FINAL TARIFF ORDERS 2008

Pet. No.
Subject
Date of Hearing
Date of Order
28/2007
Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Simhadri Super Thermal Power Station (1000 MW) -Corrigendum to the order dated 18.6.2008 NTPC Limited, New Delhi
-
24-12-2008
29/2007
Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Ramagundam Super Thermal Power Station, Stage-I and Stage II(2100 MW) -Corrigendum to the order dated 30.7.2008 NTPC Limited, New Delhi
-
24-12-2008
32/2007
Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Farakka Super Thermal Power Station (1600 MW) -Corrigendum to the order dated 22.7.2008 NTPC Limited, New Delhi
-
24-12-2008

Review
9/2007
In
163/2004
Review of the order dated 30.11.2006 in Petition No. 163/2004 regarding determination of tariff in respect of Tanda TPS for the period 1.4.2004 to 31.3.2009. NTPC Limited, New Delhi
18-09-2008
15-12-2008

27/2007
Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Kahalgaon Super Thermal Power Station, Stage-I (840 MW)-Corrigendum to the order dated 29.9.2008 NTPC Limited, New Delhi
-
11-12-2008

32/2008
In
53/2008
Approval of provisional tariff for Mejia Thermal Power Generating Station, Unit Nos.5 & 6 (250 MW each) . Damodar Valley Corporation
07-08-2008
17-11-2008

Review
101/2008
In
29/2007
Review of order dated 30.7.2008 in Petition No.29/2007 approving revised fixed charges of Ramagundam Super Thermal Power Station, Stage-I and Stage-II (2100 MW) for the period 2004-09 after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06. NTPC Ltd, New Delhi
07-10-2008
15-10-2008

155/2007

Approval of tariff in respect of Vindhyachal STPS Stage-III (1000 MW) for the period from 1.12.2006 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
12-02-2008
31-07-2008

29/2007
Approval of revised fixed charges for the period 2004-09, after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Ramagundam Super Thermal Power Station, Stage I and Stage II (2100 MW) NTPC Ltd, New Delhi
23-10-2007
30-07-2008

84/2007
Approval of tariff of Feroze Gandhi Unchahar Thermal Power Station, Stage-III (210 MW) for the period from the date of commercial operation till 31.3.2009. NTPC Ltd, New Delhi
13-12-2007
10-07-2008

22/2007
Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2004 to 31.3.2009 in respect of Rihand STPS Stage-I (1000 MW). NTPC Ltd, New Delhi
23-10-2007
10-07-2008

26/2008
In
22/1999
Review of order dated 7.1.2008 - Approval of Tariff for Kayamkulam Combined Cycle Power Project for the period 1.1.1999 to 31.3.2004. Kerala State Electricity Board, Thiruvananthpuram
17-06-2008
23-06-2008

118/2007
Approval of tariff for NLC TPS-II, Stage-I (630 MW) and Stage-II (840 MW) for the period from 1.4.2004 to 31.3.2009. Neyveli Lignite Corporation Limited
26-02-2008
04-06-2008

47/2008
In
179/2004
Petition for review of order dated 31.1.2008 in Petition No.179/2004- Determination of generation tariff in respect of Talcher STPS Stage-II (2000 MW) for the period 1.4.2004 to 31.3.2009. Tamil Nadu Electricity Borad, Chennai
24-04-2008
29-05-2008

126/2007
Approval of revised fixed charges considering the impact of additional capital expenditure incurred during the period 2004-05 to 2006-07 and impact of year-wise pooled lignite price for the period 2004-09 determined on energy charges and capacity charges for NLC TPS -I (Expansion) (2x210 MW). Neyveli Lignite Corporation Limited
22-11-2007
28-05-2008

34/2001
Approval of tariff in respect of Ramagundam STPS (2100 MW) for the period 1.4.2001 to 31.3.2004. NTPC Limited. New Delhi
-
27-05-2008

164/2007
In
140/2005
Review of order dated 15.10.2007 in Petition No.140/2005 for approval of tariff of Ramagundam STPS Stage III (500 MW) for the period 25.3.2005 to 31.3.2009. Tamil Nadu Electricity Board, Chennai
12-02-2008
26-05-2008

29/2002
Approval of tariff in respect of Ramagundam STPS (2100 MW) for the period 1.11.1997 to 31.3.2001. NTPC Limited, New Delhi
-
26-05-2008

I.A. No. 49/2008
157/2004
Approval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) for the period from 1.4.2004 to 31.3.2009. National Thermal Power Corporation Ltd.
22-01-2008
20-02-2008

179/2004
Approval of tariff in respect of Talcher STPS, Stage-II (2000 MW) for the period 1.4.2004 to 31.3.2009. NTPC Limited.
22-05-2007
31-01-2008

40/2001
Approval of tariff in respect of National Capital Thermal Power Station, Dadri for the period 1.4.2001 to 31.3.2004. National Thermal Power Corporation Ltd.
-
25-01-2008

170/2007
Adoption of tariff for supply of electricity from the Krishnapatnam Ultra Mega Power Project of Coastal Andhra Power Limited. Coastal Andhra Power Limited.
-
25-01-2008

36/2001
Approval of tariff in respect of Farakka STPS (1600 MW) for the period 1.4.2001 to 31.3.2004. National Thermal Power Corporation Ltd.
-
25-01-2008

79/2007
In
5/2002
Review of the order dated 23.3.2007 in Petition No. 5/2002 - determination of tariff of TPS-II of NLC for the period from 1.4.2001 to 31.3.2004. Tamil Nadu Electricity Board, Chennai.
22-11-2007
11-01-2008

