seeking recall of order dated 17.02.2016.
Hearing
364
65/RP/2016 in 32/IA/2016 in 018/TT/2015
GREENKO BUDHIL HYDRO POWER PRIVATE LIMITED (GBHPPL)
Application seeking recall of order dated 23.02.2016.
Hearing
365
241/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations?1999 and CERC (Terms and Conditions of Tariff) Regulations ?2014 for determination of Transmission Tariff from DOCO to 31.03.2019 for Asset 1: 400/220 kV Kankroli Substation: (+) 400 MVAR / (-) 300 MVAR SVC Under ?Static VAR    Compensators (SVCs) in Northern Region?.
Order reserved
366
237/TT/2016
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED APTRANSCO
Petition for Determination of tariff of the Inter-State transmission lines connecting two States for the APTRANSCO owned transmission lines system as per the Central Electricity Regulatory Commission's order dated14.3.2012 in Petition No.15 Suo-Moto  2012, for inclusion in POC Transmission charges in accordance with Central Electricity Regulatory Commission (TermsandConditionsof Tariff)Regulations,2014
Order reserved
367
231/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for 2 nos. 765kV Line bays along with 2x240MVAR Switchable Line reactors each at Srikakulam & Angul for termination of both circuit of 765kV D/C Srikakulam - Angul Transmission line, 2x1500MVA 765/400kV ICT's and 1x330 MVAR 765kV Bus Reactor at Srikakulam under �Common System associated with East Coast Energy private limited and NCC power projects limited LTOA generation projects in Srikakulam Area -part-C� in Southern Region and Eastern region
Order reserved
368
230/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from anticipated DOCO to 31-03-2019 for 765 kV D/C Srikakulam � Angul Transmission line under �Common System associated with East Coast Energy private limited and NCC power projects limited LTOA generation projects in Srikakulam Area -Part-A� in Southern region and Eastern region
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
369
220/MP/2016
West Bengal State Electricity Distribution Company Limited WBSEDCL
Petition under Section 79 (1) (f) of the Electricity Act, 2003 seeking adjudication of dispute between West Bengal State Electricity Distribution Company Limited and NTPC Ltd.and Damodar Valley Corporation relating to over invoicing and recovery of Rs. 1192.67Crores.
Hearing
370
217/MP/2016
Thermal Powertech Corporation India Limited TPCIL
Petition seeking compensation on account of Changes in Law under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 10 of the Power Purchase Agreement dated 01.04.2013 entered into between Thermal Powertech Corporation India Ltd and the Distribution Companies in the States of Andhra Pradesh and Telangana
Pending as per directions of the Commission
371
216/MP/2016
bhopal dhule transmission company limited (BDTCL)
Petition under Section 63 and 79(1)(f) read with Section 79(1)(c) of the Electricity Act, 2003 seeking compensatory and declaratory relief under the Transmission Services Agreement dated 07.12.2010 on account of Change in Law and Force Majeure events.
Order reserved
372
215/TT/2016
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Approval under regulation-86 of CERC (Conduct of Business) Regulations�1999 and CERC (Terms and Conditions of Tariff) Regulations�2014 for determination of Transmission Tariff from DOCO to 31-03-2019 for Asset-1) 2 Nos. 400KV Line bays at Narendra (New), 2 Nos. 400KV Line bays at Madhugiri (Tumkur), 2X63MVAR (fixed) line reactors (with 600ohm NGRs) at Narendra (New) & 2X63MVAR (fixed) line reactors (with 600ohm NGRs) at Madhugiri (Tumkur) for Narendra (New) - Madhugiri (Tumkur)  765KV D/C line (initially charged at 400KV), Asset-2) 2 Nos. 400KV Line bays at Madhugiri (Tumkur) for Madhugiri (Tumkur) - Bidadi 400KV D/C (Quad) line & Asset-3) 2 Nos. 400KV Line bays at  Bidadi for Madhugiri (Tumkur) - Bidadi 400KV D/C (Quad) line under �Sub Station Extension works associated with transmission system required for evacuation of power from Kudgi TPS (3 X 800MW in Phase �I ) of NTPC Limited�  in Southern Region
Order reserved
373
211/MP/2016
Jindal Power Limited (JPL)
Petition under Section 19 of the Electricity Act, 2003 read with Regulation 14 and Regulation 7 of the Central Electricity Regulatory Commission (Procedure, Terms and Conditions for grant of trading license and other related matters) Regulations, 2009 seeking revocation of the Inter State Trading License granted to M/s Global Energy Private Limited.
