Pet. No.
Subject
Date of Hearing
Date of Order

118/2007


Tariff petition for fixation of tariff for NLC TPS-II Stage-I (630 MW) and Stage-II (840 MW) for the period from 1.4.2004 to 31.3.2009. Neyveli Lignite Corporation Limited, Chennai.

18-12-2007

26-12-2007


86/2007


Review of order dated 20.11.2006 in Petition No. 120/2005-determination of tariff for Kahalgaon STPS for the period from 1.4.2004 to 31.3.2009. M.P. Power Trading Company Limited, Jabalpur ,National Thermal Power Corporation Ltd. and Others

27-11-2007

27-11-2007


101/2007


Approval of provisional tariff of Unit - I of Kahalgaon Super Thermal Power Station, Stage-II from its date of commercial operation till 31.3.2009. NTPC Limited, New Delhi

25-09-2007

27-11-2007


22/2007
23/2007
28/2007
29/2007
32/2007
34/2007
46/2007
47/2007
48/2007
27/2007


1. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Rihand Super Thermal Power Station,(1000MW), Stage-I. NTPC Limited, New Delhi
2. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Faridabad Gas Power Station. NTPC Limited, New Delhi. Haryana Power Generation Corporation Ltd, Panchkula
3. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Simhadri Thermal Power Station (1000MW). NTPC Limited, New Delhi
4. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Ramagundam Super Thermal Power Station, Stage-I & II (2100MW). NTPC Limited, New Delhi
5. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Farraka Super Thermal Power Station (1600 MW). NTPC Limited, New Delhi
6. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for National Capital Thermal Power Station, Dadri (840MW). NTPC Limited, New Delhi
7. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Singrauli Super Thermal Power Station. NTPC Limited, New Delhi
8. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Tanda Thermal Power Station (440MW). NTPC Limited, New Delhi. Uttar Pradesh Power Corporation Ltd., Lucknow
9. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Korba Super Thermal Power Station (2100MW). NTPC Limited, New Delhi
10. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Kahalgaon Super Thermal Power Station, Stage-I (840 MW). NTPC Limited, New Delhi

23-10-2007

06-11-2007


163/2004

Revision of tariff of Tanda TPS (440 MW) for the period from 1.4.2007 to 31.3.2009 on account of revision of operational parameters and norms. NTPC Ltd., New Delhi.

-

03-10-2007


79/2007
in5/2002

Review of the order dated 23.3.2007 in Petition No. 5/2002 - determination of tariff of TPS-II of NLC for the period from 1.4.2001 to 31.3.2004. Tamil Nadu Electricity Board, Chennai.

18-09-2007

28-09-2007


84/2007

Approval of tariff of Unit -I (210 MW) of Feroze Gandhi Uchahar Thermal Power Station Stage-III from its date of commercial operation. NTPC Limited, New Delhi.

27-09-2007

27-09-2007


32/2006

Recovery of energy charges for the energy supplied during the period 1.1.2000 to 30.6.2001-adjudication of disputes. NTPC Limited, New Delhi

27-09-2007

27-09-2007


86/2007

Review of order dated 20.11.2006 in Petition No. 120/2005-determination of tariff for Kahalgaon STPS for the period from 1.4.2004 to 31.3.2009. M.P. Power Trading Company Limited, Jabalpur

25-09-2007

25-09-2007


8/2005

Approval of revised fixed charges on account of additional capital expenditure incurred during 14.1.2000 to 31.3.2004 in respect of Tanda Thermal Power Station (440 MW).

30-08-2007

05-09-2007


27/2007
28/2007
29/2007
32/2007
48/2007

1. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Kahalgaon Super Thermal Power Station,(840MW), Stage-I. 2. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Simhadri Thermal Power Station (1000MW). 3. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Ramagundam Super Thermal Power Station, Stage-I & II (2100MW). 4. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Farraka Super Thermal Power Station (1600 MW). 5. Approval of revised fixed charges after considering the impact of additional capital expenditure incurred during 2004-05 and 2005-06 for Korba Super Thermal Power Station (2100MW).

23-08-2007

27-08-2007


150/2005

Approval of tariff in respect of Assam Gas Based Power Station (291 MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

07-08-2007


135/2005

Approval of tariff in respect of Agartala Gas Turbine Power Project (84 MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

07-08-2007


83/2007

Approval of provisional tariff for Vindhyachal STPS Stage-III (1000 MW) from date of commercial operation to 31.3.2009.

27-07-2007

13-08-2007


9/2007 in
63/2004

Review of order dated 30.11.2006 in Petition no.163/2004 determining the tariff for Tanda T.P.S (440 MW) for the period 1.4.2004 to 31.3.2009.

05-08-2007

16-07-2007


32/2006

Recovery of energy charges for the energy supplied during the period 1.1.2000 to 30.6.2001-adjudication of disputes.