1/2000
Approval of tariff in respect of Feroze Gandhi Unchahar Thermal Power Station (420 MW) for the period 1.3.2000 to 31.3.2004. NTPC Limited, New Delhi.
-
03-01-2008
Pet. No.
Subject
Date of Hearing
Date of Order
20/2008
Approval of final tariff in respect of Nathpa Jhakri Hydroelectric Project (6x250 MW) for the period 1.4.2004 to 31.3.2009. Satluj Jal Vidyut Nigam Limited, Shimla
22-04-2008
31-12-2008

107/2006
Approval of final tariff in respect of Dhauliganga Hydroelectric Project Stage-I (4x70 MW) of National Hydroelectric Power Corporation Limited for the period from 1.10.2005 to 31.3.2009. National Hydroelectric Power Corporation Limited
11-09-2008
20-10-2008

22/2008
In
107/2006
Review of the order dated 13.12.2007 in Petition No. 107/2006-Approval of final tariff in respect of Dhauliganga Hydroelectric Project Stage-I (4x70MW) of National Hydroelectric Power Corporation Limited for the period from 1.10.2005 to 31.3.2009. National Hydroelectric Power Corporation Limited
17-06-2008
28-07-2008

89/2007
Approval of tariff in respect of Ranganadi Hydro Electric Project (3X135MW) for the period from 1.4.2004 to 31.3.2009. North Eastern Electric Power Corporation Ltd.
02-08-2007
30-04-2008

115/2007
Approval of tariff in respect of Ranganadi Hydro Electric Project (3x 135 MW) for the period from 12.2.2002 to 31.3.2004. North Eastern Electric Power Corporation Ltd, Shillong
27-11-2007
29-04-2008

76/2007
Approval of tariff in respect of Kopili Hydro-electric Project - Kopili Power Station (4x50MW) for the period from 1.4.2004 to 31.3.2009. North Eastern Electric Power Corporation Ltd, Shillong
02-08-2007
19-02-2008

26/2007
Approval of tariff in respect of Khandong Hydro-electric Generating Station (2X25 MW) for the period 1.4.2004 to 31.3.2009. North Eastern Electric Power Corporation Limited.
02-08-2007
14-01-2008

36/2003
Approval of tariff in respect of Kopili Hydro-electric Generating Station (4x50 MW), a component of the Kopili Hydro-electric Project, for the period from 1.4.2001 to 31.3.2004. North Eastern Electric Power Corporation Limited, Shillong
-
08-01-2007
Pet. No.
Subject
Date of Hearing
Date of Order
27/2008
I.A.No.
36/2008
Application for grant of transmission licence for Western Region System Strengthening Scheme-II (Project-B) to Western Region Transmission (Maharashtra) Pvt. Ltd. Western Region Transmission (Maharashtra) Pvt.Ltd.,Mumbai
27-11-2008
30-12-2008
28/2008
I.A.No.
38/2008
Application for grant of transmission licence for Western Region System Strengthening Scheme-II (Project-C) to Western Region Transmission (Gujarat) Pvt. Ltd. Western Region Transmission (Gujarat) Pvt.Ltd., Mumbai
27-11-2008
30-12-2008

122/2008
Determination of provisional transmission tariff for LILO of both circuits of Madurai-Trivendrum 400 kV D/C transmission line at Tirunelveli along with 1x315 MVA transformer and 1x 63 MVA Bus Reactor with associated bays and equipments under the transmission system associated with Kudankulam Atomic Power Project (2 X 1000 MW) from the date of commercial operation to 31.3.2009 in Southern Region. Power Grid Corporation of India Limited, Gurgaon
16-12-2008
16-12-2008

123/2008
Approval of provisional transmission tariff of circuit-II of 400 kV D/C Teesta (Stage-V)-Siliguri transmission line and 315 MVA, 400/220 kV, ICT-II at Baripada sub-station along with associated bays of transmission system associated with Teesta (Stage-V) HEP in Eastern Region for the period from date of commercial operation to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
11-12-2008
11-12-2008

118/2008
Determination of provisional transmission tariff for 400 kV Khandwa-Rajgarh Ckt-II along with associated bays, ICT II at Gwalior sub-station and 765/400 kV ICT-III at Seoni sub-station (DOCO 1.4.2008) & 400 kV Khandwa-Rajgarh Ckt-I along with associated bays, 63 MVAR Bus reactor at Bina sub-station (DOCO 1.5.2008) under Sipat-II transmission system of Western Region for the from 1.4.2008 and 1.5.2008 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
11-12-2008
11-12-2008

112/2008
Determination of provisional transmission tariff for 400 kV D/C Seoni-Khanadwa transmission line along with associated bays at Seoni and Khandwa sub-stations, 80 MVAR Bus Reactor, 400/220 kV ICT II and 765/400 kV ICT-II at Seoni sub-station and LILO of 400 kV D/C Sardarsarovar-Nagda transmission line along with associated bays and 315 MVA 400/220 kV ICT -I & 765 kV Sipat Seoni Ckt-II along with 3 x 80 MVAR line reactor and associated bays at Seoni sub-station under Sipat-I transmission system in Western Region for the period from 1.4.2008 & 1.5.2008 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
11-12-2008
11-12-2008

138/2007
Determination of transmission tariff from DOCO and additional capitalization up to 1.4.2007 for (i) 400 kV S/C Dulhasti-Kishenpur Transmission line with associated bays (ii) 400 kV Kishenpur-Wagoora transmission line along with associated bays at Kishenpur and Wagoora sub-stations under Dulshasti combined transmission system in Northern Region for the period 2004-09. Power Grid Corporation of India Limited
17-01-2008
01-12-2008

76/2008
Petition for revival of dormant inter-regional link of 220 kV Ujjain-Kota and Ujjain-Modak transmission line. Western Regional Load Despatch Centre, Mumbai
30-09-2008
01-12-2008