Hearing
374
197/MP/2016
DAMODAR VALLEY CORPORATION (DVC)
Requirement of revenue in relation of Pension & Gratuity of employees and retired employees during the tariff period 2014-19
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
375
52/RP/2016 in TT/411/2014
Parbati Koldam Transmission Company Limited (PKTCL)
Review Petition in the matter of Review of the Order dated 30.07.2016 passed by this Hon?ble Commission in Petition No. 411/TT/2014 titled as 'Power Grid Corporation of India Limited vs. Rajasthan Rajya Vidyut Prasaran Nigam Limited &Ors' under section 94(1)(f) of the Electricity Act, 2003 read with Regulation 103 of the Central Electricity Regulatory Commission (conduct of business) regulations, 1999.
Order reserved
376
179/MP/2016
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (f) OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES ARISING UNDER THE POWER PURCHASE AGREEMENT DATED 27/11/2013 BETWEEN THE PETITIONER AND THE RESPONDENT
Additional information for final order to be filed by Petitioner,Respondent
377
176/MP/2016
KSK Mahanadi Power Company Limited (kskmahanadi)
PETITION UNDER SECTION 79 (1) (f) OF THE ELECTRICITY ACT, 2003 FOR ADJUDICATION OF DISPUTES ARISING UNDER THE POWER PURCHASE AGREEMENT DATED 31/07/2012 BETWEEN THE PETITIONER AND THE RESPONDENTS
Pending as per directions of the Commission
378
172/MP/2016
NTPC Limited
Petition under Section 62(a) and 79(1)(a) of the Electricity Act, 2003 read with Regulation 8(3)(ii) and 8 (7) of the CERC (Terms and Conditions of Tariff) Regulations, 2014 read with Regulation 111 of the CERC (Conduct of Business) Regulations, 1999 for recovery of Additional Expenditure incurred due to sharing of transportation cost of fly ash consequent to Ministry of Environment and Forest, Government of India Notification dated 25.01.2016 as ?Change in Law? event.
Reply / additional information as per ROP to filed by Petitioner,Respondent
379
171/MP/2016
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79 (1) (b) and (f) of the Electricity Act, 2003 for adjudication of claims towards compensation arising out of Change In Law and consequential reliefs as per provisions of the PPA dated 26.02.2014 between the Petitioner and Respondents herein.
Additional information for final order to be filed by Petitioner,Respondent
380
169/MP/2016
KSK Mahanadi Power Company Limited (kskmahanadi)
Petition under Section 79 (1) (b) and (f) of the Electricity Act, 2003 for adjudication of claims towards compensation arising out of Change In Law and consequential reliefs as per provisions of the PPA dated 31.07.2012 between the Petitioner and Respondents herein.
Pending as per directions of the Commission
381
151/MP/2016
Dakshin Gujarat Vij Company Limited DGVCL
PETITION UNDER SECTION 79 (1) (c) READ WITH SECTIONS 142 AND 146 OF THE ELECTRICITY ACT, 2003 REGARDING NON COMPLIANCE OF THE ORDER DATED 08/06/2013 PASSED BY THE HON'BLE COMMISSION IN PETITION NO. 245/MP/2012 AND FOR CONSEQUENTIAL DIRECTIONS
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
382
142/GT/2016
NTPC Limited
Tariff Petition for approval of tariff for Mouda-II (2x660 MW) from anticipated COD of U#1 to 31.3.2019
Hearing
383
137/MP/2016
GMR Kamalanga Energy Limited (GKEL)
Petition for relinquishment of Long Term Open Access
ROP Issued
384
133/MP/2016
Sasan Power Limited (SPL)
Petition under Section 79 of the Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding and Article 13.2(b) of the Power Purchase Agreement dated 07.08.2007 executed between Sasan Power Limited and the Procurers for compensation due to Change in Law impacting revenues and costs during the Operating Period
Additional information for final order to be filed by Petitioner,Respondent
385
127/MP/2016
IND BARATH ENERGY UTKAL LIMITED (IBEUL)
PETITION UNDER SECTION 79 OF THE ELECTRICITY ACT, 2003 FOR ADJUCATION OF THE MATTER BETWEEN THE PARTIES IN RELATION TO NON RELEASE OF BANK GUARANTEE FURNISHED WITH RESPECT TO LONG TERMS OPEN ACCESS GRANTED TO THE PETITIONER
Hearing
386
115/MP/2016
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION (TANGEDCO)
Excess tax reimbursed by Southern Beneficieries on account of wrong calculation of income tax by NLC.
