cerc-logo

Incentives 2008

Pet. No.
Subject
Date of Hearing
Date of Order


152/2005


Approval of incentive based on availability of transmission system for the year 2004-05 for Western Region. Power Grid Corporation of India Limited, Gurgaon

26-08-2008

11-12-2008


81/2008


Approval of incentive based on availability of 400 kV D/C Gorakhpur-Lucknow transmission line, 400 kV D/C Barielly-Mandola transmission line and 400 kV D/C Muzaffarpur-Gorakhpur transmission line (50% share), associated with Tala Hydro Electric Power Project, East-North inter-connector and Northern Region Transmission System for the year 2007-08. Powerlinks Transmission Limited, New Delhi

11-11-2008

01-12-2008


82/2008


Approval for incentive for the year 2007-08 in respect of 400 kV D/C Siliguri Purnea transmission line, 400 kV D/C Purnea-Muzaffarpur transmission line, 220 kV D/C Muzaffarpur (PGCIL)- Muzaffarpur (BSEB) transmission line and 400 kV D/C Muzaffarpur-Gorakhpur (50%) transmission line associated with Tala Hydro Electric project, East-North interconnector and Northern Region transmission system. Powerlinks Transmission Limited, New Delhi

11-11-2008

01-12-2008


I.A.No.
16/2008
In
168/2007


Approval for incentive for the year 2006-07 in respect of 400 kV D/C Siliguri Purnea transmission line, 400 kV D/C Purnea-Muzaffarpur transmission line, 220 kV D/C Muzaffarpur (PGCIL)- Muzaffarpur (BSEB) transmission line and 400 kV D/C Muzaffarpur-Gorakhpur (50%) transmission line associated with Tala Hydro Electric project, East-North interconnector and Northern Region transmission system. Powerlinks Transmission Limited, New Delhi

11-11-2008

17-11-2008


I.A.No.
17/2008
In
169/2007


Approval of incentive based on availability of 400 kV D/C Gorakhpur-Lucknow transmission line, 400 kV D/C Barielly-Mandola transmission line and 400 kV D/C Muzaffarpur-Gorakhpur transmission line (50% share), associated with Tala Hydro Electric Power Project, East-North inter-connector and Northern Region Transmission System for the year 2006-07. Powerlinks Transmission Limited, New Delhi

11-11-2008

17-11-2008


162/2005


Approval of incentive based on availability of transmission system for the year 2004-05 for Northern Region. Power Grid Corporation of India Limited, Gurgaon

26-08-2008

20-10-2008


102/2008
along with
I.A.No.
25/2008


Approval of incentive based on availability of transmission system of Northern Region for the year 2007-08. Power Grid Corporation of India Limited, Gurgaon

-

19-09-2008


98/2008
along with
I.A. 23/2008


Approval of incentive based on availability of transmission system of Eastern Region for the year 2007-08. Power Grid Corporation of India Limited, Gurgaon

-

08-09-2008


159/2005


Approval of incentive based on availability of transmission system for the year 2004-05 for Eastern Region. Power Grid Corporation of India Limited, Gurgaon

10-06-2008

01-09-2008


169/2007


Approval of incentive based on availability of 400 kV D/C Gorakhpur-Lucknow transmission line, 400 kV D/C Barielly-Mandola transmission line and 400 kV D/C Muzaffarpur-Gorakhpur transmission line (50% share), associated with Tala Hydro Electric Power Project, East-North inter-connector and Northern Region Transmission System for the year 2006-07. Powerlinks Transmission Limited, New Delhi

24-06-2008

08-07-2008


168/2007


Approval for incentive for the year 2006-07 in respect of 400 kV D/C Siliguri Purnea transmission line, 400 kV D/C Purnea-Muzaffarpur transmission line, 220 kV D/C Muzaffarpur (PGCIL)- Muzaffarpur (BSEB) transmission line and 400 kV D/C Muzaffarpur-Gorakhpur (50%) transmission line associated with Tala Hydro Electric project, East-North interconnector and Northern Region transmission system. Powerlinks Transmission Limited, New Delhi

24-06-2008

08-07-2008


152/2005


Approval of incentive based on availability of transmission system for the year 2004-05 for Western Region. Power Grid Corporation of India Limited, Gurgaon

17-06-2008

17-06-2008