Pet. No. |
Petitioner. |
Subject |
Date of Hearing |
Date of Order |
70/2003 |
PGCIL |
Approval of tariff for 315 MVA, 400 kV, 3rd ICT at Biharsharif alongwith associated bays under Bihar Grid Strengthening Scheme in Eastern Region from 1.10.2003 to 31.3.2004. |
10-12-03 |
02-12-03 |
65/2003 |
PGCIL |
Review of order dated 18.7.2003 in Petition No.51/2002 in the matter of approval of tariff for 400 kV Jeypore-Gazuwaka Transmission Line along with associated bays 500 MW HVDC back-to-back station at Gazuwaka between Southern Region and Eastern Region for the period 1.4.2001 to 31.3.2004. |
04-12-03 |
18-11-03 |
67/2003
68/2003
70/2003
69/2003 |
PGCIL |
Approval of transmission tariff for 400 kV Jamshedpur-Rourkela S/C Transmission System in Eastern Region for the period from 1.4.2001 to 31.3.2004.
Approval of Transmission Tariff for LILO of 400 kV D/C Bongaigaon-Malda at Purnea along with Purnea (new) sub-station in Eastern Region for the period 1.4.2001 to 31.3.2004.
Approval of tariff for LILO of Purnea – Dalkola 132 kV S/C Line and extension at Purnea sub-station in Eastern Region for the period up to 31.3.2004.
Approval of transmission tariff for 400 kV D/C Kolhapur-Mapusa Transmission Line and associated bays for the period 1.4.2001 to 31.3.2004 in Western Region. |
06-12-03 |
- |
57/2003 |
PGCIL |
Approval of tariff for LILO of 400 kV SC Chamera-I-Kishenpur line at Chamera-II under the transmission system associated with Chamera HEP Stage-II in Northern Region from 1.8.2003 to 31.3.2004. |
18-11-03 |
07-11-03 |
8/2003 |
PGCIL |
Transmission Tariff for 400 KV Meerut-Mandola Circuit I & II and ICT II & ICT III at Meerut sub-station with associated bays in Northern Region. |
29-10-03 |
17-09-03 |
26/2002 |
PGCIL |
Petition for approval of tariff for 400 kV Ramagundam Transmission System, including ICT at Khammam and Reactor at Gazuwaka under CTP Augmentation in Southern Region for the period 1.4.2001 to 31.3.2004. |
23-10-03 |
23-09-03 |
28/2003 |
PGCIL |
Approval under Regulation-86 for transmission tariff for (i) 400 kV D/C Nathpa Jhakri-Nalagarh line with associated bays & 2 Nos.400 kV bays at Nalagarh for Kunihar and (ii) 400 kV D/C Nathpa Jhakri-Abdullapur line, ICT-I, Bus Reactor & 2 Nos.220 kV bays for Tepla (HVPNL) at Abdullapur and other associated bays under Nathpa-Jhakri Transmission System in Northern Region, for the period from 01.04.2003 to 31.03.2004 |
24-10-03 |
17-09-03 |
65/2002 |
PGCIL |
Petition for approval of tariff for 1 x 63 MVA Reactor on 400 kV Kolaghat-Rengali line at Rengali sub-station in Eastern Region for the period 1.4.2001 to 31.3.2004. |
21-10-03 |
12-12-02 |
23/2002 |
PGCIL |
Petition for approval of tariff for Jeypore-Talcher Transmission System in Eastern Region for the period 1.4.2001 to 31.3.2004. |
22-10-03 |
12-12-02 |
54/2002 |
PGCIL |
Petition for approval of tariff for the Transmission System associated with Faridabad Gas Based Combined Cycle Power Project in Northern Region for the period 1.4.2001 to 31.3.2004. |
15-10-03 |
13-12-02 |
10/2002 |
PGCIL |
Transmission Tariff for Jalandhar-Hamirpur D/C Transmission Line with associated bays in Northern Region for the period from 1.9.2001 to 31.3.2004. |
29-08-03 |
- |
45/2003 |
PGCIL |
Incentive for Eastern Region for the year 2002-2003 |
27-08-02 |
- |
44/2003 |
PGCIL |
Incentive for Southern Region for the year 2002-2003 |
27-08-02 |
- |
72/2002 |
PGCIL |