Hearing
387
91/MP/2016
Tata Power Delhi Distribution Limited (TPDDL)
Petition under Section 79 (1) (f) and (k) of the Electricity Act, 2003 read with Regulation 54 & 55 of CERC (Terms & Conditions of Tariff) Regulations 2014 along with Regulation 111 and Regulation 115 of the CERC (Conduct of Business) Regulations, 1999, seeking re-determination of gross station heat rate of Badarpur Thermal Power Station as provided under Regulations 36 (C) (a) (ii) of the CERC (Terms & Conditions of Tariff) Regulations 2014 along with Affidavit
Hearing
388
86/MP/2016
BSES YAMUNA POWER Ltd. (BYPL)
Seeking decommissioning and/or closure of BTPS Stage-I
Hearing
389
81/TT/2016
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval under Sections 61, 62 and 79 (1) (c) & 79 (1) (d) of the Electricity Act, 2003 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of Annual Fixed Cost and determination of tariff for the licensed transmission business for the financial years 2015-16, 2016-17, 2017-18 and 2018-19 for 400 kV Srinagar-Srinagar PH line as per Hon?ble Central Electricity Regulatory Commission?s order dated 31 January 2013 against Petition number 133/ MP/2012
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
390
80/TT/2016
Power Transmission Corporation of Uttarakhand Limited (PTCUL)
Approval under Sections 61, 62 and 79 (1)(c) & 79 (1) (d) of the Electricity Act, 2003 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for approval of Annual Fixed Cost and determination of tariff for the licensed transmission business for the financial years 2015-16, 2016-17, 2017-18 and 2018-19 for 400 KV Srinagar Substation as per Hon'ble Central Electricity Regulatory Commission's order dated 31 January 2013 against Petition number 133/MP/2012.
Hearing
391
77/MP/2016
Coastal Gujarat Power Limited (CGPL)
Petition  Under Article 13 of the Power Purchase Agreement dated 22.04.2007 read with Clause 4.7 of  the competitive Bidding Guidlines and section 79 of the Electricity Act 2003
Additional information for final order to be filed by Petitioner,Respondent
392
64/MP/2016
BSES Rajdhani Power Limited (BRPL)
Petition under Section 79 (1) (f) of the Electricity Act, 2003 read with Regulation 30(7) of CERC (Terms and Conditions of Tariff), Regulations, 2014 seeking adjudication of dispute between Petitioners, i.e., BSES Rajdhani Power Limited & BSES Yamuna Power Limited with NTPC Ltd.
Hearing
393
61/GT/2016
GMR Kamalanga Energy Limited (GKEL)
Petition under section 62 and 79(1) (a) of the Electricity Act, 2003 read with CERC (Terms and Condtions of Tariff)  Regulation, 2014 for determination of Generation Tariff for the period 01.4.2014 to 31.03.2019 and Truing up of Generation Tariff from COD to 31.03.2014 in resepct of 262.5 MW gross capacity sale from 3 X 350 MW Kamalanga Thermal Power Plant of GMR -Kamalanga Energy Limited(GKEL) to GRIDCO acting as nominees of Government of Odisha for procuring power for the Odisha Distribution companies
Order reserved
394
38/MP/2016
Lanco Babandh Power Ltd
Petition u/s 79(1) ( c) read  with  79(1) (f) and 79 (1) (k) of the E. Act, 2003 inter alia seeking a decalration that the factors/ events namely dely in forest clearance of land for main plant cancellation of  allocated coal block to the Petitioner, non-signing of Fual supply agreement dely ihn acquisition /procurement of land for mkain plant, delay in approval of Land for Ash Pond by state of Odhisa, dely in clearance for construction of dedicated transmission line from Ministry of Power in the construction of the  2 x 660 MW Coal based thermal Power Plant located in dhenkenal district Odisha for Force majeure events under BPTA dated 24.02.2010 seeking extension of time period for achieving the Commercial Operation date of the project and other consequential reliefs under the BPTA dated 24.02.2010
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
395
33/MP/2016
NTPC Limited
Petition under section 79(1)(a)  of the Electricity Act, 2003 read with CERC (Terms and Conditions of  Tariff) Regulations, 2014 for relief on account of a Change in Law affecting the Badarpur Thermal Power Station.