106/2008
Determination of provisional transmission tariff for (i) 80 MVAR, 420 kV Bus Reactor at Lucknow sub-station (ii) second 400 kV S/C Bareilly-Mordabad transmission line along with associated bays under Northern Region System Strengthening Scheme-I in Northern Region for the tariff period 2004-09. Power Grid Corporation of India Limited, Gurgaon
11-11-2008
27-11-2008

92/2008
Relaxation of norms related to O & M expenditure forming part of transmission tariff of transmission system associated with the Tala Hydro Electric Project, East-North Inter-Connector and Northern Region Transmission System. M/s Powerlinks Transmission Ltd., New Delhi
11-11-2008
27-11-2008

103/2008
Determination of provisional transmission tariff for (i) LILO of Kolar-Sriperumbudur (Power Grid) 400 S/C line at Kalvindapattu (Malakottaiyur) (Power Grid) along with one No. 315 MVA Auto Transformer and one 50 MVAR reactor at Kalvindapattu (Melakottaiyur) (DOCO-1.6.2008), (ii) 2nd 315 MVA Auto transformer at Kalvindapattu (Melakottiyur) sub-station (DOCO-1.7.2008) along with associated bays and equipments under transmission system associated with Kaiga 3 & 4 (2x235 MW) project from date of commercial operation to 31.3.2009 in Southern Region. Power Grid Corporation of India Limited, Gurgaon
18-11-2008
24-11-2008

I.A.No.
30/2008
In
106/2007
Determination of provisional transmission tariff for Bina-Gwalior 765 kV S/C transmission line along with bay extensions at Bina and Gwalior under transmission system associated with SIPAT II from 1.4.2007 to 31.3.2009. Power Grid Corporation of India Limited
-
15-10-2008

I.A.No.
28/2008
In
166/2007
Determination of provisional transmission tariff for (i) 400 kV Balia-Lucknow Ckt-I & II, 400 kV Balia-Mau Ckt-I, 400 kV D/C Patna-Balia transmission line including associated bays at Patna & Balia (ii) 400 kV Balia-Mau Ckt-II, 40% FSC at Lucknow on 400 kV D/C Lucknow-Balia transmission line (iii) 80 MVAR Bus Reactor at Biharshariff sub-station (iv) 400 kV Lucknow-Bareilly Ckt-I & II along with associated bays under Kahalgaon Stage II Phase I Transmission System in Northern Region for the period 2004-09. Power Grid Corporation of India Limited, Gurgaon
-
15-10-2008

45/2008
Determination of final transmission tariff for Vindhyachal STPP-Satna 400 kV D/C transmission line (3rd and 4th circuit) and 400/220 kV Satna (Powergrid) substation (extension) with 1x315 MVA transformer under Vindhyachal Stage-III transmission system in Western Region for the period up to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
15-07-2008
17-09-2008

63/2008
Approval of transmission tariff due to additional capitalization incurred during 2005-06 and 2006-07 in respect of Hiriyur sub-stations (including 315 MVA Auto Transformer), LILO of Davangere-Hoody 400 kV D/C line at Hiriyur and additional bays at Kolar and Hosur sub-station for 2nd circuit of Kolar-Hosur 400 kV D/C transmission line under System Strengthening Scheme-II in Southern Region for the period from 1.4.2005 to 31.3.2009. Power Grid Corporation of India Limited
17-06-2008
01-09-2008

123/2007
Final transmission tariff for 2nd 315 MVA auto transformer at Narendra substation associated with Kaiga-Narendra transmission system in Southern Region for the period from 1.9.2006 to 31.3.2009 and transmission tariff for additional capital expenditure incurred during 2006-07 (2nd additional capitalization) for 400 kV D/C Kaiga-Narendra transmission line and 400/220 kV sub-station at Narendra in Southern region for the period from 1.4.2006 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
-
29-08-2008

137/2007
Determination of final transmission tariff for 2nd 315 (3 x 105) MVA, 400/220 kV transformer at Indravati (OHPC) Switchyard in Eastern Region for the period from 1.5.2006 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
17-01-2008
29-08-2008

40/2008
Approval of transmission tariff due to additional capitalization incurred during 2005-06 and 2006-07 in respect of 500 MW HVDC back-to-back station at Gazuwaka (Inter-Regional asset of Eastern Region and Southern Region) and 400 KV D/C Vijaywada-Gazuwaka transmission line along with bay extension and equipments at Vijaywada and Gazuwaka (Southern Region) under augmentation of capacity of Gazuwaka HVDC back to back project (500 MW) from 1.4.2005 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
27-05-2008
28-08-2008

103/2007
Petition for determination of final transmission tariff of (i) 40% series compensation on Meramundali-Jeypore 400 kV S/C transmission line at Jeypore (Eastern Region scheme) (ii) 50% Fixed Series Compensation on 400 kV Jeypore- Gazuwaka D/C transmission line at Jeypore (inter-regional scheme between ER and SR) associated with augmentation of capacity of Gazuwaka HVDC back-to-back project for the period from 1.1.2007 31.3.2009. Power Grid Corporation of India Limited
-
21-08-2008

146/2007
Determination of final transmission tariff for (i) ICT-I along with associated bays at Meerut sub-station (ii) 800 kV Tehri- Meerut Ckt-I along with associated bays, (iii) 800 kV Tehri- Meerut Ckt-II and 400 kV S/C Meerut -Muzaffarnagar transmission line along with associated bays and (iv) ICT at Muzaffarnagar along with one no 400 kV and one No. 220 kV bay under Tehri Transmission System in Northern Region Power Grid Corporation of India Limited
10-01-2008
21-08-2008