Transmission Tariff for Vindhyachal Stage II Transmission System in Western Region for 1.4.2001 to 31.3.2004. |
06-08-03 |
18-03-03 |
67/2002 |
PGCIL |
Petition for approval of tariff for Dehri-KarmnasaTransmission System in Eastern Region for the period 1.4.2001 to 31.3.2004. |
05-08-03 |
12-12-02 |
62/2002 |
PGCIL |
Transmission Tariff for Rangit Transmission System in Eastern Region for 1.4.2001 to 31.3.2004. |
06-08-03 |
12-12-02 |
53/2002 |
PGCIL |
Petition for approval of tariff for CTP augmentation in Southern Region for the period 1.4.2001 to 31.3.2004. |
06-08-03 |
- |
IA No. 43/2003 in 37/2003 |
PGCIL |
Incentive for Western Region for the year 2002-2003. |
07-08-02 |
- |
18/2002 |
PGCIL |
Petition for approval of tariff for Uri Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004. |
05-08-03 |
13-12-02 |
13/2002 |
PGCIL |
on for approval of tariff for Singrauli Transmission System in NorthePetitirn Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
6/2002 |
PGCIL |
Petition for approval of tariff for 220 kV Anta Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
8/2002 |
PGCIL |
Petition for approval of tariff for Transmission System associated with Auraiya Gas Power Project in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
20/2002 |
PGCIL |
Petition for approval of tariff for Salal Stage I Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
21/2002 |
PGCIL |
Petition for approval of tariff for Salal Stage II Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
19/2002 |
PGCIL |
Petition for approval of tariff for Chamera Stage I Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
22/2002 |
PGCIL |
Petition for approval of tariff for Bairasuil Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
05-08-03 |
13-12-02 |
39/2002 |
PGCIL |
Petition for approval of tariff for 400 kV S/C Chamera I - Kishenpur Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004. |
31-07-03 |
13-12-02 |
38/2002 |
PGCIL |
Petition for approval of tariff for Rihand Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
- |
129/2002 |
PGCIL |
Tariff for Special Energy Meters for the period from 1.9.2002 to 31.3.2004 in WR |
31-07-03 |
- |
12/2002 |
PGCIL |
Petition for approval of tariff for the Transmission System associated with Farakka (I & II) STPS in Eastern Region for the period 1.4.2001 to 31.3.2004 |
04-08-03 |
12-12-02 |
14/2002 |
PGCIL |
Petition for approval of tariff for 220 kV Tanakpur Transmission System in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
28/2002 |
PGCIL |
Petition for approval of tariff for 220 kV Kawas Transmission System in Western Region for the period 1.4.2001 to 31.3.2004 |
04-08-03 |
18-03-03 |
37/2002 |
PGCIL |
Petition for approval of tariff for ICT at Kishenpur in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
48/2002 |
PGCIL |
Petition for approval of tariff for 50 MVAR Reactor along with associated equipment at Chandrapur sub-station in Western Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
18-03-03 |
89/2001 |
PGCIL |
Petition for approval of tariff for Series Capacitors on Circuit I and II of 220 kV D/C Kishenpore – Pompore transmission line at Kishenpur sub-station in Northern Region for the period 1.4.2001 to 31.3.2004 |
31-07-03 |
13-12-02 |
15/2002 |
PGCIL |
Petition for approval of tariff for 400 kV D/C Singrauli-Vindhyachal transmission line along with (2 x 250 MW) HVDC back-to-back station at Vindhyachal in Northern Region and Western Region for the period 1.4.2001 to 31.3.2004 |
