cerc-logo

Technical Validation - DVC

Petition No.
Subject
Date

346/MP/2020

Request for time extension in Petition No. 346/MP/2020-reg.
12-04-2024

366/MP/2023

Petition for seeking in principle approval of additional capital expenditure for setting up of the Administrative Building of the Petitioner.
18-03-2024

373/MP/2018

Request for time extension in Petition No. 373/MP/2018 - reg.
11-03-2024

196/GT/2016

Approval of tariff for Bokaro ‘A’: Thermal Power Station Unit-I (1 x 500 MW) for the tariff period 2014-19 (from COD to 31.3.2019).
11-01-2018

-

Terms and conditions of tariff for the tariff period starting from 1.4.2019- Seeking of information from Central Generating Companies, Joint Ventures Companies, Independent Power Producers and Central/Inter-State Transmission Companies whose tariff is being regulated by CERC. .
29-12-2017

386/TT/2014

Approval of tariff of Transmission & Distribution system activities of DVC network for the period from 1.4.2014 to 31.03.2019 .
21-10-2016

547/TT/2014& 386/TT/2014

Petition No. 547/TT/2014-Truing up of tariff of Transmission & Distribution system activities of DVC network for the period from 1.4.2009 to 31.03.2014 and Petition No. 386/TT/2014-Approval of tariff of Transmission & Distribution system activities of DVC network for the period from 1.4.2014 to 31.03.2019 .
20-10-2016

144/GT/2015

Approval of tariff of Mejia Thermal Power Station Extension Units 5 & 6 ( 2 x 250 MW) for the period 2014-19.
09-09-2016

349/GT/2014

Approval of tariff of Chandrapura Thermal Power Station (3 x 130 MW) for the period from 1.4.2014 to 31.03.2019.
26-08-2016

350/GT/2014

Approval of tariff of Bokaro Thermal Power Station (3 x 210 MW) for the period from 1.4.2014 to 31.03.2019.
26-08-2016

352/GT/2014

Approval of tariff of Mejia Thermal Power station Unit IV for the period from 1.4.2014 to 31.03.2019.
26-08-2016

348/GT/2014

Approval of tariff of Durgapur Thermal Power Station Unit III and IV for the period from 1.4.2014 to 31.03.2019.
26-08-2016

181/GT/2015

Truing-up of tariff of Chandrapura Thermal Power Station Unit # 7 & 8 (2 x 250 MW) for the period 2011-14.
26-08-2016

354/GT/2014

Approval of tariff of Maithon Hydel station Unit I to III for the period from 1.4.2014 to 31.03.2019.
26-08-2016

353/GT/2014

Approval of tariff of Panchet Hydel station for the period from 1.4.2014 to 31.03.2019.
26-08-2016

180/GT/2015

Approval of tariff of Chandrapura Thermal Power Station Unit # 7 & 8 (2 x 250 MW) for the period from 1.4.2014 to 31.03.2019.
26-08-2016

224/GT/2015

Approval of tariff of Raghunathpur Thermal Power Station (2 x 600 MW) Units -1 & 2 for the period from COD to 31.3.2019.
23-08-2016

471/GT/2014

Truing up of generation tariff for the period 2009-14 in respect of Durgapur Thermal Power Station Unit Nos.3 and 4.
20-06-2016

464/GT/2014 to 471/GT/2014

Truing up of generation tariff for the period 2009-14 for generating stations of DVC i.e. Mejia TPS- Unit 1 to 3, Mejia Unit-4, Bokaro TPS, Chandrapura TPS, Durgapur TPS, Panchet Hydel PS, Maithon Hydel PS, Tilaya Hydel PS.
20-06-2016

467/GT/2014

Truing-up of generation tariff for the period 2009-14 in respect of Panchet Hydel Power station Unit Nos. 1 and 2.
20-06-2016

464/GT/2014

Petition Nos. 464/GT/2014, 465/GT/2014, 466/GT/2014, 467/GT/2014 468/GT/2014, 469/GT/2014, 470/GT/2014 & 471/GT/2014 (Tariff of 2009-14).
04-04-2016