52/2007
Approval under Section 17(3) of the Electricity Act, 2003 for transfer of ownership of switchyard associated with Faridabad Gas Power Project situated at Faridabad to NTPC. Power Grid Corporation of India Limited, Gurgaon
26-02-2008
18-06-2008

53/2007
Approval under Section 17(3) of the Electricity Act, 2003 for transfer of ownership of switchyard associated with Rajiv Gandhi Combined Cycle Power Project situated at Kayamkulam to NTPC. Power Grid Corporation of India Limited, Gurgaon
26-02-2008
17-06-2008

61/2008
Approval of provisional transmission tariff for Feeder -I of 400 kV, D/C Teesta (Stage-V)-Siliguri Transmission System, associated with Teesta (Stage-V) HEP, in Eastern Region for the period from 1.2.2008 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
10-06-2008
11-06-2008

123/2007
Final transmission tariff for 2nd 315 MVA auto transformer at Narendra sub-station associated with Kaiga-Narendra transmission system in Southern Region for the period from 1.9.2006 to 31.3.2009 and transmission tariff for additional capital expenditure incurred during 2006-07 (2nd additional capitalization) for 400 kV D/C Kaiga-Narendra transmission line and 400/220 kV sub-station at Narendra in Southern region for the period from 1.4.2006 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
27-11-2007
30-05-2008

145/2007
Determination of final transmission tariff for Bhadrawati-Chandrapur 400 kV D/C transmission line including bays at Bhadrawati (Power Grid) switching station (extension) and Chandrapur (MSEB) switchyard (extension) in Western Region for the period from 1.5.2006 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
03-01-2008
28-05-2008

141/2007
Determination of final transmission tariff of (i) 400 kV Siliguri sub-station (extension) (relevant portion), 400 kV Purnea sub-station (extension) (relevant portion) (excluding 400/220 kV, 315 MVA ICT at Purnea sub-station), 40% Fixed Series Compensation (FSC) and 5% to 15% Thyristor Controlled Series Compensation (TCSC) on each Ckt of Purnea-Muzaffarpur 400 kV D/C line at Purnea (DOCO 1.5.2006), (ii) 400/220 kV, 315 MVA ICT at Purnea sub-station (DOCO 1.6.2006) , (iii) 400/220 kV Muzaffarpur sub-station (New) (Excluding 2no, 400 kV bays at Muzaffarpur with line reactors for Muzaffarpur Gorkhpur line and ICT-II at Muzaffapur sub-station), 220 kV Muzaffarpur sub-station (BSEB Kanti) Extension (DOCO 1.9.2006) and provisional transmission tariff of 400/220 kV, 315 MVA ICT-II at Muzaffarpur sub-station (DOCO 1.6.2007) associated with Tala HEP, East-North Inter-connector and Northern Region Transmission system from DOCO to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
10-01-2008
23-05-2008

136/2007
Determination of final transmission tariff for (a) Tala-Siliguri Transmission System in Eastern Region for the period 1.10.2005 to 31.3.2009 and remaining transmission system commissioned for the period from 1.5.2006 to 31.3.2009. including additional capital expenditure for the period from date of commercial operation to 31.3.2007 in Eastern Region. Power Grid Corporation of India Limited, Gurgaon
17-01-2008
23-05-2008

135/2007
Determination of final transmission tariff for 400 kV D/C Agra-Bassi transmission line (CKT-III and II) along with associated bays under Northern Region System Strengthening Scheme-II for the tariff block 2004-09. Power Grid Corporation of India Limited, Gurgaon
17-01-2008
23-05-2008

31/2007
Determination of final transmission tariff of the assets covered under Bihar Grid Strengthening Scheme except extension of Biharshariff sub-station with 400/220 kV, 1 No. 315 MVA transformer with associated bays from 1.11.2004 to 31.3.2009. (ii) final tariff for additional capitalization for extension of Biharshariff sub-station with 400/220 kV, 1 No. 315 MVA transformer with associated bays from 1.4.2004 to 31.3.2009 (assets covered under petition No. 73/2005), under Bihar Grid Strengthening Scheme in Eastern Region. Power Grid Corporation of India Limited
14-08-2007
23-05-2008

144/2007
Determination of final transmission tariff from the date of commercial operation to 31.3.2009 after accounting for additional capitalization from date of commercial operation to 31.3.2007 for (i) 400 kV Bareilly sub-station (UPPCL) (extension) and 400 kV Mandaula sub-station (extension) associated with 400 kV Mandaula-Bareily transmission line of Powerlinks (ii) 400 kV D/C Lucknow (Power Grid)-Unnao (UPPCL) transmission line with associated bays at both ends, 400 kV D/C Gorakhpur (Power Grid)-Gorakhpur (UPPCL) transmission line with bays at both ends, 2 Nos 400 kV bays at Gorakhpur (Power Grid) and 2 Nos 400 kV bays at Lucknow (Power Grid) for 400 kV D/C Gorakhpur-Lucknow transmission line of Powerlinks, 400/220 kV 315 MVA ICT at Lucknow with associated bays and 400/220 kV 315 MVA ICT-I at Gorakhpur (Power Grid) with associated bays under the transmission system associated with Tala HEP, East-North Inter-connector and Northern Region Transmission System. Power Grid Corporation of India Limited
10-01-2008
23-05-2008

133/2007
Determination of final transmission tariff and additional capitalization from DOCO to 31.3.2007 for system strengthening scheme in Northern Region (formerly part of Tala Supplementary Scheme) for the block 2004-2009. Power Grid Corporation of India Limited, Gurgaon
17-01-2008
19-05-2008