17-07-03 |
13-12-02 |
16/2002 |
PGCIL |
Petition for approval of tariff for NLC Stage II Transmission System in Southern Region for the period 1.4.2001 to 31.3.2004 |
25-06-03 |
21-02-03 |
26/2002 |
PGCIL |
Petition for approval of tariff for 400 kV Ramagundam Transmission System including ICT at Khammam and Reactor at Gazuwaka under CTP augmentation in Southern Region for the period 1.4.2001 to 31.3.2004 |
23-07-03 |
- |
46/2002 |
PGCIL |
Petition for approval of tariff for Kakrapar Transmission System in Western Region for the period 1.4.2001 to 31.3.2004 |
16-07-03 |
18-03-03 |
47/2002 |
PGCIL |
Petition for approval of tariff for 400 kV Vindhyachal Stage-I Transmission System in Western Region for the period 1.4.2001 to 31.3.2004 |
18-07-03 |
18-03-03 |
49/2002 |
PGCIL |
Petition for approval of tariff for Korba-Budhipadar Transmission System in Western Region for the period 1.4.2001 to 31.3.2004 |
18-07-03 |
18-03-03 |
51-2002 |
PGCIL |
Petition for approval of tariff for 400 kV Jeypore-Gazuwaka Transmission Line along with associated bays 500 MW HVDC back-to-back station at Gazuwaka between Southern Region and Eastern Region for the period 1.4.2001 to 31.3.2004 |
18-07-03 |
21-02-03 |
66/2002 |
PGCIL |
Petition for approval of tariff for Vindhyachal Stage I Additional Transmission System in Western Region for the period 1.4.2001 to 31.3.2004 |
17-07-03 |
18-03-03 |
27/2002 |
PGCIL |
Petition for approval of tariff for 400 kV Korba Transmission System in Western Region for the period 1.4.2001 to 31.3.2004 |
24-07-03 |
18-03-03 |
63/2002 |
PGCIL |
Petition for approval of tariff for Hathidah River Crossing Section of 220 kV Biharsharif – Begusarai Transmission Line in Eastern Region for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
12-12-02 |
52/2002 |
PGCIL |
Petition for approval of tariff for Kayamkulam Transmission System in Southern Region for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
21-02-03 |
40/2002 |
PGCIL |
Petition for approval of tariff for 400 kV D/C Kaiga-Sirsi Transmission Line along with associated bays in Southern Region for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
21-02-03 |
11/2002 |
PGCIL |
Petition for approval of tariff for Chukha Transmission System in Eastern Region for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
12-12-02 |
7/2002 |
PGCIL |
Petition for approval of tariff for Central Transmission Project A.C. Line System in Southern Region and for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
21-02-03 |
25/2002 |
PGCIL |
Approval under Regulation-86 for inclusion of UPCL in Regional Scheme for Rihand-II Transmission System in Northern Region |
09-07-03 |
03-07-03 |
IA No. 23/2003 in Pet. No. 28/2003 |
PGCIL |
Approval under Regulation-86 for transmission tariff for (i) 400 kV D/C Nathpa Jhakri-Nalagarh line with associated bays & 2 Nos.400 kV bays at Nalagarh for Kunihar and (ii) 400 kV D/C Nathpa Jhakri-Abdullapur line, ICT-I, Bus Reactor & 2 Nos.220 kV bays for Tepla (HVPNL) at Abdullapur and other associated bays under Nathpa-Jhakri Transmission System in Northern Region, for the period from 01.04.2003 to 31.03.2004 |
10-07-03 |
08-07-03 |
IA No.18/2003 in Pet. No. 124/2002 |
PGCIL |
Seeking directions in Petition No.124/2002 - Bid against Request for Proposal (RfP) document for implementation of 400 kV D/C Bina-Nagda-Dehgam Transmission Line through IPTC route |
30-06-03 |