-

26-07-2007


22/2007
23/2007
34/2007
46/2007
47/2007

1. Approval of revised fixed charges for Rihand Super Thermal Power Station,(1000MW), Stage-I.
& 2. Approval of revised fixed charges for Faridabad Gas Power Station.
& 3. Approval of revised fixed charges for National Capital Thermal Power Station, Dadri (840MW).
& 4. Approval of revised fixed charges for Singrauli Super Thermal Power Station.
& 5. Approval of revised fixed charges for Tanda Thermal Power Station (440MW).

19-07-2007

25-07-2007


80/2006 in
154/2005

In-principle approval of project capital cost and financing plan of Torrent Power Generation Ltd. in respect of SUGEN Combined Cycle Power Project in the State of Gujarat.

24-07-2007

24-07-2007


6/2007 in
35/2004

Review/Clarification/modification/reconsideration of order dated 25.9.2006 in Petition No.35/2004 for Approval of revised fixed charges for the Talcher Thermal Power Station (460 MW).

24-07-2007

24-07-2007


16/2006

Dispute relating to apportionment of capacity charges of three NTPC Stations among the beneficiaries for the month of October 1998.

17-07-2007

17-07-2007


38/2001
151/2004

  1. Approval of tariff in respect of Rihand Super Thermal Power Station Stage I for the period from 1.4.2001 to 31.3.2004.
& 2. Approval of tariff in respect of Rihand Super Thermal Power Station Stage I(1000 MW) for the period from 1.4.2004 to 31.3.2009.

-

21-05-2007

6/2007
in
35/2004

  1. Approval of revised fixed charges due to additional capitalisation for the years 2000-2004 for the Talcher Thermal Power Station (460 MW).
& 2. Review/Clarification/modification/reconsideration of order dated 25.9.2006 in Petition No.35/2004.

29-05-2007

29-05-2007

106/2006
140/2005
179/2004

Final tariff of Unit-I (500 MW) for the period 15.8.2005 to 31.3.2006 and Units I & II (Combined) for the period 1.4.2006 to 31.3.2009 of Rihand STPS Stage II.

22-05-2007

22-05-2007

143/2006

Petition under Section 79(1) (f) of the Electricity Act, 2003.

01-05-2007

01-05-2007

I.A.No.
80/2006
in
154/2005

In-principle approval of project capital cost and financing plan of Torrent Power Generation Ltd. in respect of SUGEN Combined Cycle Power Project in the State of Gujarat.

20-02-2007

05-03-2007

113/2006

Adoption of tariff in respect of 2000 MW Thermal Power station proposed to be established by ISN International Company Pvt. Limited at District Sidhi, Madhya Pradesh.

25-01-2007

25-01-2007

154/2005

In-principle approval of project capital cost and financing plan of Torrent Power Generation Ltd. in respect of SUGEN Combined Cycle Power Project in the State of Gujarat.

08-01-2007

16/2006
With IA No.
5/2007

Dispute relating to apportionment of capacity charges of three NTPC Stations among the beneficiaries for the month of October 1998.

11-01-2007

15-01-2007

106/2006
& 140/2005
& 179/2004

1. Final tariff of Unit-I (500 MW) for the period 15.8.2005 to 31.3.2006 and Units I & II (Combined) for the period 1.4.2006 to 31.3.2009 of Rihand STPS Stage II.
& 2. Determination of tariff for Ramagundam Super Thermal Power Station, Stage-III for the period 25.3.2005 to 31.3.2009
& 3. Petition for approval of tariff for power supplied from Talcher STPS Stage-II (4x500 MW) for the period 1.4.2004 to 31.3.2009.

-

08-02-2007

5/2002

Revised tariff of Thermal Power Station II of NLC for the period 1.4.2001 to 31.3.2004.

-

16-01-2007

5/2002

Revised tariff of Thermal Power Station II of NLC for the period 1.4.2001 to 31.3.2004.

30-08-2006

08-01-2007

162/2004

Determining of tariff in respect of National Capital Thermal Power Station, Dadri for the period from 1.4.2004 to 31.3.2009.

-

15-01-2007

54/2007

Approval of tariff of Ratnagiri Gas & Power Project for the interim period 1.4.2007 to 31.6.2007 or till availability of LNG/RLNG for running the plant whichever is earlier.

-

20-04-2007

135/2005 &
150/2005

1. Approval of tariff in respect of Agartala Gas Turbine Power Project (84 MW) for the period 1.4.2004 to 31.3.2009.
& 2. Approval of tariff in respect of sale of power from Assam Gas Based Power Project (291 MW) for the period 1.4.2004 to 31.3.2009.

20-02-2007

20-02-2007

6/2007
in
35/2004

Approval of revised fixed charges due to additional capitalisation for the years 2000-2004 for the Talcher Thermal Power Station (460 MW).