77/2004
82/2004
84/2004
131/2005
97/2004
1. Approval of tariff in respect of transmission system associated with RAPP-B Project in Northern Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of transmission system associated with Unchahar Stage - II in Northern Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of Kishenpur -Moga transmission system in Northern Region for the period from 1.4.2004 to 31.3.2009 and Additional Capitalisation.
4. Approval of tariff in respect of 400 kV Nathpa Jhakri transmission system in Northern Region for the period from 1.4.2004 to 31.3.2009 and Additional Capitalisation. Power Grid Corporation of India Ltd., Gurgaon
5. Approval of tariff in respect transmission system associated with Faridabad Gas Based Combined Cycle Power Project in Northern Region for the period from 1.4.2004 to 31.3.2009 and Additional Capitalisation during 2001-04. Power Grid Corporation of India Ltd., Gurgaon
-
19-05-2008

103/2007
I.A. No. 37/2007
Petition for determination of final transmission tariff of (i) 40% series compensation on Meramundali-Jeypore 400 kV S/C transmission line at Jeypore (Eastern Region scheme) (ii) 50% Fixed Series Compensation on 400 kV Jeypore-Gazuwaka D/C transmission line at Jeypore (inter-regional scheme between ER and SR ) associated with augmentation of capacity of Gazuwaka HVDC back-to-back project for the period from 1.1.2007 31.3.2009. Power Grid Corporation of India Limited
18-10-2007
19-05-2008

35/2008
Determination of provisional transmission tariff for LILO of 400 kV S/C Korba-Raipur transmission line at Bhatapara sub-station along with associated bay equipment including ICT-I of Bhatapara sub-station under Sipat-II transmission system of Western Region for the period from 1.12.2007 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
15-05-2008
16-05-2008

105/2007
In
68/2007
Direction to CTU for grant of long-term open access on the existing ER-WR corridor, i.e. 400 kV Raipur-Rourekela transmission line including 220 kV Korba Budhipadar transmission line for transfer of 400 MW power from DVC stations at Mejia and Chandrapur. Power Grid Corporation of India Ltd., New Delhi
13-09-2007
13-05-2008

143/2007
Determination of final transmission tariff for (a) LILO of Nagarjunasagar-Raichur 400 kV S/C transmission line at Mehboobnagar (1.1.2006 to 31.3.2009) along with associated bays and (b) LILO of both the circuits of Nellor-Sriperumbudur 400 kV D/C transmission line at Almathi (1.6.2006 to 31.3.2009) along with associated bays including additional capital expenditure for 2006-07, under system strengthening-IV of Southern Region Grid in Southern Region. Power Grid Corporation of India Limited, Gurgaon
03-01-2008
12-05-2008

97/2007
I.A. No.
32/2007
Determination of final transmission tariff for (i) 315 MVA, 400/220 kV, ICT at Siliguri for the period 1.10.2006 to 31.3.2009, and (ii) 400 kV D/C Biharshariff-Muzaffarpur transmission line, Biharshariff 400 kV extension and Muzaffarpur 400 kV extension for the period 1.11.2006 to 31.3.2009 under System Strengthening Scheme for Eastern Region (formerly part of Tala Supplementary Scheme). Power Grid Corporation of India Limited
25-09-2007
06-05-2008

39/2007
40/2007
41/2007
42/2007
1. Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Southern Region.
2. Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Northern Region.
3. Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Eastern Region.
4. Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Western Region. Power Grid Corporation of India Limited, Gurgaon
-
05-05-2008

160/2007
I.A. No. 45/2007
Determination of final transmission tariff for (i) LILO of one circuit of 400 kV D/C Farakka-Jeerat line at Subhashgram and establishment of 400/220 kV Sub-station (New) at Subhashgram including 1x315 MVA, ICT-II for the period 1.3.2007 to 31.3.2009. (ii) 315 MVA, 400/220 kV, ICT-I at Subhashgram sub-station (New) for the period from 1.4.2007 to 31.3.2009. under strengthening scheme for Eastern Region (formerly part of Tala supplementary Scheme) in Eastern Region. Power Grid Corporation of India Limited
21-02-2008
01-05-2008

134/2007
Determination of final transmission tariff along with additional capitalization for 400 kV D/C Kanpur-Auraiya transmission line with bay at Auraiya under the System Strengthening Scheme-I in Northern Region for the tariff period 2004-09. Power Grid Corporation of India Limited, Gurgaon
17-01-2008
30-04-2008

149/2007
Determination of final transmission tariff for (i) 400 kV D/C Gorakhpur-Lucknow transmission line (ii) 400 kV D/C Bareilly-Mandola transmission line in Northern Region associated with Tala HEP, East-North Inter-connector and Northern Region Transmission system for the period from 2005-09. Powerlinks Transmission Limited, New Delhi
21-02-2008
30-04-2008

148/2007
Determination of final transmission tariff for 400 kV D/C Siliguri-Purnea transmission line, 400 kV D/C Purnea-Muzaffarpur transmission line and 220 kV D/C Muzaffarpur (PGCIL)-Muzaffarpur (BSEB) transmission line in Eastern Region associated with Tala Hydro Electric Project, East-North Inter-connector and Northern Region transmission system for the period from 1.9.2006 to 31.3.2009. Powerlinks Transmission Limited, New Delhi
21-02-2008
30-04-2008

72/2005
Approval of transmission charges for LILO of 400 kV S/C Singrauli-Kanpur transmission line-I, 400 kV sub-station at Allahabad and LILO of 400 kV S/C Singrauli-Kanpur transmission line-II including ICT-I & II at Allahabad with associated bays in Northern Region for the tariff period from 1.4.2004 to 31.3.2009 and for additional capitalization during 2001-04. Power Grid Corporation of India Ltd., Gurgaon
-
30-04-2008

35/2005
Approval for transmission charges for 220 kV Jallandhar-Hamirpur D/C transmission line along with associated bays in Northern Region for the period from 1.4.2004 to 31.3.2009 and impact of additional capitalization during 2001-04. Power Grid Corporation of India Limited
-
30-04-2008