25-06-03 |
64/2002 |
PGCIL |
Petition for approval of tariff for 50 MVA Auto Transformer at Malda sub-station in Eastern Region for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
12-12-02 |
9/2002 |
PGCIL |
Petition for approval of tariff for 400 kV D/C Ramagundam-Chandrapur Transmission System in Southern Region and Western Region for the period 1.4.2001 to 31.3.2004 |
30-06-03 |
21-02-03 |
41/2002 |
PGCIL |
Petition for approval of tariff 315 MVA ICT-III along with associated bay equipment at Nagajunsagar sub-station in Southern Region for the period 1.4.2001 to 31.3.2004 |
25-06-03 |
21-02-03 |
19/2000 |
PGCIL |
Petition for approval of tariff for Kaiga-Sirsi Transmission Line in Southern Region for the period from 1.12.1999 to 31.3.2001 |
17-06-03 |
01-05-03 |
16/2002 |
PGCIL |
Petition for approval of tariff for NLC Stage II Transmission System in Southern Region for the period 1.4.2001 to 31.3.2004 |
25-06-03 |
21-02-03 |
IA No. 57/2002 in Pet. No. 110/2002 |
PGCIL |
Approval of tariff for 315 MVA, 400/220 kV ICT –IV at Ballabhgarh in Northern Region from 1.7.2002 to 31.3.2004 |
04-06-03 |
30-05-03 |
48/2001
61/2002 |
PGCIL |
Approval of incentive based on availability of transmission system in Eastern Region for the period 1999-2000 and 2000-01 |
26-05-03 |
22-05-03 |
47/2001
1/2002 |
PGCIL |
Approval of incentive based on availability of transmission system of Western region for the year 1999-2000 and 2000-01 |
04-06-03 |
22-05-03 |
Rev. Pet. No. 145/2002 in Pet. No. 46/2000 |
PGCIL |
Review of the Commission's order dated 20.8.2002 in Petition No.46/2000 in the matter of approval of transmission tariff for Chandrapur HVDC back-to-back Project (2x500 MW) between Southern Region & Western Region |
31-03-03 |
05-03-03
10-03-03 |
Review Pet. No. 85/2002 in Pet no. 111/2000 |
PGCIL |
Review of order dated 27.03.2002 regarding Guiding Factors for preparation of RfQ and RfP documents |
28-05-03 |
03-12-02 |
42/2002 |
PGCIL |
Petition for approval of tariff for Special Energy Meters in Southern Region for the period from 1.4.2001 to 31.3.2004 |
12-06-03 |
21-02-03 |
19/2002 |
PGCIL |
Approval of transmission tariff for Kaiga Transmission system in SR |
01-05-03 |
01-05-03 |
RV 119/2002 in 89/2000 |
PGCIL |
Transmission tariff for Panki-Mainpuri LILO and associated bays at Kanpur S/S in NR |
09-04-03 |
11-03-03 |
RV 117/2002 in 9/2002 |
PGCIL |
Approval of transmission tariff for 220 kV S/C Budhipadar-Korba transmission line and associated bays in WR & ER |
04-04-03 |
07-03-03 |
IA No 67/2002 in 121/2002 |
PGCIL |
Tariff for 400 kV D/C Raipur – Rourkela line along with Raipur and Rourkela Ext. under Eastern Western inter-regional link in WR from 1.1.2003 to 31.3.2004 |
02-04-03 |
28-01-03 |
IA No.67/2002 in 121/2002 |
PGCIL |
Approval of tariff for 400KV D/C Raipur - Rourkela line along with Raipur and Rourkela extension under Eastern Western inter-regional link in Western region from 1.1.2003 31.3.2004 |
02-04-03 |
28-01-03 |
10/1999 14/2000 |
PGCIL |
Transmission Tariff for 400 KV D/C Vindhyachal-Satna and Satna-Bina line with associated bays in WR & 400 KV S/C Korba-Raipur Transmission line, LILO of Korba-Bhilai Circuit-I, Bhilai-Chandrapur Circuit-2 and 315 MVA ICT-I&II and associated bays in WR. |
18-03-03 |
16-01-03 |
81/2001 |
PGCIL |
Non-compliance of RLDC direction and violation of Grid discipline by Kahalgaon STPP. |
11-03-03 |
05-03-03 |
IA No. 64/2002 in 118/2002 |
PGCIL |