08-02-2007

23-02-2007

9/2007
in
163/2004

Review of order dated 30.11.2006 in Petition no.163/2004 determining the tariff for Tanda T.P.S (440 MW) for the period 1.4.2004 to 31.3.2009.

20-02-2007

28-02-2007

97/2006

Application for grant of transmission licence to Torrent Power Transmission Private Limited.

06-03-2007

22-03-2007

Pet. No.
Subject
Date of Hearing
Date of Order


66/2007
inI.A. No.43/2006
184/2004


Review of order dated 5.2.2007 in I.A. No. 43/2006 in Petition No. 184/2004 seeking relaxation of capacity index of Naptha Jhakri Hydro Electric Project (6x 250 MW) of SJVNL for the years 2004-05 and 2005-06. Satluj Jal Vidyut Nigam Limited.

11-12-2007

19-12-2007


115/2007


Approval of tariff in respect of Ranganadi Hydro Electric Project (3x 135 MW) for the period from 12.2.2002 to 31.3.2004. North Eastern Electric Power Corporation Ltd, Shillong

27-11-2007

10-12-2007


115/2007

Approval of tariff in respect of Ranganadi Hydro Electric Project (3X135 MW) for the period from 12.2.2002 to 31.3.2004. North Eastern Electric Power Corporation Ltd.

-

01-10-2007


70/2006

Approval of tariff in respect of Kopili HE Project Stage-II (1X25 MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

21-08-2007


76/2007

Approval of tariff in respect of Kopili Hydro Electric Project - Kopili Power Station (4x50MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

21-08-2007


26/2007

Approval of tariff in respect of Khandong Power Station (2X25 MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

21-08-2007


88/2007

Approval of tariff in respect of Doyang Hydro Electric Project(3X25MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

21-08-2007


89/2007

Approval of tariff in respect of Ranganadi Hydro Electric Project (3X135MW) for the period from 1.4.2004 to 31.3.2009.

02-08-2007

22-08-2007

107/2006

Approval of Generation Tariff of Dhauliganga Hydroelectric Project Stage - I for the period 1.10.2005 to 31.3.2009.

-

23-03-2007

63/2006

Approval of Generation tariff in respect of Tehri Hydroelectric Project Stage-I (4x 250MW) for the period 22.9.2006 to 31.3.2009.

28-12-2006

28-12-2006

20/2005

Provisional approval of Generation Tariff of Dhauliganga HE Project Stage-I for the period 1.4.2005 to 31.3.2006.

-

25-01-2007

107/2006

Approval of Generation Tariff of Dhauliganga HE Project Stage - I for the period 1.10.2005 to 31.3.2009.

22-02-2007

23-02-2007

Pet. No.
Subject
Date of Hearing
Date of Order


150/2007


Determination of provisional transmission tariff for (i) 400 kV bays at Kanpur sub-station associated with Kanpur-Auraiya transmission line (ii) LILO of 400 kV D/C Bareilly-Mandola transmission line along with associated bays at Bareilly and Bus reactor at Bareilly under Northern Region system strengthening scheme-I in Northern Region for the period 2004-09. Power Grid Corporation of India Limited, Gurgaon

18-12-2007

26-12-2007


130/2007


Determination of provisional transmission tariff for LILO of 400 kV Vindhyachal-Kanpur line at Singrauli along with bays at Singrauli end (Realignment of Vindhyachal-Kanpur S/C line at Singrauli and Singrauli-Vindhyachal 2nd 400 kV ckt) and Bus coupler bay at Vindhyachal HVDC under system strengthening scheme in Singrauli-Vindhyachal corridor in Northern Region for the period 2004-09 Power Grid Corporation of India Limited, Gurgaon

22-11-2007

22-11-2007


122/2007


Determination of provisional transmission tariff for 50 MVAR bus reactor at Hissar sub-station (DOCO 1.7.2007) under Northern region system strengthening scheme-III in Northern Region for the tariff period 2004-09. Power Grid Corporation of India Limited, Gurgaon

20-11-2007

29-11-2007


129/2007


Determination of provisional transmission tariff for 315 MVA ICT-IV at Moga sub-station along with associated bays under Augmentation of transformation capacity at Moga and Amritsar sub-station in Northern Region for the period 2004-2009. Power Grid Corporation of India Limited, Gurgaon

22-11-2007

22-11-2007


108/2007
In 114/2007
116/2007

1. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004 Tata Power Trading Company Ltd. Mumbai. Vishwanath Sugars Ltd., Belgaum
2. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004 Ugar Sugar Works Ltd. Sangli. Tata Power Co. Ltd., Mumbai
3. A petition under Section 79 of the Electricity Act, 2003 read with Regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Shree Doodhaganga Krishna Sahakari Sakkare Karkhane Niyamit, Chikodi.Tata Power Co. Ltd., Mumbai