6/2005
84/2005
127/2005
1. Approval of tariff in respect of 230 kV Neyveli-Bahoor transmission line along with associated bay equipment at Neyveli end in Southern Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of (A) Talcher-Kolar HVDC line (Pole-I), (B) LILO of 400 kV S/C Cuddapah-Banglore S/C line, common facilities at Kolar, and 400 kV S/C Kolar-Madras line, (C) 400 kV S/C Hossur-Salem line, 315 MVA Auto Transformer-I at Hossur, along with 220 kV switchyard (D) 315 MVA Auto Transformer-2 at Hossur, (E) 500 MVA Auto-transformer (comprising of 4x167 MVA single phase units) at Kolar along with 220 kV switchyard, and 400 kV D/C Kolar-Hoody line, under Transmission System associated with Talcher-II Project for the period 1.4.2004 to 31.3.2009 and additional capitalization for the period 2001-04
3. Approval of tariff in respect of (A) HVDC terminal station at Talcher and Kolar related with Pole-II, (B) 400 kV D/C Kolar-Hossur transmission line along with associated bays at Kolar and Hossur and (C) 400 kV S/C Salem-Udumalpet transmission line along with associated bay extension at Salem and Udumalpet etc. under transmission system associated with Talcher Super Thermal Power Station Stage-II for the period 1.4.2004 to 31.3.2009 Power Grid Corporation of India Ltd., Gurgaon
-
29-04-2008

144/2005
Approval of transmission charges in respect of LILO of Purnia-Dalkola 132 kV S/C line and extension at Purnia sub-station in Eastern Region for the period 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
29-04-2008

61/2005
Approval of transmission charges in respect of 400 kV D/C Kolhapur-Mapusa transmission line (Ckt-I & Ckt-II) and associated bays in Western Region for the period from 1.4.2004 to 31.3.2009 and additional capitalization during 2001-04. Power Grid Corporation of India Ltd., Gurgaon
-
29-04-2008

69/2004
1. Approval of tariff in respect of Korba-Budhipadar transmission system in Eastern Region and Western Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of Vindhyachal Stage-I Additional transmission system in Western Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of transmission system associated with Vindhyachal Stage II in Western Region for the period from 1.4.2004 to 31.3.2009.
4. Approval of tariff in respect of 50 MVAR Reactor along with the associated equipment at Chandrapur sub-station in Western Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
29-04-2008

147/2007
Determination of final transmission tariff for 400 kV D/C Muzaffarpur-Gorakhpur transmission line in Eastern-Northern inter-connector associated with Tala Hydro Electric Project, East-North Inter-connector and Northern Region transmission system for the period from 1.9.2006 to 31.3.2009. Powerlinks Transmission Limited, New Delhi
21-02-2008
28-04-2008

51/2005
Approval of transmission charges in respect of 400 kV D/C Biharsharif-Sasaram-Sarnath transmission lines with associated bays under Eastern-Northern inter-regional HVDC transmission system for the period from 1.4.2004 to 31.3.2009 Power Grid Corporation of India Ltd., Gurgaon
-
28-04-2008

67/2004
121/2004
1. Approval of tariff in respect of Hathidah River Crossing section of 220 kV D/C Biharsharif-Begusarai transmission line in Eastern Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of 400 kV D/C Malda-Bongaigaon transmission line in Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
16-04-2008

137/2004
Approval of tariff in respect of Ramagundam -Hyderabad transmission line in Southern Region and Chandrapur HVDC back to back station (2 x 500MW) in Western Region and Southern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
16-04-2008

74/2004
133/2004
136/2004
1. Approval of tariff in respect of Kayamkulam transmission system in Southern Region for the period from 1.4.2004 to 31.3.2009
2. Approval of tariff in respect of 315 MVA ICT -III along with associated bays equipments at Nagarjunasagar sub-station in Southern Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of 400 kV D/C Kaiga-Sirsi transmission line along with associated bays in Southern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
16-04-2008

87/2006
Determination of transmission tariff for ATS of Kathalguri GBPP in North Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
01-08-2007
16-04-2008

70/2004
Approval of tariff for 400 kV Jeypore-Gazuwaka transmission line along with associated bays and 500 MW HVDC back to back station at Gazuwaka between Southern Region and Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
09-04-2008

122/2004
124/2004
125/2004
1. Approval of tariff in respect of Jeypore-Talcher transmission system in Eastern Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of Chukha Transmission system in Eastern Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of 400 kV Talcher transmission system in Eastern Region for the period from 1.4.2004 to 31.3.2009 Power Grid Corporation of India Ltd., Gurgaon
-
31-03-2008

142/2007
Determination of final transmission tariff up to DOCO and additional capitalisation from DOCO to 31.3.2007 for (i) TCSC and 2 nos of 400 kV bays at Gorakhpur sub-station associated with 400 kV Muzaffarpur-Gorakhpur line of Powerlinks (ii) 2 nos of 400 kV bays at Muzaffarpur with line reactor associated with 400 kV Muzaffarpur-Gorkhpur line of Powerlinks, under transmission system associated with Tala HEP, East-North Inter-connector and Northern Region Transmission system, an inter-regional asset between Northern Region and Eastern Region from 1.9.2006 to 31.3.2009. Power Grid Corporation of India Limited
10-01-2008
28-03-2008

86/2006
Determination of transmission tariff for associated transmission system of Agartala GBPP in North Eastern Region for the period from 1.4.2004 to 1.3.2009. Power Grid Corporation of India Ltd., Gurgaon
01-08-2007
25-03-2008