224/GT/2014

Determination of tariff for Raghunathpur Power Station Unit I (600 MW) for the period 2014-19.
29-01-2016

464/GT/2014 467/GT/2014 & 468/GT/2014

Approval of tariff for Maithon Hydel Power Station Units I-III (2X20+1x23.2 MW) for the period 2009-14.
25-08-2015

469/GT/2014

Determination of tariff in respect of Bokaro Thermal Power Station Units I-III (3X210MW) for the tariff period 2009-14.
20-08-2015

470/GT/2014

Determination of tariff in respect of Chandrapura Thermal Power Station Units I-III (3X210MW) for the tariff period 2009-14.
20-08-2015

465/GT/2014

Determination of tariff in respect of Mejia Thermal Power Station Units I-III (3X210MW) for the tariff period 2009-14.
20-08-2015

470/GT/2014

Approval of Tariff for Chandrapura Thermal Power Station units 1-3 (3x130MW) for the tariff period 2009-14.
13-05-2015

469/GT/2014

Determination of tariff in respect of Bokaro Thermal Power Station Units I-III (3X210MW) for the tariff period 2009-14.
12-05-2015

-

Prayer for Extension of time for submission of True-up Petitions for the tariff period 2009-14.
13-11-2014

66/GT/2012

Additional Information/clarification relating to petition for determination of tariff for Durgapur Steel Thermal Power Station Units I&II.
09-07-2014

219/GT/2013

Determination of tariff for Koderma Thermal Power Station Units 1&2 (2x500 MW) for the tariff period 2009-14.
31-03-2014

109/GT/2012

Petition No. 109/GT/2012: Determination of Tariff for Koderma Thermal Power Station units 1 & 2 (2x500=1000 MW) from the respective dates of their commercial operation.
29-10-2013

89/GT/2011

Petition No. 89/GT/2011: Determination of tariff in respect of Mejia Thermal Power Station Units 7&8 (2x500 MW) from the respective dates of their commercial operation.
29-10-2013

42/GT/2011

Approval of Tariff for Chandrapura Thermal Power Station units 7 & 8 (2x500=1000MW) from the respective dates of their commercial operation.
21-10-2013

11/GT/2012

Determination of tariff in respect of Durgapur steel Thermal Power Station Units 1&2 (2x500 MW) from the respective dates of their commercial operation.
21-10-2013

89/GT/2011

Determination of tariff in respect of Mejia Thermal Power Station Units 7&8 (2x500 MW) from the respective dates of their commercial operation.
09-10-2013

109/GT/2012

Determination of Tariff for Koderma Thermal Power Station units 1 & 2 (2x500=1000 MW) from the respective dates of their commercial operation.
09-10-2013

Docket No. 049/2013

Tariff petition of Parbati HE project, Stage-III for the period from 16.04.2013 (COD of IST unit) to 31.03.2014.
09-10-2013

89/GT/2011

Determination of tariff in respect of Mejia Thermal Power Station Units 7&8 (2x500 MW) from the respective dates of their commercial operation.
08-10-2013

Dock No. 11/GT/2012

Approval of tariff of Durgapur Steel Thermal Power Units I & II (2 x 500 MW) for the period from the respective dates of their Commercial Operation to 31.03.2014.
13-09-2013

11/GT/2012

Approval of tariff for Durgapur Steel Thermal Power Station Units I&II (2X500 MW) for the period from the respective dates of their Commercial Operation to 31.3.2014.
27-08-2013

Docket No. 109/GT/2012

Determination of tariff for Koderma Thermal Power Station Units 1&2 (2x500 MW) for the tariff period 2009-14.
29-05-2013

Docket No. 109/GT/2012

Determination of tariff for Koderma Thermal Power Station Units 1&2 (2x500 MW) for the tariff period 2009-14..
09-09-2013

10/RP/2013

Petition No. 10/RP/2013: Review of the order dated 8.5.2013 in Petition No. 272/2010.
16-07-2013

268/2012 to 276/2012

Determination of tariff in Petition Nos. 268/2012 to 276/2012 for 2009-14.
05-04-2013