-

07-11-2007


119/2007

Determination of provisional transmission tariff for 400/220 kV, 315 MVA ICT-I at Gwalior sub-station along with associated bays under transmission system associated with SIPAT-II from 1.5.2007 to 31.3.2009 in Western Region. Power Grid Corporation of India Limited, Gurgaon

30-10-2007

31-10-2007


120/2007

Determination of provisional transmission tariff for 3 x 105 MVA 400/220/33 kV ICT-III at Wagoora sub-station along with associated bays under Northern Region Strengthening Scheme II in Northern Region for the period from 1.6.2007 to 31.3.2009. Power Grid Corporation of India Limited, Gurgaon

30-10-2007

31-10-2007


104/2007

Determination of provisional transmission tariff for Agra-Gwalior 765 kV S/C transmission line along with 400 kV Agra (PGCIL) switching station extension and 400/220 kV Gwalior (PGCIL) sub-station extension under Kahalgaon Stage-II Phase-I transmission system in Western Region and Northern Region from 1.4.2007 to 31.3.2009. Power Grid Corporation of India Limited

30-10-2007

31-10-2007


110/2007

Determination of provisional transmission tariff for LILO of 400 kV Satna-Bina Ckt-I & II at Bina (Power Grid) along with associated bays under Vindhyachal Stage-III transmission system in Western Region for the period from 1.4.2007 to 31.3.2009. Power Grid Corporation of India Limited

18-10-2007

18-10-2007


111/2007

Determination of provisional transmission tariff for 400 kV S/C Vindhyachal-Korba ckt-II along with associated bays equipment at Vindhyachal and Korba switch yards in Western Region 1.6.2007 to 31.3.2009. Power Grid Corporation of India Limited

18-10-2007

18-10-2007


94/2007

Determination of provisional transmission tariff for Gooty-Raichur 400 kV D/C transmission line along with bay extension at Gooty and Raichur under Scheme for system strengthening-III of Southern Region grid from 1.5.2007 to 31.3.2009.

18-09-2007

19-09-2007


106/2007

Determination of provisional transmission tariff for Bina-Gwalior 765 kV S/C transmission line along with bay extensions at Bina and Gwalior under transmission system associated with SIPAT II from 1.4.2007 to 31.3.2009.

18-09-2007

19-09-2007


29/2007
in
105/2005

Approval of transmission charges for Hiriyur sub-station (including 315 MVA Auto Transformer), LILO of Davangere-Hoody 400 kV D/C line at Hiriyur and additional bays at Kolar and Hosur sub-station for 2nd circuit of Kolar-Hosur 400 kV D/C transmission line under System Strengthening Scheme-II in Southern Region for the period from1.4.2004to31.3.2009.

-

08-08-2007


100/2007

Permission to undertake hot-line cleaning of insulators in Northern Region Transmission System through use of helicopter for a period of six months on experimental basis and to allow for reimbursement of consequential expenditure incurred on this account from the respondents.

-

08-08-2007


62/2007

Determination of provisional transmission tariff for 400 kV S/C Dulhasti-Kishenpur transmission and 400 kV D/C Kishenpur-Wagoora transmission line in Northern Region for the 2004-09 block.

28-06-2007

16-07-2007


28/2007
in 90/2007

Approval of incentive based on availability of transmission system for the year 2006-07 for Western Region.

-

18-07-2007


45/2007
in 69/2004
With IA No
17/2007

Review of the order dated 16.3.2006 - Approval of transmission charges for Korba-Budhipadar transmission system in Eastern and Western Regions for the period from 1.4.2004 to 31.3.2009.

17-07-2007

17-07-2007


64/2007

Determination of provisional transmission tariff for Neelmangala-Somanahally 400 kV D/C transmission line along with extension at Neelmangala (KPTCL) and Somanahally (Powergrid) under the System Strengthening Scheme-III of Southern Region from 1.1.2007 to 31.3.2009.

28-06-2007

16-07-2007

39/2007


40/2007


41/2007


42/2007

1 . Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Southern Region.
2 . Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Northern Region.
3 . Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Eastern Region.
4 . Restoration of equity depletion occurred as a result of fixation of tariff by GOI under section 43A (2) of the Electricity Supply Act, 1948, through various tariff notifications for block 1992-97 in Western Region.

10-07-2007

10-07-2007


63/2007

Determination of provisional transmission tariff for Vindhyachal STPP-Satna 400 kV D/C transmission line (3rd and 4th circuit) and 400/220 kV Satna (Powergrid) sub-station (extension) with 1x315 MVA transformer under Vindhyachal Stage-III transmission system in Western Region for the period up to 31.3.2009.

28-06-2007

04-07-2007


85/2007
(Suo-motu)

Proposed Approach for Sharing of Charges for and Losses in Inter-State Transmission system Pet No:-85/2007(Interim Order)dated 02.07.2007.