Approval of Transmission Tariff for strengthening of 220 KV Transmission System under System improvement scheme in Northern Region for the period from 1.4.2001 to 31.3.2004. |
11-03-03 |
25-02-03 |
IA No. 76/2002 in 133/2002 |
PGCIL |
Approval of tariff for LILO of 400 kV D/C Bongaigaon – Malda at Purnea sub-station at Purnea (New) in Eastern Region for the period up to 31.3.2004 |
24-02-03 |
31-01-03 |
IA No. 62/2002 in 116/2002 |
PGCIL |
Approval of tariff for Stage – I of 400 kV Thyristor controlled series compensation project (Facts Device) on Kanpur – Ballabhgarh 400 kV S/C line at Ballabhgarh in Northern Region from 1.7.2002 to 31.3.2004 |
28-03-03 |
30-01-03 |
27/2002 28/2002 46/2002 47/2002 48/2002 49/2002 66/2002 72/2002 74/2002 |
PGCIL |
Approval of Tariff for Gandhar Transmission System in WR for the period from 1.4.2001 to 31.3.2004 |
21-03-03 |
18-03-03 |
IA No. 59/2002 in 112/2002 |
PGCIL |
Approval of tariff for strengthening of Farakka – Malda transmission link and provision of additional 315 MVA transformer at Malda in Eastern Region from 1.5.2002 to 31.3.2004 |
21-03-03 |
13-03-03 |
IA No. 56/2002 in 109/2002 |
PGCIL |
Approval of tariff for Agra (Powergrid) – Agra (UPPCL) 400 KV inter-connection in Northern Region for the period up to 31.3.2004 |
07-03-03 |
21-02-03 |
RV 97/2002 in 9/1999 |
PGCIL |
Review of Commission's Order dated 03.06.2002 |
06-02-03 |
19-12-02 |
IA No. 73/2002 in No. 135/2002 |
PGCIL |
Approval of tariff for LILO of Purnia – Dalkola 132 kV S/C Line and extension at Purnia sub-station in Eastern Region for the period up to 31.3.2004 |
17-02-03 |
31-01-03 |
IA No. 75/2002 in No. 132/2002 |
PGCIL |
Approval of tariff for Talcher HVDC Terminal stations at Talcher and Kolar related with Pole II, 400 kV D/C Kolar-Hosur line along with associated bays at Kolar and Hossur and 400 kV S/C Salem-Udumalpet line along with associated bay Extensions at Salem and Udumalpet, etc under Transmission system associated with Talcher-II project (East-South interconnector-II) for the period up to 31.3.2004. |
17-02-03 |
31-01-03 |
IA No. 66/2002 in No. 120/2002 |
PGCIL |
Approval of tariff for 400 kV D/C Kolhapur-Mapusa Transmission Line in Western Region for the period up to 31.3.2004 |
17-02-03 |
28-01-03 |
114/2002 |
PGCIL |
Approval for final recovery of extra Rupee Liability due to Foreign Exchange Rate Variation for the year 2000-01 in Northern, Western, Eastern and Southern Region. |
11-02-03 |
06-02-03 |
60-2002 |
PGCIL |
Approval of incentive under Regulation-86 based on availability of transmission system of SR for the year 99-00 & 2000-01 |
28-01-03 |
22-01-03 |
75/2002 |
PGCIL |
Approval of incentive under Regulation-86 based on availability of transmission system of NR for the year 99-00 & 2000-01dt 28-1-03 |
28-01-03 |
22-01-03 |
70/2002 |
PGCIL |
Approval of tariff for one additional converter transformer (Spare) for Rihand-Dadri HVDC Bi-pole in Northern Region from 1.4.2001 to 31.3.2004 |
23-01-03 |
08-01-03 |
IA No. 68/2002 in No. 122/2002 |
PGCIL |
Approval of tariff for Talcher-Kolar HVDC line with HVDC Pole-I at Talcher & Kolar. Kolar-Madras line, LILO of Cuddapah-Bangalore S/C line, Kolar-Hoody D/C line, 4x167 MVA auto transformer, 400 KV Hossur-Salem S/C line and 2x315 auto transformer with associated bays for line and ICT etc., under Transmission system associated with Talcher-II project (from 1.11.2002 to 31.3.2004) |
21-01-03 |
08-01-03 |