268/GT/2012

Approval of tariff for Bokaro Thermal Power Station Units 1,2&3 (3x210 MW), Mejia Thermal Power Station 1,2&3 (3x210 MW), Mejia Thermal Power Station Unit IV, Chandrapura Thermal Power Station Unit 1to3 and Durgapur Thermal Power Station Unit 3&4 for the period 1.4.2009 to 31.3.2014.
14-02-2013

271/GT/2012

Approval of tariff for Maithon Hydel Station (2x20=40 MW + 1x23.2 MW), Panchet Hydel Station (2x40=80 MW) and Tilaya Hydel Station (2x2 MW) for the period 1.4.2009 to 31.3.2014.
13-02-2013

Docket No. 33/GT/2011

Approval of tariff of Maithon Hydel Power Station 3 Units (2 x 20 MW + 23.2 MW) for the period 1.4.2009 to 31.3.2014.
11-01-2013

Docket No. 34/GT/2011

Approval of tariff of Panchet Hydel Power Station 2 Units (2 x 40 MW) for the period 1.4.2009 to 31.3.2014.
11-01-2013

89/GT/2011

Approval of tariff for Mejia Thermal Power Station Phase-II, Unit I and II (2x500 MW) from the respective dates of their commercial operations.
07-01-2013

148/GT/2011

Approval of tariff in respect of Mejia Thermal Power Station Extn. Unit 5&6 (2x250 MW) in consideration with Additional capital expenditure from 24.9.2008 to 31.3.2009.
07-01-2013

Docket No.
31/GT/2011

Approval of tariff of Mejia Thermal Power Station Unit 1, 2, & 3 (3 x 210 MW) for the period 1.4.2009 to 31.3.2014..
07-01-2013

Docket No.
30/GT/2011

Approval of tariff of Bokaro Thermal Power Station Unit 1, 2, & 3 (3 x 210 MW) for the period 1.4.2009 to 31.3.2014. .
07-01-2013

Docket No.
25/GT/2011

Additional information relating to Approval of tariff in respect of Mejia Thermal Power Station Extension Unit 5&6 (2x250 MW) in consideration with additional capital expenditure for the tariff period 2009-14. .
11-12-2012

Docket No.
42/GT/2011

Determination of tariff in respect of Chandrapura Thermal Power Station Units 7 & 8 (2x250 MW) for the tariff period 2009-14 .
11-12-2012

Docket No.
25/GT/2011

Petition for approval of tariff in respect of Mejia Thermal Power station Extension Unit No. 5 and 6 (2X 250 MW) in consideration with Addl. Capital expenditure for the tariff period 2009-14. .
19-11-2012

Docket No.
33/GT/2011,
34/GT/2011
and
35/GT/2011

Additional information relating to petition for approval of tariff in respect of Maithon (2 x 20 MW + 1 x 23.2 MW), Panchet (2 x40 MW) and Tilaya (2 x 2 MW) Hydel Power stations for the tariff period 2009-14.
30-08-2012

Docket No.
33/GT/2011,
34/GT/2011
and
35/GT/2011

Petition for approval of tariff in respect of Maithon (2 x 20 MW + 1 x 23.2 MW), Panchet (2 x40 MW) and Tilaya (2 x 2 MW) Hydel Power stations for the tariff period 2009-14
13-08-2012

25/GT/2011

Petition for approval of tariff in respect of Mejia Thermal Power station Extension Unit No. 5 and 6 (2X 250 MW) in consideration with Addl. Capital expenditure for the tariff period 2009-14. - Dock. No. 25/GT/2011
11-06-2012

25/GT/2011

Petition for approval of tariff in respect of Mejia Thermal Power station Extension Unit No. 5 and 6 (2X 250 MW) for the tariff period 2009-14..
31-10-2011

25/GT/2011

Petition for approval of tariff in respect of Mejia Thermal Power station Extension Unit No. 5 and 6 (2X 250 MW) in consideration with Addl. Capital expenditure for the tariff period 2009-14.
20-10-2011