-

02-07-2007

19/2007 in
136/2006

Correction of error in order dated 6.2.2007 in Petition No 136/2006 determining final transmission tariff for 400 kV D/C Madurai-Thiruvananthapuram Transmission System in Southern Region for the period 1.8.2005 to 31.3.2009 including additional capitalization form the date of commercial operation (1.8.2005) to 31.3.2006.

-

07-06-2007

10/2007

Determination of provisional transmission tariff for 220 kV S/C Meerut-Shatabdinagar transmission line under system improvement scheme in Uttar Pradesh for the period from 1.7.2005 to 31.3.2009.

29-05-2007

29-05-2007

73/2007
138/2006

Approval of provisional transmission tariff for 400 kV D/C Kanpur- Auraiya transmission line with bays at Auraiya under Northern Region System Strengthening Scheme-I in Northern Region for the period from 1.10.2006 to 31.3.2009.

-

29-05-2007

IA No. 4/2007
in 2/2007

Determination of final transmission tariff for 400 kV D/C Rihand-Allahabad, Allahabad-Mainpuri & Mainpuri-Ballabhgarh transmission lines with associated bays, ICT-I & II at Patiala sub-station, LILO of one circuit of Nalagarh-Hissar transmission line at Kaithal, LILO of one circuit of Nalagarh-Hissar line at Patiala, 400 kV S/C Patiala-Malerkotla transmission line, ICT-III at Abdullapur sub-station and provisional transmission tariff for 400 kV S/C Dadri-Panipat transmission line with associated bays and 2 nos of bays at Abdullapur sub-station under Rihand STPS Stage-II Transmission System in Northern Region for tariff block 2004-09 period.

26-04-2007

22-05-2007

35/2007

Approval of provisional transmission tariff for 400 kV D/C Kanpur- Auraiya transmission line with bays at Auraiya under Northern Region System Strengthening Scheme-I in Northern Region for the period from 1.10.2006 to 31.3.2009.

26-04-2007

21-05-2007

36/2007

Determination of provisional transmission tariff for 400/220 kV Kolhapur (MSEB) sub-station (extension) under System Strengthening Scheme-III in Western Region from 1.12.2006 to 31.3.2009.

26-04-2007

21-05-2007

4/2007
in
2/2007

Determination of final transmission tariff for 400 kV D/C Rihand-Allahabad, Allahabad-Mainpuri & Mainpuri-Ballabhgarh transmission lines with associated bays, ICT-I & II at Patiala sub-station, LILO of one circuit of Nalagarh-Hissar transmission line at Kaithal, LILO of one circuit of Nalagarh-Hissar line at Patiala, 400 kV S/C Patiala-Malerkotla transmission line, ICT-III at Abdullapur sub-station and provisional transmission tariff for 400 kV S/C Dadri-Panipat transmission line with associated bays and 2 nos of bays at Abdullapur sub-station under Rihand STPS Stage-II Transmission System in Northern Region for tariff block 2004-09 period.

26-04-2007

22-05-2007

45/2007
in 69/2004
With IA No
17/2007

Review of the order dated 16.3.2006 - Approval of transmission charges for Korba-Budhipadar transmission system in Eastern and Western Regions for the period from 1.4.2004 to 31.3.2009.

-

23-05-2007

IA No.9/2007
in
26/2005

Miscellaneous petition under Regulations 24, 111 and 114 of the CERC (Conduct of Business) Regulations 1999 for 'restoration of equity depletion occurred as a result of fixation of tariff by Government of India under Section 43 A(2) of the Electricity (Supply) Act, 1948, through various tariff notifications for the block 1992-1997.

-

15-03-2007

26/2005

Miscellaneous Petition under Regulations 24, 111 and 114 of the CERC (Conduct of Business) Regulations 1999 for restoration of equity depletion occurred as a result of fixation of tariff by GOI under Section 43A(2) of the Electricity (Supply) Act 1948, through various tariff notifications for block 1992-1997.

15-01-2007

133/2006
in
139/2005

Review of the order dated 9.5.2006 in Petition No.139/2005-Approval of tariff for Unified Load Despatch and Communication (ULD&C) Scheme in Northern Region for the period from 1.4.2004 to 31.7.2017.

-

16-03-2007

97/2006

Application for grant of transmission licence to Torrent Power Transmission Private Limited.

-

08-01-2007 

3/2007

Determination of transmission tariff for Fixed and Thyristor Controlled Series Compensation for 400 kV D/C Raipur-Rourkela transmission line at Raipur in Western Region for the period from 1.11.2004 to 31.3.2009.

-

18-01-2007

82/2006
to
90/2006

Determination of transmission tariff for Rangandi-Ziro transmission system in North Eastern Region for the period from 1.4.2004 to 31.3.2009.

30-11-2006

02-01-2007

146/2006

Seeking directions for the method of charging transmission charges in case of extending supply from the existing Powergrid sub-station and for LILO of existing transmission line for laying and establishment of new lines and sub-stations by State Sector investing its own resources.