Hearing
396
51/MP/2016
Bharat Aluminium Company Limited (BALCO)
An application for Regulatory Compliance of order dated 30.10.2014 passed in Petition No.134/MP/2011 and Order dat ed 09.10.2015 passed in Petition No. 124/RC/2015 under Section 142 and 146 of the Electricity Act, 2003
Pending as per directions of the Commission
397
10/MP/2016
Jaiprakash Power  Ventures Limited
Petition u/s 79(1) (f) and Sec- 19 of E. Act, 2003 read with Regulations 14 of CERC(procedures, Terms and Condtions for grant of trading license and other realted matters) Regualtions, 2009 seeking refund of the Late payment of Surchages illegally retained by the Respondent No. 1 under Power Purchase Agreement dat ed 30.0.5 2011 alongnwith interest and initiation of proceedings for revocation of the Inter State Trading License of the Respondent No.1
Pending as per directions of the Commission
398
03/MP/2016
M/s Vendanta Limited (Formerly Sesa  Sterlite Limited)
Petition  for the relinquishment of the Long Term Open Access under the Bulk Power Transmission Agreement dated 5th July, 2010 under Regulation 2010 read with Regulation 32 of the CERC(Grant of Connectivity, Long Terms Access and Medium Terms Open Access in inter State Transmission and related  matters ) Regulations, 2009
ROP Issued
399
312/MP/2015
Meenakshi Energy Private Limited (MEPL)
Petition under Section 79(1)(f) of the Electricity Act, 2003 qua adjudication  over paymnent of transmission charges and other liabilities under the Bulk Power Transmission agreement between Meenakshi Energy Private Limited, a generating  company, and PGCIL the Central Transmission Utility.
Order reserved
400
311/MP/2015
Tata Power Delhi Distribution Limited (TPDDL)
Petition praying for appropriate directions restraining the Respondent from recovering the Energy Charge Rate strictly in terms of the Tariff Regulations framed b y this Honble Commission
Hearing
401
309/GT/2015
Pragati Power Corporation Limited (PPCL)
Filing of Petition under Sec 62 and 79(1) (a) & (b) of the Electricity Act, 2003, CERC (Terms and  Conditions of Tariff) regulations, 2009 and sec-86 of CERC(CB)  Regulations, 1999 for True up of  Generation Tariff of  Pragati-III CCPS 1371.2 MW pwoer plant  of Pragati Power Corporation Limited for the period from COD of GT#1 up to 31.03.2014 of MYT 2009-2014
Hearing
402
305/MP/2015
Adhunik Power and Natural Resources limited.
Petition under Section 79 of the Electricity Act, 2003 read with  provisions of the Power Supply agreement dated 05.1.2011 and Power Purchase Agreement dated 25.03.2011 for directions to make Energy Charges as pass-through based on the actual fuel cost incurred by the Petitioner
Order reserved
page separator
S. No.
Petition No.
Petitioner
Subject
Status
403
303/MP/2015
M/s Vedanta Limiited
Petition for the relinquishment of the long term open access under the bulk power transmission agreement dated  5.1.2011 under Regulaiton 18 read with Regulation 32 of the CERC (Grant of Connectivity, Long Term Access and Medium Term Access in inter-State transmission and related matters) Regulations, 2009
ROP Issued
404
014/SM/2015
Suo Motu
Notice under Section 19 of the Electricity Act 2003 for revocation of the inter-State transmission licence granted to Talcher II Transmission Company Ltd. Talcher II Transmission Company Ltd.
Pending as per directions of Higher Court
405
13/SM//2015
Suo Motu
Revocation of transmission licence under Section 19 of the Electricity Act, 2003 granted to North Karanpur Transmission Compnay Limited
Pending as per directions of Higher Court
406
221/GT/2015
Pragati Power Corporation Limited (PPCL)
Tariff Petition under section 62 and 79(1) (a) & (b) of the Electricity Act, 2003 and CERC Tariff Regulation 2014 for determination of Generation Tariff of Pragati-III CCPS 137.2 MW Power plant of Pragati Power Corporation Limited for the period  from 01-04-2014 to 31-03-2019 of current MYT
Hearing
407
183/MP/2015
Meenakshi Energy Private Limited (MEPL)
For adjudication of disputes over  an increas in tariff sought by the Petitioner for its Power plant selling to AP and telangana
Pending as per directions of the Commission
408
092/MP/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Petition seeking directions with regard to difficulties in impementing some of the directions given in the Order dated 16.02.2015 in Petition Nos 92/MP/2014 alongwith IA Nos. 43/2014, 51/2014, 54/2014, 56/2014 & 59/2014, Petition NO 376/MP/2014, Petition NO 382/MP/2014, Petition NO 393/MP/2014 and Review petition No. 25/RP/2014.