129/2004
130/2004
135/2004
1. Approval of tariff in respect of 315 MVA 400/230 KV Auto Transformer at Hyderabad and one 50 MVAR Reactor at Cuddapah under Central Transmission Project Augmentation in Southern Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of 400 KV Ramagundam Transmission System including ICT Khammam & Reactor at Gazuwaka under CTP Augmentation in Southern Region for the period 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of Central Transmission Project-I in Southern Region for the period 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd.
-
17-03-2008

112/2004
114/2004
115/2004
1. Approval of tariff in respect of transmission system associated with Gandhar Gas Power Station-I in Western Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of Kawas Transmission System in Western Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of Kakrapar Transmission System in Western Region for the period from 1.4.2004 to 31.3.2009 Power Grid Corporation of India Ltd., Gurgaon
-
14-03-2008

19/2002
Approval of tariff in respect of Chamera Stage I Transmission system Northern Region for the period from 1.4.2001 to 31.3.2004. Power Grid Corporation of India Ltd., Gurgaon
-
14-03-2008

83/2006
Determination of transmission tariff for ATS of Loktak HEP in North Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
01-08-2007
10-03-2008

84/2006
Determination of transmission tariff for Ranaganadi transmission system in North Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
01-08-2007
07-03-2008

166/2007
Determination of provisional transmission tariff for (i) 400 kV Balia-Lucknow Ckt-I & II, 400 kV Balia-Mau Ckt-I, 400 kV D/C Patna-Balia transmission line including associated bays at Patna & Balia (ii) 400 kV Balia-Mau Ckt-II, 40% FSC at Lucknow on 400 kV D/C Lucknow-Balia transmission line (iii) 80 MVAR Bus Reactor at Biharshariff sub-station (iv) 400 kV Lucknow-Bareilly Ckt-I & II along with associated bays under Kahalgaon Stage II Phase I Transmission System in Northern Region for the period 2004-09. Power Grid Corporation of India Ltd., Gurgaon
20-02-2008
29-02-2008

96/2004
98/2004
105/2004
109/2004
1. Approval of tariff in respect of Rihand Transmission System in Northern Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of 220 kV Anta transmission system in Northern Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of transmission system associated with Auraiya Gas Power Project (625 MW) in Northern Region for the period from 1.4.2004 to 31.3.2009.
4. Approval of tariff in respect of Chamera Stage-I Transmission System in Northern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
29-02-2008

89/2006
Determination of transmission tariff for associated transmission system of Doyang HEP in North Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
02-08-2007
21-02-2008

88/2006
Determination of transmission tariff for Augmentation Scheme in North Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
01-08-2007
13-02-2008

111/2004
113/2004
117/2004
138/2004
1. Approval of tariff in respect of 400 kV Vindhyachal Stage-I transmission system in Western Region for the period from 1.4.2004 to 31.3.2009.
2. Approval of transmission tariff for 400 kV D/C Singrauli-Vindhyachal transmission line along with (2x250 MW) HVDC back to back at Vindhyachal between Northern Region and Western Region for the period from 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of 400 kV Korba transmission system in Western Region for the period from 1.4.2004 to 31.3.2009.
4. Approval of transmission tariff for 400 kV D/C Ramagundam-Bhadrawati (Chandrapur) Transmission System between Southern Region and Western Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
14-02-2008

21/2007
Determination of final transmission tariff for integration of Sikkim Transmission System with Eastern Region by LILO of Siliguri-Gangatok section of 132 kV Rangit-Siliguri transmission line at Melli in Eastern Region for the period 1.10.2005 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
14-08-2007
15-02-2008

7/2002
9/2002
26/2002
&
40/2002
41/2002
51/2002
52/2002
53/2002
1. Approval of tariff for Central Transmission Project A.C. Line System in Southern Region and for the period 1.4.2001 to 31.3.2004.
2. Approval of tariff in respect of 400 KV D/C Ramagundum-Chandarpur Transmission System in Southern and Western Region for the period from 1.4.2001 to 31.3.2004.
3. Approval of tariff in respect of 400 kV Ramagundam Transmission System, including ICT at Khammam and Reactor at Gazuwaka under CTP Augmentation in Southern Region for the period 1.4.2001 to 31.3.2004.
4. Approval of tariff in respect of 400 kV D/C Kaiga-Sirsi Transmission Line along with associated bays in Southern Region for the period 1.4.2001 to 31.3.2004.
5. Approval of tariff in respect of for additional 315 MVA, 400/200 KV Station in Southern Region from 1.4.01 to 31.3.04.
6. Approval of transmission tariff in respect of 400 kV Jeypore-Gazuwaka Transmission Line along with associated bays 500 MW HVDC back-to-back station at Gazuwaka between Southern Region and Eastern Region for the period 1.4.2001 to 31.3.2004.
7. Approval of tariff in respect of Kayamkulam Transmission System in Southern Region for the period 1.4.2001 to 31.3.2004.
8. Approval of tariff in respect of one 315 MVA 400/230 kV Auto Transformer at Hyderabad and one 50 MVAR Reactor at Cuddapah in Southern Region for the period from 1.4.2001 to 31.3.2004. Power Grid Corporation of India Ltd., Gurgaon
-
08-02-2008

17/2002
Approval of tariff in respect of transmission system associated with Talcher -I STPS in Eastern Region for the period from 1.4.2001 to 31.3.2004. Power Grid Corporation of India Ltd., Gurgaon
-
12-02-2008