13-01-2007

13-02-2007

10/2007

Determination of provisional transmission tariff for 220 kV S/C Meerut-Shatabdinagar transmission line under system improvement scheme in Uttar Pradesh for the period from 1.7.2005 to 31.3.2009.

27-02-2007

27-02-2007

Pet. No.
Subject
Date of Hearing
Date of Order


61/2007

Application for grant of inter-State trading licence in electricity to Sri Balaji Biomass Power Private Limited. Sri Balaji Biomass Power Private Limited, Hyderabad,Shri C.Purshotham, SBBPPL.

18-12-2007

19-12-2007


61/2007

Application for grant of inter-State trading licence in electricity. Sri Balaji Biomass Power Private Limited

25-09-2007

31-10-2007


58/2007

Application for grant of an Inter-State Trading Licence to Maharashtra Industrial Development Corporation (MIDC) Maharashtra Industrial Development Corporation

18-10-2007

19-10-2007


41/2007
in
28/2004

Grant of licence for inter-state trading in electricity to Chhattisgarh Electricity Company Limited. Chhattisgarh Electricity Company Limited

15-10-2007


108/2007
in
114/2007

1. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004. 2. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004.

25-09-2007

25-09-2007


61/2007

Application for grant of inter-state trading licence in electricity. Sri Balaji Biomass Power Private Limited.

06-09-2007

06-09-2007


58/2007

Application for grant of an Inter-State Trading Licence to Maharashtra Industrial Development Corporation (MIDC) Maharashtra Industrial Development Corporation.

23-08-2007

28-08-2007


61/2007

Application for grant of inter-state trading licence in electricity Sri Balaji Biomass Power Private Limited

21-08-2007

21-08-2007


44/2007

Application for grant of transmission licence to Jaypee Powergrid Limited.

24-08-2007

17-08-2007


34/2007
in
98/2006

Grant of licence for inter-state trading in electricity to GEA Energy System (India) Limited.

-

08-08-2007


74/2007

Application for grant of inter-State trading licence in electricity. Patni Projects Pvt. Ltd., Mumbai

19-07-2007

19-07-2007


152/2006

Application for grant of inter-State trading licence in electricity. Ispat Energy Limited

17-07-2007

17-07-2007


60/2007

Application for grant of inter-State trading licence in electricity

05-07-2007

05-07-2007


74/2007

Application for Grant of inter-State trading licence for Category `C'

05-07-2007

05-07-2007


44/2007

Application for grant of transmission licence to Jaypee Powergrid Limited .

14-06-2007

29-06-2007


31/2004

Grant of licence for inter-state trading in electricity to Global Energy Limited (GEL) .

-

15-06-2007

17/2007

Application for grant of inter-State trading licence in electricity by Visa Power Limited .

29-05-2007

29-05-2007

17/2007

Application for grant of inter-state trading licence in electricity by Visa Power Limited .

01-05-2007

01-05-2007

31/2006
in
153/2005

Review of the order dated 16.3.2006 in Petition No. 153/2005 - Grant of inter-State trading licence in electricity by
21 st Century Infrastructure (India) Pvt. Limited .

04-07-2006

09-01-2007

Pet. No.
Subject
Date of Hearing
Date of Order


131/2007(Suo-motu)

Default in payment of Unscheduled Interchanges (UI) charges for the energy drawn in excess of the drawal schedule Uttar Pradesh Power Corporation Limited.

-

05-11-2007


132/2007(Suo-motu)

Default in payment of Unscheduled Interchanges (UI) charges for the energy drawn in excess of the drawal schedule Power Development Department, Government of J & K

-

05-11-2007


117/2007

Directing the constituents to honour the power transfer limits and curb the overdrawals from the grid so that the entire NEW electricity grid is secure. Northern Regional Load Despatch Centre, New Delhi.

-

28-09-2007


71/2007

Implementation of ABT with effect from 1.1.2007 in intra-State Central Generating Station NLC-TPS I supplying power to the sole beneficiary, TNEB. Seeking intervention of the Commission for appropriate remedy for the problems encountered in UI Accounting. Neyveli Liginite Corporation Limited.

21-08-2007

01-10-2007

I.A. No.
67/2006
in
67/2003
(SUO MOTU)

Bringing generating stations of Central Public Sector Undertakings (CPSU's) supplying power to single beneficiary State under provision of Availability Based Tariff (ABT).

-

08-01-2007

145/2006

Ensuring secure and reliable operation of Southern Regional Grid by maintaining the grid frequency above 49.0 Hz.

02-02-2007

13-02-2007

15/2007
(Suo-motu)

Revision of UI Vector.

02-02-2007

12-02-2007

14/2007
(Suo-motu)

Ensuring secure and reliable operation of Regional Grid by maintaining the grid frequency above 49.0 Hz.

02-02-2007

13-02-2007

145/2006

Ensuring secure and reliable operation of Southern Regional Grid by maintaining the grid frequency above 49.0 Hz.