Order reserved
409
064/TT/2015
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
APPROVAL OF TRANSMISSION TARIFF FOR ËSSAR GUJARAT TPS AND EXTENSION OF BACHAO SUBSTATION UNDER TRANSMISSION SYSTEM FOR CONNECTIVITY OF ESSAR POWER GUJARAT LIMITED IN WESTERN REGION FOR TARIFF BLOCK 2014-19
Hearing
410
018/SM/2015
Suo Motu
Suo motu Petition in the matter of declaration of commercial operation of Units 20 to 50 of Mundra Ultra Mega Power Project developed by Coastal Gujarat Power Ltd
Additional information for final order to be filed by Petitioner,Respondent
411
MP/463/2014
GMR Vemagiri Power Generation Limited.
Petition under Section 79(I)(f) of the Electricity Act, 2003 for a direction to the Respondents to pay Additional Fixed Charge of Rs.0.439/KWH for the balance period of PPA.
Pending as per directions of the Commission
412
RC/441/2014
Manikaran Power Limited MPL
Regulatory compliance for change of Category-II trading License to Category I for Interstate Trading Power.
Hearing
page separator
S. No.
Petition No.
Petitioner
Subject
Status
413
GT/130/2014
NTPC Limited
Petition Under section 62 and 79(I)(a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity regulatory Commission (Conduct of Business) regulations, 1999 for approval of tariff of Barh Super thermal Power Station Stage-II (2X660 MW) for the period  from anticipated Date of Commercial operation of 1st Unit (Unit-IV) to 31.03.2019.
Hearing
414
MP/041/2014
Aurum Renewables Energy Pvt. Ltd. AREPL
Petition for adjustment of capacity utilization, adjustment of tariff, extension of time for execution of project and other consequential reliefs.
Pending as per directions of the Commission
415
MP/024/2014
Adani  Power Limited.
Petition under Section 79 of the Electricity Act, 2003 to evolve a mechanism/adjust tariff on account of subsequent events rendering Petitioners power plant commercially unviable due to unprecedented, unforseeable and uncontrollable events including enactment of new Coal pricing regulation by Indonesian Government and depreciation of Indian Rupee vis-a-vis US Dollar and Levy MAT as per amendment of Section 115JB of I.T Act, 1961.
Hearing
416
MP/014/2014
KVK ENERGY VENTURES PVT. LTD. (KVKENERGY)
petition for adjustment of Tariff, extension of time for execution of project and other consequential reliefs.
Pending as per directions of the Commission
417
MP/327/2013
DIWAKAR SOLAR PROJECTS PRIVATE LIMITED (DIWAKAR_SOLAR)
For adjustment of tariff, extension of time for execution of project and other consequential reliefs.
Pending as per directions of the Commission
418
009/2009
MPPTCL
Payment of interest on the excess amount recovered as per order dated 23.10.2000 and order dated 30.09.2008 in Petition No.10/2000 and order dated 23.03.2007 in Petition No. 6/2004 in respect of wheeling charges payable to Gridco for wheeling of Central Sector Power from NTPC power station is in Eas
Pending as per directions of Higher Court
419
130/2009
Suo Motu
Maintenance of Grid Discipline-non-compliance of provisions of the Indian Electricity Grid Code by TNEB
Pending as per directions of Higher Court
420
081/2009
Suo Motu
Maintenance of Grid Discipline – Non  ‐compliance of provisions of the Indian Electricity Grid Code by Tamil Nadu Electricity Board.
Pending as per directions of Higher Court
421
080/2009
Suo Motu
Maintenance of Grid Discipline-Compliance of provisions of  the Indian Electricity Grid Code by Transmission Coporation of Andhra Pradesh Ltd.
Pending as per directions of Higher Court
422
121/2007
POWER GRID CORPORATION OF INDIA LIMITED (POWERGRID)
Revision of tariff for the block years 2001-04 and 2004-09 in terms of  the interpretation of tariff regulations by Appellate Tribunal for Electricity.
Pending as per directions of Higher Court
423
131/2007
Suo Motu
Default in payment of Unscheduled Interchanges (UI) charges for the energy drawn in excess of her drawal schedule (UP).
Pending as per directions of Higher Court