6/2002
8/2002
15/2002
19/2002
IN
38/2002
43/2002
50/2002
54/2002
68/2002
73/2002
1. Approval of tariff for 220 kV Anta Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004.
2. Approval of tariff in respect of Transmission System associated with Auraiya Gas Power Project in Northern Region for the period 1.4.2001 to 31.3.2004.
3. Approval of tariff in respect of 400 kV D/C Singrauli-Vindhyachal transmission line along with (2 x 250 MW) HVDC back-to-back station at Vindhyachal in Northern Region and Western Region for the period 1.4.2001 to 31.3.2004.
4. Approval of tariff in respect of Chamera Stage I Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004.
5. Approval of tariff in respect of Rihand Transmission System, Reactor at Agra in Northern Region for the period 1.4.2001 to 31.3.2004
6. Approval of transmission tariff in respect of 800 KV S/C Kishenpur-Moga Transmission Line Ckt-I with associated bays, 420 KV, 63 MVAR Bus Reactor at Kishenpur sub-station with associated bays and 400/220 KV, 250 MVA ICT-III at Moga sub-station with associated bays and 800 KV Kishenpur-Moga Transmission Line Ckt-II with associated bays in Northern Region for the period from 1.4.2001 to 31.3.2004.
7. Approval of tariff in respect of transmission system associated with RAPP-B Project in Northern Region from 1.4.2001 to 31.3.2004.
8. Approval of tariff in respect of Transmission System associated with Faridabad GBCCPP in Northern Region for the period from 1.4.2001 to 31.3.2004.
9. Approval of tariff in respect of transmission system associated with Unchahar Thermal Power Station Stage II in Northern Region for the period from 1.4.2001 to 31.3.2004.
10. Approval of tariff in respect of transmission system associated with Nathpa-Jhakri HE Project in Northern Region for the period from 1.4.2001 to 31.3.2004. Power Grid Corporation of India Ltd.,Gurgaon
-
08-02-2008

128/2007
Determination of final transmission tariff along with additional capitalization-I for Neelmangala-Somanahally 400 kV D/C transmission line with bay extension at Neelmangala (KPTL) and Somanahally (Power Grid) under Scheme for System Strengthening-III of Southern Region Grid from 1.1.2007 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon
11-12-2007
08-02-2008

126/2004
IN
127/2004
1. Approval of tariff in respect of 400 kV transmission system associated with Farakka (I &II) STPS in Eastern Region for the period from 1.4.2004 to 31.3.2009
2. Approval of tariff in respect of 400 kV Kahalgaon transmission system in Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
07-02-2008

131/2004
IN
134/2004
1. Approval of tariff in respect of NLC Stage-II Transmission System in Southern Region for the period 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of NLC Stage-I Transmission System in Southern Region for the period 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
24-01-2008

101/2004
102/2004
103/2004
IN
106/2004
108/2004
110/2004
1. Approval of tariff in respect of Bairasuil Transmission System in Northern Region for the period 1.4.2004 to 31.3.2009.
2. Approval of tariff in respect of Singrauli Transmission System in Northern Region for the period 1.4.2004 to 31.3.2009.
3. Approval of tariff in respect of Salal Stage-II Transmission System in Northern Region for the period 1.4.2004 to 31.3.2009.
4. Approval of tariff in respect of Moga-Hissar-Bhiwani Transmission System in Northern Region for the period 1.4.2004 to 31.3.2009.
5. Approval of tariff in respect of Tanakpur Transmission System in Northern Region for the period 1.4.2004 to 31.3.2009.
6. Approval of tariff in respect of Salal Stage-I Transmission System in Northern Region for the period 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
-
22-01-2008

27/2002
47/2002
48/2002
49/2002
IN
66/2002
69/2002
72/2002
74/2002
1. Approval of tariff for 400 kV Korba Transmission System in Western Region for the period 1.4.2001 to 31.3.2004.
2. Approval of tariff in respect of 400 kV Vindhyachal Stage-I Transmission System in Western Region for the period from 1.4.2001 to 31.3.2004.
3. Approval of tariff in respect of 50 MVAR Reactor along with associated equipment at Chandrapur sub-station in Western Region for he period 1.4.2001 to 31.3.2004.
4. Approval of tariff in respect of Korba-Budhipadar Transmission System in Western Region for the period from 1.4.2001 to 31.3.2004.
5. Approval of tariff in respect of 400 kV Vindhyachal Stage-I additional transmission System in Western Region for the period from 1.4.2001 to 31.3.2004.
6. Approval of transmission tariff in respect of Ramagundam-Hyderabad transmission line in Southern Region and Chandrapur HVDC back-to-back station (2x400 MW) in Western Region and Southern Region for the period from 1.4.2001 to 31.3.2004.
7. Approval of tariff in respect of 400 kV Vindhyachal Stage-II Transmission System in Western Region for the period from 1.4.2001 to 31.3.2004.
8. Approval of tariff in respect of transmission system associated with Gandhar Gas Power Station (stage I) in Western Region for the period from 1.4.2001 to 31.3.2004. Power Grid Corporation of India Ltd
-
17-01-2008

12/2002
25/2002
IN
63/2002
71/2002
1. Approval of tariff for 400 kV Transmission System associated with Farakka (I & II) STPS in Eastern Region for the period 1.4.2001 to 31.3.2004.
2. Approval of tariff in respect of Kahalgaon Transmission System in Eastern Region for the period 1.4.2001 to 31.3.2004
3. Approval of tariff in respect of Hathidah River Crossing Section of 220 kV Biharsharif-Begusarai Transmission Line in Eastern Region for the period 1.4.2001 to 31.3.2004
4. Approval of tariff in respect of Malda-Bongaigoan Transmission Line in Eastern Region for the period from 1.4.2001 to 31.3.2004. Power Grid Corporation of India Ltd.
-
05-01-2008

85/2006
Determination of transmission tariff for transmission system associated with Kopili Hydroelectric Stage-I extension project (2x50 MW) in North Eastern Region for the period from 1.4.2004 to 31.3.2009. Power Grid Corporation of India Ltd., Gurgaon
02-08-2007
16-01-2008