11-01-2007

15-01-2007

Pet. No.
Subject
Date of Hearing
Date of Order


108/2007
in114/2007
116/2007


1. Petition under Section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Tata Power Co. Ltd., Mumbai.Viswanath Sugar Ltd., Mumbai
2. Petition under Section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Ugar Sugar Works Ltd., Sangli.Tata Power Co. Ltd., Mumbai
3. Petition under Section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Shree Dhoodhaganga Krishna Sahakari Sakkere Karkhane Niyamit, Chikodi.Tata Power Co. Ltd., Mumbai

-

21-11-2007


108/2007
in 114/2007
116/2007


1. Petition under Section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Tata Power Co. Ltd., Mumbai.Viswanath Sugar Ltd., Mumbai
2. Petition under Section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Ugar Sugar Works Ltd., Sangli.Tata Power Co. Ltd., Mumbai
3. Petition under Section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Shree Dhoodhaganga Krishna Sahakari Sakkere Karkhane Niyamit, Chikodi.Tata Power Co. Ltd., Mumbai

20-11-2007

20-11-2007


91/2007

Petition under para 6.3 of the Guidelines issued by the Central Electricity Regulatory Commission vide order dated 6.2.2007 in Petition No.155/2006 (Suo Motu) for grant of permission for setting up and operation of Power Exchange. NTPC Ltd.

25-09-2007

06-11-2007

143/2006

Petition under Section 79(1) (f) of the Electricity Act, 2003 Indraprastha Power Generation Company Limited.Haryana Vidyut Prasaran Nigam Limited, Panchkula

30-10-2007

31-10-2007


108/2007
114/2007 in
116/2007

1. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004 Tata Power Trading Company Ltd. Mumbai. Vishwanath Sugars Ltd., Belgaum
2. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004 Ugar Sugar Works Ltd. Sangli. Tata Power Co. Ltd., Mumbai
3. A petition under Section 79 of the Electricity Act, 2003 read with Regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Shree Doodhaganga Krishna Sahakari Sakkare Karkhane Niyamit, Chikodi. Tata Power Co. Ltd., Mumbai

23-10-2007

29-10-2007


108/2007
114/2007 in
116/2007

1. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004 Tata Power Trading Company Ltd. Mumbai. Vishwanath Sugars Ltd., Belgaum
2. Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004 Ugar Sugar Works Ltd. Sangli. Tata Power Co. Ltd., Mumbai
3. A petition under Section 79 of the Electricity Act, 2003 read with Regulation 35 of the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004. Shree Doodhaganga Krishna Sahakari Sakkare Karkhane Niyamit, Chikodi. Tata Power Co. Ltd., Mumbai

16-10-2007

18-10-2007


107/2007

Petition for direction to U.P Power Corporation Ltd (UPPCL) for payment of compensation amount to M.P Power Trading Co. Ltd (MPTRADECO) due to retention of MP's share of power/non-supply of it from Rihand and Matatila Hydel Power Stations to MPSEB and resumption of MP's

share of power from Rihand and Matatila Hydel Power Stations. Madhya Pradesh Power Trading Company Ltd

16-10-2007

16-10-2007


85/2007
(Suo-motu)

Proposed Approach for Sharing of Charges for and losses in Inter-State Transmission System.

-

03-10-2007


96/2007

Approval of tariff for Ratnagiri Gas and Power Private Limited. Ratnagiri Gas and Power Pvt. Ltd.

18-09-2007

01-10-2007


32/2006

Recovery of energy charges for the energy supplied during the period 1.1.2000 to 30.6.2001-adjudication of disputes. NTPC Limited, New Delhi

27-09-2007

27-09-2007


116/2007

A petition under Section 79 of the Electricity Act, 2003 read with Regulation 35 of the Central Electricity Regulatory Commission (Open Acces in inter-State Transmission) Regulations, 2004.

-

26-09-2007


-

Generic Procedure on regulation of power supply to beneficiaries in case of non-payment of dues of Central Power Utilities.

-

26-09-2007


108/2007

Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004.

18-09-2007

18-09-2007


114/2007

Petition under section 79 of the Electricity Act, 2003 read with regulation 35 of the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004.

-

18-09-2007


55/2007 In
65/2005

Review Petition against the order dated 29.1.2007 of the Commission in Petition No.65/2006 of North Eastern Electric Power Corporation (NEEPCO) in the matter of additional capitalization of Assam Gas Based Power Project, Kathalguri for the year 2003-04.

-

10-09-2007


143/2006

Petition under Section 79(1) (f) of the Electricity Act, 2003.

23-08-2007

23-08-2007


9/2003

Petition under Section 13 (h) read with Section 13 (c) of the Electricity Regulatory Commissions Act, 1998-Recovery of outstanding dues on account of wheeling charges from January 2001 to July 2001 from APTRANSCO.

14-08-2007

14-08-2007


18/2007

Adoption of tariff for the supply of electricity from the Mundra Ultra Mega Power Project of Coastal Gujarat PowerLimited. Coastal Gujarat Power Limited

-

07-08-2007


30/2007

Dispute on the payment of the amounts payable for trading of power.

19-07-2007

19-07-2007


38/2007

Application for grant of permission for setting up of Power Exchange. Indian Energy Exchange Limited

10-07-2007

17-07-2007


9/2003

Petition under Section 13 (h) read with Section 13 (c) of the Electricity Regulatory Commissions Act, 1998-Recovery of outstanding dues on account of wheeling charges from January 2001 to July 2001 from APTRANSCO .

05-07-2007

05-07-2007


30/2007

Dispute on the payment of the amounts payable for trading of power

05-07-2007

05-07-2007


70/2007
in 24/2007

  1. Review of the order dated 7.3.2007 in Petition No. 24/2007. & 2. Refusal No 131 of 25.1.2007 by the Western Regional Load Despatch Centre of the open access application filed by Tata Power Trading Company Limited for transmission of 27 MW power through Eastern Regional Load Despatch Centre and Orissa State Load Despatch Centre from Nava Bharat Ventures Ltd, on the ground of "No consent from OPTCL".

05-07-2007

05-07-2007


110/2006
(Suo-motu)

Petition for `in principle` approval of the estimated project cost and financing plan of 1000 MW (gross) power project being set up by Tata Power Company Ltd. at Chola in Uttar Pradesh

05-06-2007

27-06-2007


108/2006
(Suo-motu)

Petition for `in principle ` approval of the estimated project cost and financing plan of 1000 MW (gross) power project being set up by Visa Power Ltd. in Orissa.

05-06-2007

27-06-2007


109/2006
(Suo-motu)

Petition for `in principle` acceptance of project capital cost and financing plan of 1000 MW Thermal Power Project at Chandannagar, Surguja District, Chattisgarh proposed to be set up by IFFCO Chattisgarh Power Limited.

05-06-2007

27-06-2007


85/2007
(Suo-motu)

Proposed Approach for Sharing of Charges for and Losses in Inter-State Transmission system.

-

02-07-2007

31/2001

Approval of tariff in respect of Kawas GPS for the period from 1.4.2001 to 31.3.2004.

-

21-05-2007

21/2007
in
52/2007

Approval under Section 17(3) of the Electricity Act, 2003 for transfer of ownership of switchyard associated with Faridabad Gas Power Project situated at Faridabad to NTPC.

-

14-06-2007

22/2007
in 53/2007

Approval under Section 17(3) of the Electricity Act, 2003 for transfer of ownership of switchyard associated with Rajiv Gandhi Combined Cycle Power Project situated at Kayamkulam to NTPC.

-

14-06-2007

151/2006

Petition under Section 79 of the Electricity Act, 2003 read with Regulations 12 and 13 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004.

29-05-2007

29-05-2007

52/2007

Approval under Section 17 (3) of the Electricity Act, 2003 for transfer of ownership of switchyard associated with Faridabad Gas Power Project (GPP) situated at Faridabad to NTPC.

-

17-05-2007

53/2007

Approval under Section 17 (3) of the Electricity Act, 2003 for transfer of ownership of switchyard associated with Rajiv Gandhi Combined Cycle Power Project (RGCCPP) situated at Kayamkulam to NTPC.

-

17-03-2007

9/2003

Petition under Section 13 (h) read with Section 13 (c) of the Electricity Regulatory Commissions Act, 1998-Recovery of outstanding dues on account of wheeling charges from January 2001 to July 2001 from APTRANSCO.

-

28-02-2007

15/2006

Seeking direction to Grid Corporation of Orissa Ltd., not to charge trading margin exceeding 4 paise/kWh, notified by the Commission.

28-12-2006

28-12-2006

151/2006

Petition under Section 79 of the Electricity Act, 2003 read with Regulations 12 and 13 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004.

16-01-2007

17-01-2007

112/2006

Request for certain clarifications on the tariff policy issued by the Government of India vide notification published in the Gazette dated 6th January, 2006 ("Tariff Policy");.

11-1-2007

17-01-2007

9/2003

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from January, 2001 to July, 2001.

20-12-2006

20-12-2006

151/2006

Petition under Section 79 of the Electricity Act, 2003 read with Regulations 12 and 13 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,2004.

13-02-2007

13-02-2007

143/2006

Petition under Section 79(1) (f) of the Electricity Act, 2003.

13-02-2007

13-02-2007

9/2003

Petition under Section 13(h)read with Section 13(c) of the Electricity Regulatory Commissions Act, 1998 - Recovery of outstanding dues on account of wheeling charges from 01/2001 to 07/2001 from APTRANSCO.

24-01-2007

06-02-2007

155/2006
(Suo motu)

Development of a common platform for electricity trading.

19-12-2006

18-01-2007